Question

16) A partially solved PERT problem is detailed in the table below. Times are given in weeks. Optimisti Activity Preceding Ti

0 0
Add a comment Improve this question Transcribed image text
Answer #1

(a) For each activity, find the expected mean time (u) = (a + 4m +b)/6, and Variance o = (b - a)?/3 Activity Immediate predec

(b)

Find the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF) times and Slack for each activity. Early Star

Activities A, D, H, I, J, K form the critical path

(c) Estimated time of the critical path is: 40.5 week

(d) Project variance = sum of variances of activities that form the critical path

= 4+1.36+1+2.78+2.78+1

= 12.92

Project standard deviation = square root of variance

= sqrt(12.92)

= 3.59 weeks

(e)

For target week 42,

z value = (42 - estimated time of critical path) / Standard deviation

= (42 - 40.5)/3.59

= 0.4178

P(z<0.4178) = NORMSDIST(0.4178)

= 0.662

or 66.2 %

Probability of completion of the project before week 42 = 66.2 %

Add a comment
Know the answer?
Add Answer to:
16) A partially solved PERT problem is detailed in the table below. Times are given in...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A partially solved PERT problem is detailed in the table below. Times are given in weeks....

    A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Preceding Optimistic Time Probable Time Pessimistic Time Expected Time Variance A -- 7 9 14 1.361 B A 2 2 8 0 C A 8 12 16 0 D A 3 5 10 1.361 E B 4 6 8 0 F B 6 8 10 0 G C, F 2 3 4 0 H D 2 2 8 1.000 I H 6 8...

  • The table below shows the output from a system that uses PERT for project scheduling. The...

    The table below shows the output from a system that uses PERT for project scheduling. The project involves 12 interdependent activities and all times are reported in weeks. Based on the information provided, answer the following questions: IMMEDIATE EXPECTED ACTIVITY PREDECESSORS TIME EARLIEST EARLIEST LATEST LATEST START FINISH START FINISH 16 BNS lolos 12 4 31 28 43 32 10 6 38 D, J, K (a) What is the minimum expected time required to complete the project? (b) How is...

  • PERT Analysis: The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A -...

    PERT Analysis: The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 3 8 14 B - 8 8 8 C A 6 9 18 D B 6 11 17 According to the data in the above Table: What is the critical path? What is the minimum expected completion time for the project? According to the above Table, there are four activities in the project....

  • The estimated times and immediate predecessors for the activities in a project at ABC Retinal Scanning...

    The estimated times and immediate predecessors for the activities in a project at ABC Retinal Scanning Company are given in the following table. Assume that the activity times are independent. Activity Immediate Predecessor a (time weeks) m (time weeks) b (time weeks) A - 9 10 11 B - 4 10 16 C A 9 10 11 D B 5 8 11 Calculate the expected time (mean) and variance for each activity, then answer the following: a. What is the...

  • Use a PERT network to establish the expected duration for the project described in the table...

    Use a PERT network to establish the expected duration for the project described in the table below:    (SHOW the PERT NETWORK) Activity Predecessors Duration a        m       b Exp. Duration Var. Crash Week 1 Crash Week 2 A - 3 6 9 700 100 B A 6 7 14 600 200 C A 4 6 14 400         600 D B, C 4 6 8 200                             600 E B, C 6 9 12 400 300 F C 4 6 14...

  • please help!! The estimated times and immediate predecessors for the activities in a project at Howard...

    please help!! The estimated times and immediate predecessors for the activities in a project at Howard Umrah's retinal scanning company are given in the following table. Assu that the activity times are independent. Time (weeks) Immediate Time (weeks) Immediate Activity a bPredecessor(s)Activitya bPredecessor(s) 12 10 12 8 17 This exercise contains only parts a, b, c, d, and e a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response...

  • #1 #2 #3 #4 Time Estimates (in weeks) for SOM's Bus Project is given in the...

    #1 #2 #3 #4 Time Estimates (in weeks) for SOM's Bus Project is given in the following table. Activity Optimistic time Most likely time Pessimistic time A 2 4 6 B 3 5 8 Ic с 4 6 8 D 3 5 10 Please help the project management team to find the standard deviation of Activity D. keep two decimals if not exact, either round up or down is ok. For example, for 0.1346, (0.13 or 13) and (0.14 or.14)...

  • Consider the project network information in Table 1 of Case Study A on Page 3 below....

    Consider the project network information in Table 1 of Case Study A on Page 3 below. Assuming the project starts at time zero and all activity connections are finish-to-start, draw an Activity on the Node (AON) network diagram of the project, determine the expected project completion time, state the critical activities and critical path(s). Crash the project by 1 week and state the total crash cost. (b) (18 narl Case Study A Table 1 below contains activities associated with a...

  • Consider the project network information in Table 1 of Case Study A on Page 3 below....

    Consider the project network information in Table 1 of Case Study A on Page 3 below. Assuming the project starts at time zero and all activity connections are finish-to-start, draw an Activity on the Node (AON) network diagram of the project, determine the expected project completion time, state the critical activities and critical path(s). Crash the project by 1 week and state the total crash cost. (b) (18 nar Case Study A Table 1 below contains activities associated with a...

  • Pert project method Activity Predecessors A group 5 optimistic Most likely Pessimistic Expected Variance a m...

    Pert project method Activity Predecessors A group 5 optimistic Most likely Pessimistic Expected Variance a m b Time (t) o 2 3 2 1 B с D NWN mlm A 1 A,B 2 4 1 6 7 9 F 1 с с DE F,G 4 2 5 3 G 4 12 H 2 4 From the table above find the flowing answers. 1. Construct the project Network 2. Find the expected duration and Variance of each activity 3. Find the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT