Question
#1
Time Estimates (in weeks) for SOMs Bus Project is given in the following table. Activity Optimistic time Most likely time Pe
#2
A projects critical path is CDFGI. The expected time and the standard deviation of each activity are as follows. Activity AB
#3
A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the cri
#4
A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the cri
0 0
Add a comment Improve this question Transcribed image text
Answer #1

у Activity Optimistic time Most likely time Pessimistic time 3 5 To Standard deviation of activity Ds Pessimistic 6 Optimisti3% means 214 days variances 81 standard deviation = variance 581 q 7- Scode X - mean Standard deviation 11 Q18 - 214 4 9 0.464) १[x 218) P( P/X-21, 218 - 214 १ १ । - P (7 * 0.५५) P[2< 0.५५) 046716 0.3284 - Answer : 0.3283 :

Add a comment
Know the answer?
Add Answer to:
#1 #2 #3 #4 Time Estimates (in weeks) for SOM's Bus Project is given in the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • NETWORK: PERT 4 - Consider the following table: ACTIVITY PREC. ACT. TIME ESTIMATES tml - 2...

    NETWORK: PERT 4 - Consider the following table: ACTIVITY PREC. ACT. TIME ESTIMATES tml - 2 (days) tp c D, E 1) Construct a PERT network. [NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.) 2) By using ES, EF, LF, LS, find the slack of each activity and the critical path. 3) Find the completion time (x) and the standard deviation (6) for the project-...

  • PART I: PERT Consider the following table: ACTIVITY      PREC. ACT.              TIME ESTIMATES     (days)       &n

    PART I: PERT Consider the following table: ACTIVITY      PREC. ACT.              TIME ESTIMATES     (days)         to                       tml                 tp                       te     A                      ---                           2                      3                      4                          B                      A                            2                      4                      6     C                      A                            4                      6                      8     D                      A                            4                      5                      6     E                       B                            6                      7                      8     F                       D                            1                      3                      5     G                 E, C, F                        3                      5                      7 1.   Construct a PERT network. (20 points) [NOTE: This...

  • A partially solved PERT problem is detailed in the table below. Times are given in weeks....

    A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Preceding Optimistic Time Probable Time Pessimistic Time Expected Time Variance A -- 7 9 14 1.361 B A 2 2 8 0 C A 8 12 16 0 D A 3 5 10 1.361 E B 4 6 8 0 F B 6 8 10 0 G C, F 2 3 4 0 H D 2 2 8 1.000 I H 6 8...

  • HOMEWORK ASSIGNMENT FOR PROJECT MANAGEMENT 13. An automation project has the following activities and related data Time (weeks)Crash Immed. Maximum Activity Prede- Opti- Most Cost/week Crashable...

    HOMEWORK ASSIGNMENT FOR PROJECT MANAGEMENT 13. An automation project has the following activities and related data Time (weeks)Crash Immed. Maximum Activity Prede- Opti- Most Cost/week Crashable Mean Varice cessors mistic (a) Likely (m) mistic (c (S1000) Weeks E(t) V(t) C A 5 D A 4 E B1 F B1 G C,D,E 2 6 6 HF2 12 15 3 13a. (5 points) Compute the mean and variance of each activity and record them on the table above. 13b. (5 points) Develop...

  • 16) A partially solved PERT problem is detailed in the table below. Times are given in...

    16) A partially solved PERT problem is detailed in the table below. Times are given in weeks. Optimisti Activity Preceding Time Probable Pessimistie Expected Time Time Time Variance 10 8 19 20 - 니다 4-ww0 8 16 14 1 2.79 276 G + - 5 (a) Calculate the expected time and variance for each activity. Enter these values in the appropriate columns in the table above. (b) Which activities form the critical path? (c) What is the estimated time of...

  • PERT Analysis: The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A -...

    PERT Analysis: The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 3 8 14 B - 8 8 8 C A 6 9 18 D B 6 11 17 According to the data in the above Table: What is the critical path? What is the minimum expected completion time for the project? According to the above Table, there are four activities in the project....

  • 1. The activities needed for a new project your company is undertaking are listed in the...

    1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...

  • Problem 9-14 Given the following activity times in months, determine the items listed below: Time Estimates...

    Problem 9-14 Given the following activity times in months, determine the items listed below: Time Estimates (months) Activity Activity Predecessor а т 4 12 A B 6 10 15 С 2 10 14 1 D A 4 13 E A 3 F В 3 6 18 G 2 8 12 Н С.Е.F С.Е.F 15 22 I 5 12 21 J D 20 25 K G.I 5 12 L Н.К 3 20 Expected activity times b. Variance times а. c. Earliest...

  • 5. A project has critical path activities A, B, and C. A is the predecessor of B. B is the predec...

    5. A project has critical path activities A, B, and C. A is the predecessor of B. B is the predecessor of C. The duration estimate for activity A, B and C is shown in the following table. Fill the table with mean duration, standard deviation, and variance for activities and the whole project (critical path). Determine what is the probability of completing this project within 80 days? (10 points) Activity Optimistic Pessimistic Most likely Mean Standard Variance deviation duration...

  • 123) Given (Time in weeks): Activity Optimistic Most Likely Pessimistic A 3 4 5 B 6...

    123) Given (Time in weeks): Activity Optimistic Most Likely Pessimistic A 3 4 5 B 6 7 14 C 2 3 10 D 6 9 12 E 4 5 12 F 1 3 11 G 1 2 9 H 2 5 8 I 1 4 7 Determine: (a) the critical path. ( HOW DO I DO THIS WITH OUT A PREDECESSOR?) (b) the probability that the project will be completed in 22 weeks.

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT