Question

1.)Ready Care is a specialized medical treatment care facility that has recently opened in the local...

1.)Ready Care is a specialized medical treatment care facility that has recently opened in the local Wal-Mart. Currently, they offer assessments on common ailments as they are only staffed by nurse practitioners. The organization has decided to measure its process performance in terms of processing patients in a timely manner. The data for what was deemed a standard week is shown below.

Patient 1

Patient 2

Patient 3

Patient 4

Monday

25

32

22

24

Tuesday

32

34

18

25

Wednesday

21

26

35

19

Thursday

22

17

33

27

Friday

19

27

26

21

Given the data above, what is the upper control limit (UCL) for the R chart?

2.)Given the data in Question 1, what is the lower control limit (LCL) for the R chart?

3.)Again using the data from Question 1, what is the upper control limit (UCL) for the x-bar chart?

4.)Finally, what is the lower control limit (LCL) for the x-bar chart?

5.)After the control charts have been constructed, Ready Care collected more data on a continual basis (see chart below) in order to assess their delivery process

Patient 1

Patient 2

Patient 3

Patient 4

Monday

18

19

22

24

Tuesday

35

34

37

32

Wednesday

34

34

33

36

Thursday

22

17

33

27

Friday

19

27

26

21

Given the additional data, what can be said about the process?

a.) It is capable of meeting customer expectations

b.) It is not capable of meeting customer expectations

c.) It is in control

d.) It is out of control

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Patient 1 Patient 2 Patient 3 Patient 4
Monday 25 32 22 24
Tuesday 32 34 18 25
Wednesday 21 26 35 19
Thursday 22 17 33 27
Friday 19 27 26 21
Total 119 136 134 116 Total
Average = Total /5 23.80 27.20 26.80 23.20 101.00
Range = Max observation -Min observation 13 17 17 8 55.00

Now, X -bar = 101/ 4 =25.25 , R-bar = 55/4 =13.75

Formulas to be used:

Now, Sample size n =5, For n =5 . A2 =0.577 , D3=0, D4 =2.114 where A2, D3 and D4 are X-chart and R-chart constants.

UclX = X-bar + A2*R-bar = 25.25 + 0.577*13.75 = 33.18

LCLx= X-bar - A2*R-bar= 25.25 - 0.577*13.75 = 17.32

UCLr = R-bar*D4 = 13.75*2.114 = 29.07

LCLr =R-bar*D3 = 13.75*0 = 0

Part 5 ) The process is capable of meeting customer expectations as the next sample's averages and range are within the control limits calculated above.

Patient 1 Patient 2 Patient 3 Patient 4
Monday 18 19 22 24
Tuesday 35 34 37 32
Wednesday 34 34 33 36
Thursday 22 17 33 27
Friday 19 27 26 21
Total 128 131 151 140
Average = Total /5 25.60 26.20 30.20 28.00
Range = Max observation -Min observation 17 17 15 15
Add a comment
Know the answer?
Add Answer to:
1.)Ready Care is a specialized medical treatment care facility that has recently opened in the local...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Travel Data 10. Using your travel data: a. Develop a 95% confidence interval for your mean...

    Travel Data 10. Using your travel data: a. Develop a 95% confidence interval for your mean time to work (lunch) using time in minutes. b. What assumption is necessary for you to complete part (a)? Do you feel this assumption is valid? 119 B C A 1 TO WORK Time in Day of Week Minutes 2 Date Ce 2-Sep Monday 3-Sep Tuesday 4-Sep Wednesday 5-Sep Thursday 6-Sep Friday 9-Sep Monday 10-Sep Tuesday 11-Sep Wednesday 12-Sep Thursday 13-Sep Friday 16-Sep Monday...

  • B. Bell Grove Medical Center Ms. Gene Dempsey manages the emergency care center at Bell Grove...

    B. Bell Grove Medical Center Ms. Gene Dempsey manages the emergency care center at Bell Grove Medical Center. One of her responsibilities is to have enough nurses so that incoming patients needing service can be handled promptly. It is stressful for patients to wait a long time for emergency care even when their care needs are not life threatening. Ms. Dempsey gathered the following information regarding the number of patients over the last several weeks. The center is not open...

  • 1. The service departments at Tionesta Ford Lincoln Mercury and Sheffield Motors Inc., two of the...

    1. The service departments at Tionesta Ford Lincoln Mercury and Sheffield Motors Inc., two of the four Applewood Auto Group dealerships, were both open 24 working days last month. Listed below is the number of vehicles serviced last month at the two dealerships. Construct dot plots and report summary statistics to compare the two dealerships. Tionesta Ford Lincoln Mercury Friday Saturday Thursday Wednesday Tuesday Monday 26 28 39 27 33 23 35 32 33 28 32 30 32 27 31...

  • Need some assistance with this question, please show work if applicable. Thank you! A quality analyst...

    Need some assistance with this question, please show work if applicable. Thank you! A quality analyst wants to construct a control chart for controlling the variability of a packaging process. Each day last week, he randomly selected four packages and weighed each.The data from that activity appear below. Construct a 3-sigma control chart. What is the upper control limit? (Keep two decimal places) Package 1 23 Package 2 22 21 23 Day Monday Tuesday Wednesday Thursday Friday Weight Package 3...

  • The Goodman Tire and Rubber Company periodically tests its tires for tread wear under simulated road...

    The Goodman Tire and Rubber Company periodically tests its tires for tread wear under simulated road conditions. To study and control the manufacturing process, 20 samples, each containing three radial tires, were chosen from different shifts over several days of operation, with the following results. Tread wear measurements are in hundredths of an inch. Sample Tread Wear 1 31 42 28 2 26 18 35 3 25 30 34 4 17 25 21 5 38 29 35 6 41 42...

  • Elm Street Medical Hospital has the largest emergency room in the city. Because approximately 85% of...

    Elm Street Medical Hospital has the largest emergency room in the city. Because approximately 85% of the emergency room visits in the city are handled by Elm Street Medical Hospital, the emergency room is often crowded and the staff work longer hours than advised. The hospital administrators and city officials are concerned about patient care and want to assess the level of service the emergency room is capable of providing its patients. Wait time, the time between when a patient...

  • 4) Now that Continental can detect more defects before the Silver Box is shipped, I decided...

    4) Now that Continental can detect more defects before the Silver Box is shipped, I decided process Improvements in its circuit board fabrication department would further improve quality. So, for one process they collected the following data this morning to set up a mean control chart. Since the process mean is unknown, estimate the mean and find the UCL and LCL for a 3-sigma mean control chart using this morning's samples. Sample 1 - 24, 24, 25, 22, 21 Sample...

  • PHP code for a calendar using  control structures Design Overview and Requirements As part of the...

    PHP code for a calendar using  control structures Design Overview and Requirements As part of the first submission point, you should generate a static calendar for the current month. The current month used for the header and display can be determined in your code by using the date () function. To be eligible for grading you should construct the calendar using one or more control structures nested inside a calendar php script file. An example of how the calendar may...

  • ​​​​​​​Please solve and explain steps thanks A sample of 200 ROM computer chips was selected on each of 30 consecutive d...

    ​​​​​​​Please solve and explain steps thanks A sample of 200 ROM computer chips was selected on each of 30 consecutive days, and the number of nonconforming chips on each day was as follows: The data has been given so that it can be copied into R as a vecto. #### non.conforming = c(11, 21, 27, 16, 35, 17, 4, 22, 9, 22, 30, 18, 15, 21, 20, 19, 12, 23, 11, 22, 15, 16, 12, 26, 28, 14, 11, 17,...

  • 1. A local restaurant is open 7 days a week. The owner looked at their revenue...

    1. A local restaurant is open 7 days a week. The owner looked at their revenue from a recent week and found that 4% of it came from Monday, 7% came from Tuesday, 7% came from Wednesday, 5% came from Thursday, 27% came from Friday, 33% came from Saturday, and 17% came from Sunday. What are the expected proportions of revenue for each day of the week, if there is no daily effect on revenue? Match the correct percentage to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT