1. Calculate total time required to complete each path. Determine the Critical Path(s). Complete the table by indicating the Critical
Path (CP), the amount of slack and whether the task is a milestone.
Task Predecessors Duration CP (Yes/No)? Slack (Amount)? Milestone?
PROJECT 2
A2 - 1
B2 A2 2
C2 A2 2
D2 B2, C2 3
E2 D2 2
F2 D2 3
G2 E2,F2 2
2. Draw a PERT (Network) chart for PROJECT 2.
3. Draw a GANTT chart for PROJECT 2.
4. Schedule PROJECT 2 on a 5-day work week, indicating the tasks and slack available.
Data | Immediate Predecessors (1 per column) | ||
Activity | Time | Pred 1 | Pred 2 |
A2 | 1 | ||
B2 | 2 | A2 | |
C2 | 2 | A2 | |
D2 | 3 | B2 | C2 |
E2 | 2 | D2 | |
F2 | 3 | D2 | |
G2 | 2 | E2 | F2 |
Results | |||||
Activity | Early Start | Early Finish | Late Start | Late Finish | Slack |
A2 | 0 | 1 | 0 | 1 | 0 |
B2 | 1 | 3 | 1 | 3 | 0 |
C2 | 1 | 3 | 1 | 3 | 0 |
D2 | 3 | 6 | 3 | 6 | 0 |
E2 | 6 | 8 | 7 | 9 | 1 |
F2 | 6 | 9 | 6 | 9 | 0 |
G2 | 9 | 11 | 9 | 11 | 0 |
Project | 11 |
The bold letters Slack values are in the critical path
The PERT chart
The Gantt Chart is shown below
Please rate me
Thanks
1. Calculate total time required to complete each path. Determine the Critical Path(s). Complete the table...
Question on Project 2, Steps. Help. Thanks Provide ALL possible paths for the completion of the PROJECT 1. Calculate total time required to complete each path. Determine the Critical Path(s). Complete the table by indicating the Critical Path (CP), the amount of slack and whether the task is a milestone. Task Predecessors Duration CP (Yes/No)? Slack (Amount)? Milestone? PROJECT 1 A1 A1, B1 NNNWNN D1, F1 PROJECT 2 A2 B2 A2 B2,C2 NWNWNN D2 E2, F2
Microsoft Project Assignment Description A system development project has been defined to contain the following list of activities along with their estimated times for completion. The project will start on 5/1/2019. Project Data Provided: Activity ID Activity Name Days Predecessors Optimistic(O) Realistic(R) Pessimistic(P) 1 Gather Requirement 1 2 3 2 Analyze processes 1 2 6 1 3 Define DFDs 0.5 1 1.5 2 4 Design Processes 2 7 12 2 5 Design database 4 7 22 3 6 Design UI...
question 3.12 Chapter 3 Project Management 91 Table for 3.8 Time Activity Immediate Code Description in hours) Predecesur Planning Find location determine resource requirements Purchasing Requisition of lumber and sand Excavation Planning Dig and grade Sawing Planning Saw lumber inte appropriate sizes Placement Purchasing Position lumber in comect locations Sawing. c om Assembly Nail lamber together Placement Tafill Put sand in and under the equipment Ambly Outfill Put dirt a nd the equipment Assembly Decoration Put grass all over the...
Given the following Project Activities and Precedence Relations table; determine the Critical Path, and the minimum Project Duration. Create the Gantt Chart for the project represented in the table. Project Activities and Precedence Relations ACTIVITY DURATION PRECEDED BY: A 3 B 2 A C 2 D 1 E 1 B F G 2 1 D D H 4 BD 2 J J 1 4 K F L 3 G M N 3 3 IJ H 0 4 HKL MNO Р...
. Construct a Gantt chart and project network for the following set of activities, compute the length of each path in the network, and indicate the critical path: Activity Activity Predecessor Time (months) 1 ___ 4 2 ___ 7 3 1 8 4 1 3 5 2 9 6 3 5 7 3 2 8 4,5,6 6 9 2 5
Given the following Project Activities and Precedence Relations table; determine the Critical Path, and the minimum Project Duration. Create the Gantt Chart for the project represented in the table. Project Activities and Precedence Relations ACTIVITY DURATION PRECEDED BY: А 3 B 2 A C 2 1 D E 1 B F 2 1 D D G H 4 2 BD E J 1 E F 4 K L 3 G M N 3 3 H 0 4 HKL P MNO...
(3) Determine the critical path and critical time of the network shown below. Use the critical path method (the table of ES, EF, etc.). (3) Determine the critical path and critical time of the network shown below. Use the critical path method (the table of ES, EF, etc.). po Problem . Example a 100 For all starting activities, ES is taken as 0. Activities 1-2, 1-3 gets ES of O. Find EF-ES +time. Activity Time ES E F LS L...
The software developing firm, Flow Associates, is rolling out the new software. They are calling a meeting of the potential customers to demonstrate the new software. To setup the meeting requires several tasks to be performed in a designated time period. Based on the management briefing, the system analyst came up with the following paragraph. First reserve the meeting room. Then order the marketing material and brief the managers. After the briefing send put the customer emails and burn sample...
5-9 answer only, 10 please tell me how to get the answer. mal limits (keep three deci 5 What are the upper and lower control chart limits using 3-sigma I places if necessary and select the closest one) (d) (6.583, 33.416] () [17,23] (d) I6.583, 33.41 (o) [o.o96, 0.105) (e) (0.037,0.163] (b) 10.099, 0.101) 6. Is the process in control? (a) Yes (b) No 7. If the parking office didn't count how many vehicle every day, is the process s...
Scenario Operations managers use many techniques to solve problems. Some of these techniques are graphical and can be solved using software tools and programs. Before you start this activity, review the Excel for Operations Management Software page and download Microsoft Excel and the Excel for OM plugin. You will use these tools to solve real-life problems encountered by operations managers. How many times have you waited, not so patiently in the departure area, for your aircraft to be serviced before...