Jobs spend less time in the system with SPT than with FCFS.

The system has more capacity with SPT than with FCFS.

Jobs spend more time in the system with SPT than with FCFS.

The system has less capacity with SPT than with FCFS.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Jobs spend more time in the system with SPT than with FCFS.

Jobs in SPT spend the longest time due to it's processing time.

Add a comment
Know the answer?
Add Answer to:
Which of the following is TRUE when comparing the shortest processing time (SPT) versus first-come-first-served (FCFS)...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • a) Using the FCFS (first come, first served) decision e for sequencing the jobs, the order...

    a) Using the FCFS (first come, first served) decision e for sequencing the jobs, the order is t Richard's Machine Shop, following jobs (below) are ready for dispatching to a work center. The processing times, date job recuived, and due dales for the jobs a ranked according lo the decision rukes given below whal sequence would the jobs b Sequence Job Date Job Processing (days) Job Received D 105 122 195 20 180 120 205 25 I times d daysloday...

  • Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is:...

    Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241 (day 241 is a work day). Job names refer to names of clients and contract numbers. Compute...

  • a) Using the FCFS​ (first come, first served​ ) decision rule for sequencing the​ jobs, the...

    a) Using the FCFS​ (first come, first served​ ) decision rule for sequencing the​ jobs, the order is​ (assume that jobs came in the order in which they are listed in the​ table): Sequence Job 1 A 2 B 3 C 4 D 5 E The average tardiness​ (job lateness) for the sequence developed using the FCFS rule​ = ___ days ​(round your response to two decimal​ places). The following jobs are waiting to be processed at the same machine...

  • ​a) Using the SPT​ (shortest processing​ time) decision rule for sequencing the​ jobs, the order is​...

    ​a) Using the SPT​ (shortest processing​ time) decision rule for sequencing the​ jobs, the order is​ (to resolve a​ tie, use the order in which the jobs were​ received): Sequence Job 1 ▼ N L M K O 2 ▼ K O L M N 3 ▼ K N L O M 4 ▼ N L M O K 5 ▼ N O K M L The total flow time for the sequence developed using the SPT rule​ = nothing...

  • Problem 15.18 E Question Help Using the FCFS (first come, first served) decision rule for sequencing...

    Problem 15.18 E Question Help Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: The following jobs are waiting to be prooessed at Rick Sclano's machine center. Solanos machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241 (day 241 is a work day). Job names refer to names of...

  • Five jobs are ready for processing at time zero through a workstation. The details regarding the...

    Five jobs are ready for processing at time zero through a workstation. The details regarding the processing time and the due date of completion are provided in the following table. Job Processing Time (days) Days Due from Today A6 C 5 Using the shortest processing time (SPT) rule, it can be concluded that the average lateness for the five jobs is: O a. more than -6 but less than or equal to -2 days. O b. more than -2 but...

  • Five jobs are ready for processing at time zero through a workstation. The details of the...

    Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table. Job Processing Time (days) Due Date A 8 12 B 4 9 C 3 6 D 7 7 E 5 20 Using the shortest processing time (SPT) rule, it can be concluded that the average flow time for these five jobs is _____. a. more than 14 but less than...

  • The following table contains information concerning four jobs that are awaiting processing at a work center....

    The following table contains information concerning four jobs that are awaiting processing at a work center. Job Job Time (Days) Due Date (Days) A 14 20 B 10 16 C 7 15 D 6 17 a. Sequence the jobs using (1) First come, first served, (2) Shortest processing time, (3) Earliest due date, and (4) Critical ratio. Assume the list is by order of arrival. Sequence for First come, first served   (Click to select)   A-B-C-D   D-C-B-A   C-B-D-A   A-C-D-B Sequence for Shortest processing time   (Click...

  • The following table contains information regarding jobs that are to be scheduled through one machine. Assume...

    The following table contains information regarding jobs that are to be scheduled through one machine. Assume jobs are listed in order of arrival (i.e., A, then B, then C, etc.). JOB PROCESSING TIME (DAYS) DUE DATE     A 7 20     B 15 21     C 1 16     D 12 17     E 11 15     F 4 6     G 5 12 Round your answers to 1 decimal place. a. What is the first-come, first-served (FCFS) schedule? b. What is the shortest operating time...

  • java  Operating System Scheduler Two scheduling strategies for an operating system scheduler are first come first serve...

    java  Operating System Scheduler Two scheduling strategies for an operating system scheduler are first come first serve (FCFS) and fixed priority pre-emptive scheduling (FPPS). Since queues operate on a first come first serve basis, FCFS is implemented using a queue. Similarly, FPPS is implemented using a priority queue. The operating system scheduler simulation is already provided for you. To use it you simply need to modify the main method to run the simulator using either the LinkedListQueue or the PriorityQueue. Run...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT