Question

What is the first step in developing the project scope management plan? a. Develop a project...

What is the first step in developing the project scope management plan?

a.

Develop a project scope statement

b.

Develop a cost management plan

c.

Think about what you, as a project manager, would like to do

d.

Think about what the team would like to do.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The correct option is A. Develop a project scope statement.

Do give a positive rating if you think this answer helped

Add a comment
Know the answer?
Add Answer to:
What is the first step in developing the project scope management plan? a. Develop a project...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT