Question

Question

Using the following project outline for problems 33-35 Immediate Task Predecessor Task Length (Days) 6 6 C, D 5 C, D E, F E,35) What is the slack for task C? A. 1 days B. 3 days C. 5 days D. 4 days

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Earliest time when C can be started = Time when its predecessor A ends = Day 3

Now, C and D take 6 days each and must both the complete before E starts. But, D starts on Day 4 and ends on Day 10. Hence, to end by Day 10, C must start by Day 10 - 6 = Day 4

Latest time when C must be started = Day 4

=> Slack for task C = 1 day

Add a comment
Know the answer?
Add Answer to:
Question Using the following project outline for problems 33-35 Immediate Task Predecessor Task Length (Days) 6...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT