Question

A tool used to monitor past project schedule performance and current performance, and to estimate future...

A tool used to monitor past project schedule performance and current performance, and

to estimate future schedule trends is a simple line chart known as a

1. Project control chart.

2. Gantt chart.

3. PERT chart.

4. Network diagram.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1. A. Project control chart

A project control chart allows the organization the ability to measure their current performance to the past based on centralized values and control limits which tells if the processes (performance in this case) is in control(optimal and acceptable)

#Please rate the answer positively.

Add a comment
Know the answer?
Add Answer to:
A tool used to monitor past project schedule performance and current performance, and to estimate future...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1. Compare the three popular scheduling tools (1) milestone chart, (2) Gantt chart, and (3) PERT/CPM...

    1. Compare the three popular scheduling tools (1) milestone chart, (2) Gantt chart, and (3) PERT/CPM network diagram regarding their strengths, weaknesses, and limitations. 2. How does modern information technology affect managerial power and leadership style? 3. How do you overcome team member resistance to accept or use a new project management tool, such as following a new design review process or using a new method for reporting progress or changes?

  • Part 2 Remember the old saying, “A project plan is not a schedule until resources are...

    Part 2 Remember the old saying, “A project plan is not a schedule until resources are committed.” This exercise illustrates this sometime subtle, but important point. Using your files from Part 1, input resources and their costs if you have not already done so. All information is found in Tables A2.1 and A2.2. Prepare a memo that addresses the following questions: 1. Which if any of the resources are overallocated? 2. Assume that the project is time constrained and try...

  • Question 2 XYZ Industrial Machines has initiated a large client project to design, manufacture and instal a spoke plastics forming machine at a local manufacturing site. At this pre-project ph...

    Question 2 XYZ Industrial Machines has initiated a large client project to design, manufacture and instal a spoke plastics forming machine at a local manufacturing site. At this pre-project phase, it has sembled a project planning team and is undertaking discussions with the client to produce a mgheve pct plan. A range of key tasks have been identified and a logical network diagram for high-level the project has been developed. Project task information is provided in the following table (Table...

  • 1 In regard to Project Work, which activity refers to “reviewing the progress and capturing project...

    1 In regard to Project Work, which activity refers to “reviewing the progress and capturing project performance data with reference to the project plan, developing performance measures, and communicating performance information?” a. controlling b. monitoring c. executing d. managing 3 Which of the following formulas represents the schedule performance index (SPI)? a. EV/PV b. EV PV c. EV AC d. EV/AC 4 If your sponsor asks for an estimate as to how much more money your team needs to complete...

  • Question 2 XYZ Industrial Machines has initiated a large client project to design, manufacture and instal...

    Question 2 XYZ Industrial Machines has initiated a large client project to design, manufacture and instal a spoke plastics forming machine at a local manufacturing site. At this pre-project phase, it has sembled a project planning team and is undertaking discussions with the client to produce a mgheve pct plan. A range of key tasks have been identified and a logical network diagram for high-level the project has been developed. Project task information is provided in the following table (Table...

  • 1. Calculate total time required to complete each path. Determine the Critical Path(s). Complete the table...

    1. Calculate total time required to complete each path. Determine the Critical Path(s). Complete the table by indicating the Critical Path (CP), the amount of slack and whether the task is a milestone. Task       Predecessors     Duration              CP (Yes/No)?        Slack (Amount)?   Milestone? PROJECT 2 A2 - 1    B2 A2    2 C2 A2 2 D2 B2, C2 3 E2 D2 2 F2 D2 3 G2 E2,F2 2 2. Draw a PERT (Network) chart for PROJECT 2. 3. Draw a...

  • Microsoft Project Assignment Description A system development project has been defined to contain the following list of...

    Microsoft Project Assignment Description A system development project has been defined to contain the following list of activities along with their estimated times for completion. The project will start on 5/1/2019. Project Data Provided: Activity ID Activity Name Days Predecessors Optimistic(O) Realistic(R) Pessimistic(P) 1 Gather Requirement 1 2 3 2 Analyze processes 1 2 6 1 3 Define DFDs 0.5 1 1.5 2 4 Design Processes 2 7 12 2 5 Design database 4 7 22 3 6 Design UI...

  • 5-9 answer only, 10 please tell me how to get the answer. mal limits (keep three...

    5-9 answer only, 10 please tell me how to get the answer. mal limits (keep three deci 5 What are the upper and lower control chart limits using 3-sigma I places if necessary and select the closest one) (d) (6.583, 33.416] () [17,23] (d) I6.583, 33.41 (o) [o.o96, 0.105) (e) (0.037,0.163] (b) 10.099, 0.101) 6. Is the process in control? (a) Yes (b) No 7. If the parking office didn't count how many vehicle every day, is the process s...

  • Develop a 4 part project plan, using as your focus a work-related project you are doing...

    Develop a 4 part project plan, using as your focus a work-related project you are doing now or will be doing in the future. Part 1 Create a Service Level Agreement which includes which includes: Project Description, Purpose, and Objectives: Part 2 Using a Gantt chart, construct a project schedule. Part 3 describe the project budget key success factors Part 4Create a risk management and quality management plan,

  • Module Three covers refining your project schedule and fine-tuning resources. Table 1-1: Project ...

    Table 1.1 Module Three covers refining your project schedule and fine-tuning resources. Table 1-1: Project Management Process Group and Knowledge Area Mapping (PMBOK Guide® on page 556) provides you with a very specific guideline concerning what task is due for each knowledge area throughout the five projec management process groups. As you can determine from Table 1-1, a large majority of the tasks are complete during the planning process group Describe and explain how sound industry standards or best practices...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT