Which of the following is a tool or technique for the Develop Project Team process?
A. |
Organizational charts |
|
B. |
Colocation |
|
C. |
Acquisition |
|
D. |
Conflict management |
Correct answer: (B) “Colocation”
Reason:
For developing a project team
process different tools and techniques are utilized for making the
process better. The tools and techniques results to improve on
categories like interpersonal skills, team-building, training,
ground rules, colocation, personnel assessment tools, and on
recognition or rewards. For developing the project team process, it
is required to do work on the above categories for making the
organizational performances to reach an esteemed height. It
motivates and boosts the team to obtain a productive outcome.
Therefore; apart from “Colocation”, the remaining tools and
techniques are the part of the different processes of human
resource management.
Which of the following is a tool or technique for the Develop Project Team process? A....
QUESTION 8 An automated tool, project records, performance indicators, data bases, and financials are examples of items in Organizational process assets O Project management information systems O Project management planning approaches O The tools and techniques for project plan development QUESTION 8 An automated tool, project records, performance indicators, data bases, and financials are examples of items in Organizational process assets O Project management information systems O Project management planning approaches O The tools and techniques for project plan development
Present and discuss an example of a conflict between team members of a project or team, and which strategy or technique would you use to mediate and resolve conflicts without risking the end result of the project. One page essay.
A) We require you to describe how you would use project management tools to develop and implement a project plan. Discuss at least 3 tools from below: project management software Gantt and bar charts critical path method (CPM) Program Evaluation Review Technique charts (PERT) cost schedule control system life cycle cost analysis logistics support analysis spreadsheets technical resources B) Whilst completing your project plan, ensure you include the following: deliverables work breakdown budget and allocation of resources timelines risk management...
Project Management nstute 3FOLD Education Centre ACTIVITY No. 9.4 Conflict Management Conflict Resolution Technique Scenario A team member is not accepting a mistake, however there is a clear factual evidence of him making the mistake A team member has raised a trivial issue in the project team meeting A major incident has caused severe conflict among multiple project team members. A new project team member has made an unintentional error which was quickly rectified. Project Management nstute 3FOLD Education Centre...
1)A “Pure Project” organizational structure means one in which: a) The team members often feel they have too many bosses. b) A self-contained team of different specialists work together full-time on a single project. c) A project is housed within one functional division within a company. d) The X-bar and R-Bar charts are always in complete control. 2)Which of the following is an essential element of lean production? a)Waste reduction b)Multiple suppliers c)Safety stock increases d)Push production system 3)Lean Production...
1 You are project manager in a global project with a team consisting of people from various countries. What can you try to prevent misunderstandings due to cross-cultural differences? a Use all communication methods available that are suitable for the team and follow up in writing when communicating verbally. Remember that cultural and individual diversity may help project teams solving unforeseen problems during the course of the project. b When you are about to form a team for your project,...
What is the first step in developing the project scope management plan? a. Develop a project scope statement b. Develop a cost management plan c. Think about what you, as a project manager, would like to do d. Think about what the team would like to do.
Discuss the tradeoffs between the three objectives in Project management. How do these tradeoffs depend on the life cycle of the project? Identify some multicultural factors requiring special consideration in projects and project managers. Discuss the advantages and disadvantages of housing projects within each of the three major organizational forms: functional, pure project or matrix organization. Explain the effects of the organizational form on coordination and interaction both within the project team and between the team and the rest of...
Someone on your team is skeptical that the project is following the project's original requirements. Which document will you refer to in order to convince him/her that the project is indeed following the original requirements? a. Project Management Plan b. Project Scope Statement c. Project Charter d. Work Breakdown Structure
5. You are taking over a project that is currently in the planning stage. The previous project manager worked with the team to finalize the process of defining activities, and you joined the team at the end of this process. The next process requires the determination and documentation of the relationships among project activities. Of the following, which is a tool and technique used in this process? a. Schedule Baseline b. Dependency Determination c. Activity List d. Schedule Compression You...