Question

1. Calculate total time required to complete each path. Determine the Critical Path(s). Complete the table...

1. Calculate total time required to complete each path. Determine the Critical Path(s). Complete the table by indicating the Critical

Path (CP), the amount of slack and whether the task is a milestone.

Task       Predecessors     Duration              CP (Yes/No)?        Slack (Amount)?   Milestone?

PROJECT 2

A2 - 1   

B2 A2    2

C2 A2 2

D2 B2, C2 3

E2 D2 2

F2 D2 3

G2 E2,F2 2

2. Draw a PERT (Network) chart for PROJECT 2.

3. Draw a GANTT chart for PROJECT 2.

4. Schedule PROJECT 2 on a 5-day work week, indicating the tasks and slack available.

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Data Immediate Predecessors (1 per column)
Activity Time Pred 1 Pred 2
A2 1
B2 2 A2
C2 2 A2
D2 3 B2 C2
E2 2 D2
F2 3 D2
G2 2 E2 F2
Results
Activity Early Start Early Finish Late Start Late Finish Slack
A2 0 1 0 1 0
B2 1 3 1 3 0
C2 1 3 1 3 0
D2 3 6 3 6 0
E2 6 8 7 9 1
F2 6 9 6 9 0
G2 9 11 9 11 0
Project 11

The bold letters Slack values are in the critical path

The PERT chart

The Gantt Chart is shown below

Please rate me

Thanks

Add a comment
Know the answer?
Add Answer to:
1. Calculate total time required to complete each path. Determine the Critical Path(s). Complete the table...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT