What is the Multifactor productivity for the Blue Space Inc. if they have the following data?
Units produced: 25,000
Standard price: $30/unit
Labor input: 500 hours
Cost of labor: $25/hour
Cost of materials: $10,000
Cost of overhead: 2x labor cost
Multifactor Productivity= Output/Labor+Material+Overhead
VALUES
LABOR = 12500
MATERIAL = 10000
OVERHEAD = 25000
OUTPUT = 750000
PRODUCTIVITY = OUTPUT / TOTAL INPUT
PRODUCTIVITY = 750000 / (12500 + 10000 + 25000) = 15.79
What is the Multifactor productivity for the Blue Space Inc. if they have the following data?...
Compute the multifactor productivity measure for an 8 hour day in which the usable output was 920 units, produced by 6 workers who used 354 pounds of materials. Workers have an hourly wage of 19 and material cost is 3.2 per pound. Overhead is 1.6 times labor cost. The multifactor productivity (units/$) = Blank 1 (round to 4 decimal places)
QUESTION 2 3 p Compute the multifactor productivity measure for an 8 hour day in which the usable output was 630 units, produced by 5 workers who used 905 pounds of materials. Workers have an hourly wage of 17 and material cost is 2.2 per pound. Overhead is 1.5 times labor cost The multifactor productivity (units/S)- decimal places) (round to 4
please answer both questions
% (round to 2 decimal places) QUESTION 2 Compute the multifactor productivity measure for an 8 hour day in which the usable output was 653 units, produced by 7 workers who used 534 pounds of materials. Workers have an hourly wage of 19 and material cost is 1.2 per pound. Overhead is 1.5 times labor cost 3 paints The multifactor productivity (units/S) (round to 4 decimal places) QUESTION 3 3points ve A A health club has...
Problem 2-3 Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars. Assume 40-hour weeks and an hourly wage of $16. Overhead is 1.5 times weekly labor cost Material cost is $9 per pound. (Round your answers to 2 decimal places.) Workers Material (1lbs) t (units) 25,000 30,000 35,000 45,000 400 450 550 650 12 MFP (Output/Total Cost)
Compute the average multifactor productivity for this
process.
ogether with labor and material (X-ray film) inputs. The standard charge valueofte data f per unit. Overhead is charged weekly at a rate of $1,500 plus 0.5 times direct l $125 Assume a forty-hour week and an hourly wage of $16. Material cost is o Compute the average multifactor productivity for this process. b. Does a targei piu. ts. The standard charge value of the output is 94 The weekly output of...
Question Set 2. For this question set, you will calculate labor productivity and multifactor productivity, both in tons of rice produced per dollar value of inputs. A Rice Manufacturer employs 65 field workers (each working 40 hours per week at a wage of $12hr) and 18 line workers (each working 40 hours per week at a wage of $22/hr). The business has capital expenses of $17,500 per week and produces 325,000 tons of rice per week. Recently, the company decided...
Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars. Assume 40-hour weeks and an hourly wage of $16. Overhead is 1.5 times weekly labor cost. Material cost is $9 per pound. (Round your answers to 2 decimal places.) Week Output (units) 26,000 31,000 29,000 33,000 Workers Material (1bs) 400 450 490 510 WeekMFP (output/ Total Cost)
Use Excel to compute multifactor productivity for the following two weeks. Assume 40-hour weeks and an hourly wage of $16. Overhead is 1.5 times weekly labor cost. Material cost is $9 per pound. Week Output(units) Workers Material(lbs) 1 30,000 6 450 2 35,400 8 480 How much percent is the productivity increase or decrease in Week 2 compared to Week 1? An Excel file must be uploaded to indicate your computation to get the points of this question.
Question 47 5 pts Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars. Assume 40-hour weeks and an hourly wage of $12. Overhead is 2 times weekly labor cost. Material cost is $6 per pound. What is the productivity of the most productive week? (Round your answers to 2 decimal places.) Week Output (units) Workers Material (lbs) 30,000 33,000 32,000 36,000 470 550 540 560 2.49 2.23 3.23 2.17 2.99
Please answer the following question correctly please:
Problem 2-3 Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars. Assume 40-hour weeks and an hourly wage of $16. Overhead is 1.5 times weekly labor cost. Material cost is $9 per pound. (Round your answers to 2 decimal places.) Output (units) 32,000 37,000 28,000 38,000 Week Workers Material (lbs) 470 520 480 580 3 Week MFP (output /Total Cost)