Question

Consider the following information about a small project:

Task Duration Estimates ImmediatePredecessors
A 2 days None
B 3 days A
C 3 days B
D 4 days A
E 1 day B & D
F 9 days E & C


b-1. Identify the critical path.

A-B-C-F
A-B-E-F
A-D-E-F

b-2. Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "0" wherever required.)



c. Which of these activities should the project manager track most closely?

A-B-C-F
A-B-E-F
A-D-E-F

Conter thewing amtn about asmal prcyec 2 day 0 3 day C days L days Fİday F days F&C b-1. Idtity the: cntkal path OA-B-C-F b-2·ldernify the eariest surt and fineれand slacKfor earl lask. {Leave no cels bank-be certain to enter0 wherever required. Task A None F C.E lask Latast Start(LSSlack E F B C.E A , D OADEF
0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
Consider the following information about a small project: Task Duration Estimates ImmediatePredecessors A 2 days None...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Consider the following information about a small project: b-1. Identify the critical path. A. A-D-E-F b....

    Consider the following information about a small project: b-1. Identify the critical path. A. A-D-E-F b. A-B-C-F C. A-B-E-F Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "0" wherever required.) c. Which of these activities should the project manager track most closely? A. A-B-E-F b. A-D-E-F c. A-B-C-F Problem 15.6 Task Duration Estimate (in Days) Immediate Predecessors None А B A B and D E and C Earliest...

  • Given the following information about a small project, Task     Duration         Immediate Estimates        Predecessors A      &n

    Given the following information about a small project, Task     Duration         Immediate Estimates        Predecessors A          2 days              None B          5 days              A C          4 days              B D          9 days              A E          4 days              B & D F          12 days            E & C Draw a network diagram. Identify the critical path, earliest start and finish and slack for each task. Using MS Excel, produce a Gantt chart for this project. What would happen if a new estimate for task D increases...

  • Problem 15-7 Consider the following table of precedence relationships for a portion of a house building...

    Problem 15-7 Consider the following table of precedence relationships for a portion of a house building project: Task Duration Estimates Immediate Predecessor(s) A Prepare Site 3 days None B Install Rough Plumbing 2 days Prepare Site C Pour Concrete Foundation 3 days Install Rough Plumbing D Concrete Curing Time 4 days Pour Concrete Foundation E Preassemble Wall Frames 6 days None F Erect Wall Frames 2 days Preassemble WF, Cure Concrete G Install Roof 1 day Erect Wall Frames H...

  • Problem 15-8 (Algo) Based on the precedence table below, identify the critical path, earliest start and...

    Problem 15-8 (Algo) Based on the precedence table below, identify the critical path, earliest start and finish, and slack for each task. Activity Duration (Days) Immediate Predecessor none none none KUHIGT mono 00 00 ONTHOOOO D, E G, J, K b. Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "0" wherever required.) Task Earliest Start s+ Start (ES) Earliest Completion (EC) Immediate Predecessors None None None B C...

  • The following information is provided for the tasks on a project. Times are in days. Task...

    The following information is provided for the tasks on a project. Times are in days. Task Time Predecessor A 12 B 21 B, C F 15 G 5 F, G H 17 [Select ] The critical path is [Select ] The time to complete this project will be The slack for task G is Select ] If the duration on task A increases by three days, how long will the project take to complete? I Select ]

  • Consider a project having the following six activities:                                  

    Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task 1. Draw the project network and list...

  • Your schedule has a critical path of tasks A-D-E-F. A team member tells you that task B, which was originally planned to take 6 days with 5 days of float, has been re-estimated to take 9 days. What ef...

    Your schedule has a critical path of tasks A-D-E-F. A team member tells you that task B, which was originally planned to take 6 days with 5 days of float, has been re-estimated to take 9 days. What effect would you expect this to have on the schedule? Select one: a. Task B would have 1 day of lag b. The project completion date would be increased by 3 days. c. Task B is now part of the critical path...

  • Question Using the following project outline for problems 33-35 Immediate Task Predecessor Task Length (Days) 6...

    Question Using the following project outline for problems 33-35 Immediate Task Predecessor Task Length (Days) 6 6 C, D 5 C, D E, F E, F 4 35) What is the slack for task C? A. 1 days B. 3 days C. 5 days D. 4 days

  • not the first one Stuart Entertainment sponsors rock concerts. The company is considering a contract to...

    not the first one Stuart Entertainment sponsors rock concerts. The company is considering a contract to hire a band at a cost of $65,000 per concert. Required a. What are the total band cost and the cost per person if concert attendance is 6,000, 6,500, 7000, 7,500, or 8,000? b. Is the cost of hiring the band a fixed or a variable cost? Complete this question by entering your answers in the tabs below. Required A Required B What are...

  • Given the information in the following table: Activity Duration Predecessor A 4 None B 6 A...

    Given the information in the following table: Activity Duration Predecessor A 4 None B 6 A C 4 A D 2 C E 4 B F 5 B, D G 3 C H 4 F, G I 2 E, H Construct the (AON) Activity on Node network diagram Find each activity’s ES, EF, LS and LS Identify all paths. Which path is the critical path? Calculate the slack for each activity. How long will it take to complete the project?

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT