Question

PART I: PERT Consider the following table: ACTIVITY      PREC. ACT.              TIME ESTIMATES     (days)       &n

PART I: PERT

Consider the following table:

ACTIVITY      PREC. ACT.              TIME ESTIMATES     (days)        

to                       tml                 tp                       te

    A                      ---                           2                      3                      4                     

    B                      A                            2                      4                      6

    C                      A                            4                      6                      8

    D                      A                            4                      5                      6

    E                       B                            6                      7                      8

    F                       D                            1                      3                      5

    G                 E, C, F                        3                      5                      7

1.   Construct a PERT network. (20 points)

[NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.]

2.   By using ES, EF, LF, LS, find the slack of each activity and clearly state the critical path. (10 points)

3.   Find the completion time ( ) and the standard deviation (σ) for the project— round off the standard deviation to the nearest hundredth: two decimal places. (20 points)

[NOTE: Sigma is only computed on the critical path.]

4.   What is the completion time at 68% and 95% confidence levels? (20 points)

5.   What is the likelihood of this project being completed in more than 20 days? (15 points)

6.   Between 16 and 18 days? (15 points)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Formula:

Expected Activity Duration using Beta Distribution / Formula = (O + (4 X M) + P)/6

Variance =Standard Deviation^2

Standard Deviation=(Pessimistic Time -Optimistic Time)/6

1 B C D E F G H I J
2 Activity Predecessor Optimistic time - O Most Likely Time - M Pessimistic Time - P Expected Activity Duration using Beta Distribution / Formula = (O + (4 X M) + P)/6 Variance Standard Deviation Activity on Critical Path - Yes or No
3 A --- 2 3 4 3 0.11 0.33 Yes
4 B A 2 4 6 4 0.44 0.67 Yes
5 C A 4 6 8 6 0.44 0.67 No
6 D A 4 5 6 5 0.11 0.33 No
7 E B 6 7 8 7 0.11 0.33 Yes
8 F D 1 3 5 3 0.44 0.67 No
9 G E,C,F 3 5 7 5 0.44 0.67 Yes
10 Total Variance of the Critical Path 1.11
11 Standard Deviation of the Critical Path 1.05

Formula:

1 B C D E F G H I J
2 Activity Predecessor Optimistic time - O Most Likely Time - M Pessimistic Time - P Expected Activity Duration using Beta Distribution / Formula = (O + (4 X M) + P)/6 Variance Standard Deviation Activity on Critical Path - Yes or No
3 A --- 2 3 4 =(D3+(4*E3)+F3)/6 =I3^2 =(F3-D3)/6 Yes
4 B A 2 4 6 =(D4+(4*E4)+F4)/6 =I4^2 =(F4-D4)/6 Yes
5 C A 4 6 8 =(D5+(4*E5)+F5)/6 =I5^2 =(F5-D5)/6 No
6 D A 4 5 6 =(D6+(4*E6)+F6)/6 =I6^2 =(F6-D6)/6 No
7 E B 6 7 8 =(D7+(4*E7)+F7)/6 =I7^2 =(F7-D7)/6 Yes
8 F D 1 3 5 =(D8+(4*E8)+F8)/6 =I8^2 =(F8-D8)/6 No
9 G E,C,F 3 5 7 =(D9+(4*E9)+F9)/6 =I9^2 =(F9-D9)/6 Yes
10 Total Variance of the Critical Path =SUM(H3+H4+H7+H9)
11 Standard Deviation of the Critical Path =SQRT(H10)

1)

Network diagram:

7 E 14 3 B 7 0 7 0 4 0 7 0 14 7 3 14 G 19 9 с 6 0 5 0 con w 5 0 14 14 A 3 19 0 3 0 3 0 3 D 8 8 F 11 3 5 3 3 3 11 3 14 6 11

2)

Legends are as stated below to find ES, EF, LS, LF and Total float of each activity

Activity Id Early Finish-Early Start + Duration Duration Early Start=Highest Early finish time of all predecessor activities

here, critical path is A-B-E-G as activities on this path have zero total float

3)

Project completion time=19 days

Standard Deviation =1.05 as shown in the excel sheet with formula

4)

Completion time at 95% confidence level

=(19-(1.96*1.05/Square root of 4)) to (19+(1.96*1.05/Square root of 4))

= (19-(1.96*1.05/2))to (19+(1.96*1.05/2))

= (19-1.03)to (19+1.03)

=17.97 to 20.03

Completion time at 68% confidence level

=(19-(0.468*1.05/Square root of 4)) to (19+(0.468*1.05/Square root of 4))

=(19-(0.468*1.05/2))to (19+(0.468*1.05/2))

= 18.754 to 19.245

5)

Project will take at least 19 days time to complete, so μ= 19 Days, Standard Deviation = 1.05

Given, X = 20 Days

Thus, Value of Z score = (X- μ)/ Standard Deviation = (20-19)/1.05 = 0.95 (Rounded up to 2 Decimal Numbers)

Thus, using Z table, The probability that the project will complete within 20 days = 82.894%

The probability that the project will take more than 20 days=(100-82.894)%=17.106%

6)

Project will take at least 19 days time to complete, so μ= 19 Days, Standard Deviation = 1.05

Given, X = 20 Days

Thus, Value of Z score = (X- μ)/ Standard Deviation = (20-19)/1.05 = 0.95 (Rounded up to 2 Decimal Numbers)

Thus, using Z table, The probability that the project will complete within 20 days = 82.894%

The probability that the project will take more than 20 days=(100-82.894)%=17.106%

Project will take at least 19 days time to complete, so μ= 19 Days, Standard Deviation = 1.05

Given, X = 16 Days

Thus, Value of Z score = (X- μ)/ Standard Deviation = (16-19)/1.05 = -2.86 (Rounded up to 2 Decimal Numbers)

Thus, using Z table, The probability that the project will complete within 16 days = 0.00212=.212%

Given, X = 18 Days

Thus, Value of Z score = (X- μ)/ Standard Deviation = (18-19)/1.05 = -0.95 (Rounded up to 2 Decimal Numbers)

Thus, using Z table, the probability that the project will complete within 18 days=.17106=17.106%

Thus, using Z table, the probability that the project will complete Between 16 and 18 days=(17.106-0.212)=16.89%

Add a comment
Know the answer?
Add Answer to:
PART I: PERT Consider the following table: ACTIVITY      PREC. ACT.              TIME ESTIMATES     (days)       &n
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • NETWORK: PERT 4 - Consider the following table: ACTIVITY PREC. ACT. TIME ESTIMATES tml - 2...

    NETWORK: PERT 4 - Consider the following table: ACTIVITY PREC. ACT. TIME ESTIMATES tml - 2 (days) tp c D, E 1) Construct a PERT network. [NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.) 2) By using ES, EF, LF, LS, find the slack of each activity and the critical path. 3) Find the completion time (x) and the standard deviation (6) for the project-...

  • activity immediate processor activity time (days) A - 6 B - 8 C A,B 5 D...

    activity immediate processor activity time (days) A - 6 B - 8 C A,B 5 D B 4 E C 7 F C,D 3 G D 6 H E,F,G 5 Given the following information for a project. SHOW ALL WORK. a) Draw the AON(Activity-On-Node) project network b) Write the estimated slack times for activities A-H c) Identify the critical path d) Determine the total completion time of the project.

  • 11. In CPM/PERT, an activity that is on the critical path A. has equal values for...

    11. In CPM/PERT, an activity that is on the critical path A. has equal values for "Latest Start" and "Earliest Start" ( LS = ES ) B. has equal values for "Latest Finish" and "Earliest Finish" ( LF = EF ) C. is used in calculating total project duration D. has slack equal to zero E. all of the above 12. In CPM/PERT, the critical path through the network A. will require the most time of any path B. will...

  • The following info is available for drawing a PERT network using AOA. *(More than one answer...

    The following info is available for drawing a PERT network using AOA. *(More than one answer may be selected)* Activity Immediate Predecessors Activity Duration (days) A -- 10 B -- 13 C A 12 D B 15 E A 13 F C 16 G D,E 10 H G,F 5 a. the critical path includes: B, D, G, and H. b. the slack on activity G is not 11 days. c. there is one critical path. d. the total duration to...

  • 2. Assume you have a project with ten activities labeled A-J, as shown. Derive the earliest...

    2. Assume you have a project with ten activities labeled A-J, as shown. Derive the earliest completion time (EF), latest completion time (LF) and slack for each of the following tasks (begin at time 0). Which tasks are on the critical path? Highlight the critical path on your network diagram [5] Activity Preceding Expected EF LF Slack Critical Event Duration Path? A 4 A 5 C A 6 A 7 E A, D 6 C, E 4 G D, E...

  • (3) Determine the critical path and critical time of the network shown below. Use the critical...

    (3) Determine the critical path and critical time of the network shown below. Use the critical path method (the table of ES, EF, etc.). (3) Determine the critical path and critical time of the network shown below. Use the critical path method (the table of ES, EF, etc.). po Problem . Example a 100 For all starting activities, ES is taken as 0. Activities 1-2, 1-3 gets ES of O. Find EF-ES +time. Activity Time ES E F LS L...

  • Activity Activity Predecessor Time (days) A -- 4 B -- 12 C A, B 15 D...

    Activity Activity Predecessor Time (days) A -- 4 B -- 12 C A, B 15 D A, B 8 E A, B 6 F C, D, E 14 G C, D, E 3 H F, G 6 The expected completion time for the project above is? 27 days 68 days 47 days 30 days The critical path for the project is? B, C, F, H B, C, F, G, H A, C, F, G A, C, E, H How much...

  • #1 #2 #3 #4 Time Estimates (in weeks) for SOM's Bus Project is given in the...

    #1 #2 #3 #4 Time Estimates (in weeks) for SOM's Bus Project is given in the following table. Activity Optimistic time Most likely time Pessimistic time A 2 4 6 B 3 5 8 Ic с 4 6 8 D 3 5 10 Please help the project management team to find the standard deviation of Activity D. keep two decimals if not exact, either round up or down is ok. For example, for 0.1346, (0.13 or 13) and (0.14 or.14)...

  • Pert project method Activity Predecessors A group 5 optimistic Most likely Pessimistic Expected Variance a m...

    Pert project method Activity Predecessors A group 5 optimistic Most likely Pessimistic Expected Variance a m b Time (t) o 2 3 2 1 B с D NWN mlm A 1 A,B 2 4 1 6 7 9 F 1 с с DE F,G 4 2 5 3 G 4 12 H 2 4 From the table above find the flowing answers. 1. Construct the project Network 2. Find the expected duration and Variance of each activity 3. Find the...

  • Based on the following table, calculate the ES, EF, LS, LF and Slack for each activity...

    Based on the following table, calculate the ES, EF, LS, LF and Slack for each activity using an expected completion time of 16 weeks. Please use the table format presented in the text to solve this problem. Please create one table with the original plan and a second table with the updates based on actual performance. What is the critical path for the original project? If the critical path changes as a result of actual progress, identify the new critical...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT