The supervisor at the Precision Machine Shop wants to determine the staffing policy that minimizes total...

The supervisor at the Precision Machine Shop wants to determine the staffing policy that minimizes total operating costs. The average arrival rate at the tool​ crib, where tools are dispensed to the​ workers, is 5 machinists per hour. Each​ machinist's pay is ​$25 per hour. The supervisor can staff the crib either with a junior attendant who is paid ​$5 per hour and can process 10 arrivals per hour or with a senior attendant who is paid ​$18 per hour and can process 18 arrivals per hour. Which attendant should be​ selected?  

The _____ should be selected, with a total estimated hourly cost of $__

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Case I

arrival rate lambda = 5 per hour

Service rate = 10 per hour

The waiting time for machinist = lambda / mu ( mu-lambda)

= 5 /10 x5 = 1/10 hour = 6 min.

Hourly waiting cost = [5 x 6 /60] x25 = 12.5 per hour

Total cost = attendant's pay + waiting cost = 5+12.5 =17.5

Case II

Waiting time = 5 / 18 x( 18-5) = 0.02136 hours = 1.2820 minutes

Total waiting time per hour = 1.2820 x5 = 6.41 min

Cost of waiting = 6.41 x25 /60 =2.67

Total cost = 18+2.67 = 20.67

As the cost is less in option I, the lower paid attendant is more economical.

Attendant I should be selected with a total estimated cost of 17.5

Add a comment
Know the answer?
Add Answer to:
The supervisor at the Precision Machine Shop wants to determine the staffing policy that minimizes total...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The Ace Job Shop is made up of a production facility where machinists work. In a...

    The Ace Job Shop is made up of a production facility where machinists work. In a nearby area, the tool crib, these machinists pick up their tools from an attendant at the tool crib. The Ace Job Shop employs both the machinists and the tool crib attendants. On average 8 machinists arrive at the tool crib every hour. Each machinist is paid $18 per hour. The supervisor can staff the crib with a junior attendant who is paid $10.00/hour and...

  • This comes from the book Decision Technology: Modeling, Software and Applications by Matthew J. Liberatore &...

    This comes from the book Decision Technology: Modeling, Software and Applications by Matthew J. Liberatore & Robert L. Nydick ISBN: 0471-41712-2 The Subject is actually Systems Engineering TOOLCRIB is a production shop of a large industrial corporation that services skilled workers. Attendants dispense tools on a first-come-first serve basis to the skilled workers who need tools during an eight-hour workday. Recently, the vice president of production has been receiving complaints of excessively long waiting lines for the skilled workers. A...

  • PART I: Multiple Choice Write all answers to the following questions. No partial credit available. Consumption...

    PART I: Multiple Choice Write all answers to the following questions. No partial credit available. Consumption utility is composed of price and convenience. True or False? A firm reduces inefficiencies by making trade-offs. True or False? A firm can increase its profitability by: A. increasing costs and reducing price. B. moving away from the efficient frontier. C. increasing inefficiencies. D. reducing inefficiencies. Operations comes from the Latin word "opus," which means: A. activity. B. helping people. C. improvement. D. work....

  • Hello! Could you please write a 6 paragraph summary (5-6 sentences each paragraph) of the below?...

    Hello! Could you please write a 6 paragraph summary (5-6 sentences each paragraph) of the below? In the overview, if you could please describe the information in detail. Please have completed in 6 days if possible. Thank you! In 50 Words Or LesS .6TOC combines lean Six Sigma (LSS) and the theory of constraints (TOC) for bottom-line benefits . The method's metrics pyramids and communi- cations allow organiza- tions to retain gains and monitor benefits. · 6TOC goes beyond fac-...

  • Elroy had been with Barnes Machine Company a year since finishing a BS in industrial engineering...

    Elroy had been with Barnes Machine Company a year since finishing a BS in industrial engineering (IE). Barnes had been in business for over 50 years, but the company had only recently moved from Detroit to Gainesville, Georgia. The public reason for the move was the economics of the old facility. Privately, based on comments he had heard, Elroy believed a shift to nonunion labor was a larger motive. Elroy’s boss is the production supervisor, Mr. Hill. Because the plant...

  • Case 34 Emirates Airline Emirates Airline was one of the three Middle East carriers that were sin...

    Case 34 Emirates Airline Emirates Airline was one of the three Middle East carriers that were singled out by the largest US airlines in the report that was released on March 5, 2015. The report charged that that the flagship airline of Dubai, along with Etihad Airways and Qatar Airways, had received over $42 billion in government subsidies and tax breaks since 2004. Claiming that this gave an unfair advantage to these state-owned airlines, the US airlines demanded that the...

  • What types of organizational culture apply to J.C. Penney before and during this change in leadership?...

    What types of organizational culture apply to J.C. Penney before and during this change in leadership? CASE DESCRIPTION Leadership is the primary subject matter of the case. Secondary issues that may also be examined are corporate culture and the marketing mix of product, price, place and promotion. The difficulty level of this case is a three. It would be appropriate for junior, senior and graduate students. The case may be taught in as little as one hour or could easily...

  • How can we assess whether a project is a success or a failure? This case presents...

    How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...

  • I have this case study to solve. i want to ask which type of case study...

    I have this case study to solve. i want to ask which type of case study in this like problem, evaluation or decision? if its decision then what are the criterias and all? Stardust Petroleum Sendirian Berhad: how to inculcate the pro-active safety culture? Farzana Quoquab, Nomahaza Mahadi, Taram Satiraksa Wan Abdullah and Jihad Mohammad Coming together is a beginning; keeping together is progress; working together is success. - Henry Ford The beginning Stardust was established in 2013 as a...

  • And there was a buy-sell arrangement which laid out the conditions under which either shareholder could...

    And there was a buy-sell arrangement which laid out the conditions under which either shareholder could buy out the other. Paul knew that this offer would strengthen his financial picture…but did he really want a partner?It was going to be a long night. read the case study above and answer this question what would you do if you were Paul with regards to financing, and why? ntroductloh Paul McTaggart sat at his desk. Behind him, the computer screen flickered with...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT