Construction of the cattery could be distilled to eight distinct
steps, from the official groundbreaking ceremony to the cutting of
the litterbox ribbon. The activities, their durations and
predecessors are shown in the table below. Use this scenario to
answer the following question(s).
Activity | Predecessors | Time (weeks) |
A | -- | 10 |
B | A | 8 |
C | A | 7 |
D | C | 11 |
E | D | 12 |
F | B | 11 |
G | E, F | 6 |
H | E, F | 9 |
Refer to the scenario above. Which of these activities has the
least slack?
Slack represents the amount of time a task or activity can be delayed without affecting the project deadline.
Slack = Smallest of {Late Finish - Early finish} and {Late Start -Early start}
Let us now look at the precedence diagram for the above chart:
Results:
Slacks of Activity A,C,D,E, and H has a slack '0'
The critical path has zero slack. Hence, all the activities A,C,D,E and H lie on Critical path (as shown in red line in precedence diagram)
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony...
Job Saint has laid out the major steps and eight activities to complete the wing assembly for an experimental air craft. These activities have been labeled A to H in the following table, which also shows their estimated completion time (in weeks) and immediate predecessors. Activity Immediate Predecessors a m b A --------- 1 2 3 B -------- 2 3 4 C A 4 5 6 D B 8 9 10 E C ...
Module 5 Assisted Problems M5_A1. A farm owner is going to erect a maintenance building with a connecting electrical generator and water tank. The activities, activity descriptions, and estimated durations are given in the following table IMMEDIATE TIME ACTIVITY ACTIVITY DESCRIPTION (WEEKS) PREDECESSORS A Excavate 2 Erect building Install generator A 6 C A 4 Install tank A 2 Install maintenance equipment B 4 E Connect generator and tank to building Paint finish В, С, D P 5 3 Check...
A construction company has a project proposal, which takes 10 activities as follows: Activity Predecessors Activity Duration Time (In DAYS ) Early Start (ES) (In DAYS ) Early Finish (EF) (In DAYS ) Late Start (LS) (In DAYS ) Late Finish (LF) (In DAYS ) SLACK (In DAYS ) A - 14 B - 13 C A 11 D A 15 E B 14 F B 11 G D, E 13 H F 15 J C 12 K G,H 11...
Scenario: Your organisation, ABC construction group has made a winning bid to construct a new manufacturing plant. The client expects the plant to be functional within a year. You are assigned as the Project Manager to ensure that the whole project stays on schedule. The two important conditions as per the client contract are:- ABC construction group will incur a penalty if the work is not completed by the deadline of 47 weeks from now. ABC construction group will be...
QUESTION 9 Consider the following project; for which activities is it possible that the slack can be greater than zero? Activity Immediate Predecessors B, E a. Only activities B or E could have slack, but they could not both have slack. Ob. Only activities B or C could have slack, but they could not both have slack. Oc. It is possible for any or all activities in this project to have slack. Od. It is possible for either all three...
A Question 11 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) 2 B 3 C B D А E A.C 1 F DE 3 с 3 2 6 G Determine the amount of slack time for Activity E: a. O weeks b. 1 week C. 2 weeks O d. 3 weeks Question 12 Assume that activity A has the following times: Early start time...
2. Can the project be completed before construction can begin, which is scheduled 40 weeks later? a. Yes, because the project duration time is 39 weeks. b. No, because the project duration time is 41 weeks. c. No, because the project duration time is 42 weeks. d. Yes, because the project duration time is 40 weeks. 3. Which activities can be delayed without delaying the projection completion time? a. B, D and F b. B, D and G c. A,...
Use a PERT network to establish the expected duration for the project described in the table below: (SHOW the PERT NETWORK) Activity Predecessors Duration a m b Exp. Duration Var. Crash Week 1 Crash Week 2 A - 3 6 9 700 100 B A 6 7 14 600 200 C A 4 6 14 400 600 D B, C 4 6 8 200 600 E B, C 6 9 12 400 300 F C 4 6 14...
please answer from a until i with the solving steps CHAPTER 13 / Developing and implementing Effective Accounting Information Systems 431 14 FIGURE 13-11 PERT network diagram for a systems implementation project. 13-19. Do you understand PERT charts? Refer back to Figure 13-11 and answer the following questions: a. Which activity or activities must be completed before activity C can begin? b. Which activity or activities must be completed before activity G can begin? c. Which activity or activities must...
A small software development project has eight major activities. The times are estimated and provided in the table below: Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessor(s) A 3 4 5 -- B 5 7 9 -- C 2 3 10 A D 2 5 8 B E 1 7 7 B F 3 5 7 C, D G 7 8 9 D, E H 2 6 10 F Answer the following questions based on above table 1-2...