Question

Based on the following table, calculate the ES, EF, LS, LF and Slack for each activity...

  1. Based on the following table, calculate the ES, EF, LS, LF and Slack for each activity using an expected completion time of 16 weeks. Please use the table format presented in the text to solve this problem. Please create one table with the original plan and a second table with the updates based on actual performance.

What is the critical path for the original project? If the critical path changes as a result of actual progress, identify the new critical path.

Can the project be completed on time? If necessary, identify activities you would focus on to get the project back on schedule.

Activity

Estimated Time

Actual Finish Time

Immediate Predecessor(s)

A

3

       2

-

B

3

       6

-

C

4

           8

A

D

5

A,B

E

4

B

F

5

C,D,E

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Original network

Activity ES EF LS LF Slack
a 0 3 0 3 0
b 0 3 0 3 0
c 3 7 4 8 1
d 3 8 3 8 0
e 3 7 4 8 1
f 8 13 8 13 0

MOdified network

Activity ES EF LS LF Slack
a 0 2 1 3 1
b 0 6 0 6 0
c 2 10 3 11 1
d 6 11 6 11 0
e 6 10 7 11 1
f 11 16 11 16 0

Yes. The project can be completed in 16 days despite the delay. However, activities B,D and E form critical path and need to be taken care of to ensure that it completes on time.

Add a comment
Know the answer?
Add Answer to:
Based on the following table, calculate the ES, EF, LS, LF and Slack for each activity...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT