Four subsequent stages have the following capacity, respectively: 4/hr, 6/hr, 8/hr, and 10/hr. If demand id 4/hr, then which stage is the Bottleneck?
A. The stage with a capacity of 8/hr
B. The stage with a capacity of 4/hr
C. The stage with a capacity of 6/hr
D. The stage with a capacity of 10/hr
Bottleneck will be the stage which will have the lowest capacity or highest cycle time.
From given subsequent stages lowest capacity is 4 per hour.
Hence, Bottleneck will be the stage with a capacity of 4 per hour.
Correct option will be A. The stage with a capacity of 4 per hour.
Four subsequent stages have the following capacity, respectively: 4/hr, 6/hr, 8/hr, and 10/hr. If demand id...
I need help plz 6. 4-stage MIPS pipeline: It has "IF, ID-EX, MEM, WB" stages. Specify how many stalls (or bubbles) are required for the following cases. Assume that there is a forwarding logic and branch condition is determined at ID-EX stage. No delayed branch is assumed. (a) lw $1, 4($0) add $2, $1, $1 (b) lw $1, 4($0) beq $1, $2, add $3, $4, $5 X: sub $3, $3, $5 7. For problem 2 (c), how many bubbles are...
Problem 5 (10 points) Give the following diagram. Printed (Chinese) Name: THU ID: Class: 15 units/hr 17 units/hr 17 units/hr 0 0 0 What is the capacity of this system? 1553 R 4tk If the capacity of one operation could be increased in order to increase the output of the system, which operation should it be, and what amount of increase? 1 3 : 4. * to thol ) lb capado cai-ty 1
6(10%) (Pipelining) Suppose you have a system where every problem must pass through 4 pipeline stages with delays of 30ns, 60ns, 15ns, 20ns. Each stage cannot be replicated, but can be pipelined. (a) What is the minimum number of stages, from beginning to end,in a pipeline that has no load imbalance? (b) What is the clock cycle time for this case, assuming clock to q delay, setup time and hold time is 2ns for registers? 6(10%) (Pipelining) Suppose you have...
Question 8 The velocity equations valt), vb(t), vc(t), and up(t) in (km/hr) of four cars A, B, C, and D, respectively are moving along a straight line and given by, VA(T) = arctan(81) UB(l) = In(91) vo(t) = e-71 Up(l) = V8 +12 Which of these cars travelled further during the time interval (12,14] (A) Car A (B) Car B. (C) Car C (D) Car D Your answer 4. 10 Points Determine concavity of the following. Find X-values where the...
Figure: The Demand and Supply of Wheat Price (per bushel) 2 4 6 8 10 12 Quantity of wheat (thousands of bushels per period) 6a. If there were an increase in demand of 2,000 bushels at each price, the equilibrium price and quantity would be and bushels, respectively. A) $5; 5,000 B) $6; 7,000 C) $7; 7,000 D) $8; 8,000 6b. (Figure: The Demand and Supply of Wheat) If a price of $8 temporarily exists in this market: A) a...
1. Assume that individual stages of the datapath have the following latencies: IF ID EX MEM WB 250 ps 350 ps 150 ps 300 ps 200 ps Also, assume that instructions executed by the processor are broken down as follows: alu beq lw sw 45% 20% 20% 15% What is the total latency of an ?w instruction in a pipelined and non-pipelined processor? Instead of a single-cycle organization, we can use a multi-cycle organization where each instruction takes multiple cycles...
8. a) (3) Assume that initially registers $8 and $10 contain 4 and 8 respectively. If every byte in the data memory initially contains the value 6, show the contents (in decimal) of all registers and/or data memory locations modified by following pair of instructions: lui $10,0x1004 sw $8,-256($10) b) (3) Assume that initially registers $8 and $10 contain 4 and 8 respectively. If every byte in the data memory initially contains the value 6, show the contents (in decimal)...
A small manufacturing company has a demand of 800 units of its products per month. The process is completed in four stages, which produce the following average percentages of good-quality units: Stage 1 Stage 2 Stage 3 Stage 4 88% 92% 81% 95% How many units of components does it need to buy to satisfy demand? a. 701 – 950 b. 1201 – 1450 c. More than 1450 d. Less than or equal to 700 e. 951 – 1200
A company makes four products: Product A sells for $50 but needs $10 of materials; Product B sells for $75 but needs $30 of materials; Product C sells for $100 but needs $50 of materials; Product D sells for $150 but needs $75 of materials. The labor cost is $15/hr. The processing requirements for each product on each of the four machines are shown in the table. Table 6 Work Center Processing Time (min/unit) A B C D W 3...
3) (10 points total) You have the following expressions for bond demand and bond supply respectively: BD: P 200-3Q B: P 50 +2Q a) (2 points) Solve for the equilibrium quantity and price in this bond market (please show work) b) (4 points for correct and completely labeled diagram) Draw a demand and supply diagram and locate this initial point as point A. Now conditions change.... bond demand remains the same but bond supply changes and is now: BS: P-...