Given the following information about a small project, Task     Duration         Immediate Estimates        Predecessors A      &n

Given the following information about a small project,

Task     Duration         Immediate

Estimates        Predecessors

A          2 days              None

B          5 days              A

C          4 days              B

D          9 days              A

E          4 days              B & D

F          12 days            E & C

  1. Draw a network diagram.
  2. Identify the critical path, earliest start and finish and slack for each task.
  3. Using MS Excel, produce a Gantt chart for this project.
  4. What would happen if a new estimate for task D increases its expected duration from 9 days to 11 days? Would the project take longer? Would anything else change?
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Below is the AON network for the project.

Early Start and Early Finish for a activity is calculated as follows. Early start is the earliest the activity can start. Early finish is determined by adding the duration of the activity to the early start time. Early Start of successor activities is the early finish of the predecessor activity. If there are more than one predecessor activity early start of the successor activity is the early finish of the predecessor activity which finishes the latest.

Once we calculate the early start and early finish of all the activities we can determine the time a project will take which will equal to the early finish of the last activity.

Late Start and Late Finish for a activity is calculated as follows. Late finish is the latest the activity can finish without delaying the project. Late start is determined by subtracting the duration of the activity to the late finish time. Late finish of predecessor activities is the late start of the successor activity. If there are more than one successor activity late finish of the predecessor activity is the late start of the successor activity which start the earliest.

Once the late start and late finish is calculated, we can calculate the slack for each activity and the critical path of the project. Slack is calculated as the difference between early start and late start or early finish and late finish of the particular activity. Slack is the amount of time an activity can be delayed without delaying the overall project. The critical path is the path traced by all those activities where slack is zero. In other words there can be no delay in any activities which make up the critical path without delaying the project.

Using the above logic, the early start (ES), early finish (EF), late start (LS), late finish (LF) are as shown in the below diagram.

The above details are tabulated in the below table along with slack and the critical path

The critical path is thus A-D-E-F

Below is the Gantt Chart for the project

If the expected duration for D increase from 9 to 11, the project would take longer as activity D falls on the critical path. In addition activity E will also be delayed as this activity is also part of critical path.

Add a comment
Know the answer?
Add Answer to:
Given the following information about a small project, Task     Duration         Immediate Estimates        Predecessors A      &n
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Consider the following information about a small project: b-1. Identify the critical path. A. A-D-E-F b....

    Consider the following information about a small project: b-1. Identify the critical path. A. A-D-E-F b. A-B-C-F C. A-B-E-F Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "0" wherever required.) c. Which of these activities should the project manager track most closely? A. A-B-E-F b. A-D-E-F c. A-B-C-F Problem 15.6 Task Duration Estimate (in Days) Immediate Predecessors None А B A B and D E and C Earliest...

  • Consider the following information about a small project: Task Duration Estimates ImmediatePredecessors A 2 days None...

    Consider the following information about a small project: Task Duration Estimates ImmediatePredecessors A 2 days None B 3 days A C 3 days B D 4 days A E 1 day B & D F 9 days E & C b-1. Identify the critical path. A-B-C-F A-B-E-F A-D-E-F b-2. Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "0" wherever required.) c. Which of these activities should the project...

  • Consider a project having the following six activities:                                  

    Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task 1. Draw the project network and list...

  • Consider the following project where times are in weeks. Activity Duration Immediate Predecessors A B с...

    Consider the following project where times are in weeks. Activity Duration Immediate Predecessors A B с D E F G H A.B B A с E,F 8 12 7 4 2 3 7 3 DF a) Determine the activity schedule (ES, EF, LS, and LF) as well as slack using the information from the table above (11 marks) b) Determine all the possible paths of this project and determine the shortest possible time this project can be completed? (4 marks)...

  • Problem 5: For the given activity network, if there are 35 days required to complete the...

    Problem 5: For the given activity network, if there are 35 days required to complete the project, find the following Complete the network by filling in ES, LS, EF and LF Earliest start for activities D, E, F, H, G, L, M ill. Earliest finish for activities D, E, F, H,G,L,M Latest start for activities D, E, F, H, G, LM V. Latest finish activities D, E, F.H.GLM vi. Slack/Float time for each activities D, E, F, H, G, LM...

  • Activity Duration Precedence Problem# 3 For the project information given below (wecks) information a) Draw the...

    Activity Duration Precedence Problem# 3 For the project information given below (wecks) information a) Draw the network diagram to accurately B must be after C represent the information given C must be after A 10 15 b) Determine the earliest start, earliest D must be after B E must be after C F must be after D and E G must be after F H must be after G 1 must be after F finished, latest start, latest finish for...

  • Q5: A construction project consists of activities, immediate predecessors (IPA) and duration in weeks are as...

    Q5: A construction project consists of activities, immediate predecessors (IPA) and duration in weeks are as shown in the following table. Draw the project network diagram, find the critical path and calculate the corresponding project completion time. Also, find the total float as well as the free float for each activity and the non- critical activities. (10 Marks) ТРА Duration (Weeks) Activity A B نما 4 с 14 D A 10 E F A BD BD с F.H 5 4...

  • Problem 15-8 (Algo) Based on the precedence table below, identify the critical path, earliest start and...

    Problem 15-8 (Algo) Based on the precedence table below, identify the critical path, earliest start and finish, and slack for each task. Activity Duration (Days) Immediate Predecessor none none none KUHIGT mono 00 00 ONTHOOOO D, E G, J, K b. Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "0" wherever required.) Task Earliest Start s+ Start (ES) Earliest Completion (EC) Immediate Predecessors None None None B C...

  • not the first one Stuart Entertainment sponsors rock concerts. The company is considering a contract to...

    not the first one Stuart Entertainment sponsors rock concerts. The company is considering a contract to hire a band at a cost of $65,000 per concert. Required a. What are the total band cost and the cost per person if concert attendance is 6,000, 6,500, 7000, 7,500, or 8,000? b. Is the cost of hiring the band a fixed or a variable cost? Complete this question by entering your answers in the tabs below. Required A Required B What are...

  • Answer all questions Consider a project consisting of 12 activities and their duration along with...

    please answer this problem Answer all questions Consider a project consisting of 12 activities and their duration along with precedence as follows: Activity Precedence Duration (Days) B,C D,F.H IJ 10 5 marks Questionl Analyze the critical path to determine the total duration for the completion of the project Question2: Compute slack time for each task and analyze the appropriateness of the slack time and its usage in the process [5 marks] [5 marks Question3: Determine appropriate technological solution for the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT