Question

Someone on your team is skeptical that the project is following the project's original requirements. Which...

Someone on your team is skeptical that the project is following the project's original requirements. Which document will you refer to in order to convince him/her that the project is indeed following the original requirements?

a. Project Management Plan

b. Project Scope Statement

c. Project Charter

d. Work Breakdown Structure

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The document you will refer to in order to convince him/her that the project is indeed following the original requirements:-

a) Project Management Plan

Add a comment
Know the answer?
Add Answer to:
Someone on your team is skeptical that the project is following the project's original requirements. Which...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question #12 On agile projects, the scope definition begins with: A-Requirements B-large chunks of work, or...

    Question #12 On agile projects, the scope definition begins with: A-Requirements B-large chunks of work, or features C-work packages D: stories and personas Question# 13 Which of the following is an advantage associated with managing projects in a functional organization? A-Traditional department barriers are reduced. B-Combines task focus with technical capability. C- Rapid communication between the various functions working on the project. D-Rapid communication between the various functions working on the project. Question #14 A project communications plan generally includes...

  • 1 Which of the following is true regarding the code of accounts? a It allows one...

    1 Which of the following is true regarding the code of accounts? a It allows one to easily identify the breakdown level of the item in the resource structure. b It describes the coding structure used by the performing organization to report financial information in its general ledger. c It is the collection of unique identifiers generally assigned to WBS items. d It defines ethical behavior in the project and the responsibilities to the customer and the profession. 2 You...

  • 9. A project manager spent some days to create a multi-page document, which he called project...

    9. A project manager spent some days to create a multi-page document, which he called project charter. The document should have been issued by the project sponsor.The sponsor found the document outsized and asked for a condensed document. Which of the following is usually not an element of the project charter? a. The authority level of the project manager b. Detailed control account and work package descriptions C. The business need that the project was undertaken to address d. High-level...

  • Which of the following is NOT an element of the project master plan (i.e., project charter)?...

    Which of the following is NOT an element of the project master plan (i.e., project charter)? A. schedules B. PMBOK C. resource requirements D. personnel E. potential risks What should the results of the project launch meeting include? A. finalizing the project team B. finalizing the project’s schedule C. finalizing the project’s budget D. the project’s scope is understood E. selecting the project sponsor Which of the following is NOT a characteristic of effective project team members? A. They are...

  • The evaluation team should be made up of: a. representatives from potential contractors. b. several individuals...

    The evaluation team should be made up of: a. representatives from potential contractors. b. several individuals from different depar ackgrounds and from different departments in the organization with various viewpoints and different c. Several of the stakeholders of the project from the community. d. one person from the company. The project charter helps the team to: a. set the evaluation criteria to select the project. b. decide which contractor to select to work on a project. c. develop a detailed...

  • I have this assignment that I need help with, I turned it in but I got...

    I have this assignment that I need help with, I turned it in but I got a bad grade for it, could someone please help me take an overview of it or take a look at it. but I want to change the project to Fundraising for kids in need all over the world. Because there is an assignment that I did in the past that is connected to it. Develop a work breakdown structure (WBS) for the project. Break...

  • HU, Closed book, 13. Scope management for a project begins with: (53M) A) A work package....

    HU, Closed book, 13. Scope management for a project begins with: (53M) A) A work package. B) An organization breakdown structure. C) A statement of goals. D) A configuration statement. 14. A graphical display of costs against project schedule is called a(n): (5SS) A) S-curves. B) Gantt chart C) Project schedule chart D) Budget in phases 15. The lowest level in work breakdown structure contains the: (50V) A) Atoms. B) Activities. C) Finite elements D) Work packages. E) Sub-Task or...

  • - 16 Which of the following tailoring considerations is concerned with the team's background? Life cycle...

    - 16 Which of the following tailoring considerations is concerned with the team's background? Life cycle approach Physical location Diversity Standards compliance -17Which of the following is an input to plan resource management process? Project charter Resource management plan Team charter Change requests -18"In an IT project, where Ayman is the project manager, Hussain is one of the team members; he is arguing with Ayman regarding an ambiguous part of the scope; Ayman told Hussain to stop this discussion and...

  • Sample Questions (Midterm Exam) Chapter 5 Initiating and Planning Systems Development Projects 1) Who is typically...

    Sample Questions (Midterm Exam) Chapter 5 Initiating and Planning Systems Development Projects 1) Who is typically responsible for performing the PIP process? A) Managers B) Users C) Systems analyst D) The basiness unit 2) What is an example of a project assumption? A) Size B) Potential problems C) Soope D) Complexity Answer: B Difficulty: Difficult AACSB: Information Technology LO: 5.1 Deseribe the steps involved in the project initiation and planning process Classification: Concept 3) What is the tem that describes...

  • Module Three covers refining your project schedule and fine-tuning resources. Table 1-1: Project ...

    Table 1.1 Module Three covers refining your project schedule and fine-tuning resources. Table 1-1: Project Management Process Group and Knowledge Area Mapping (PMBOK Guide® on page 556) provides you with a very specific guideline concerning what task is due for each knowledge area throughout the five projec management process groups. As you can determine from Table 1-1, a large majority of the tasks are complete during the planning process group Describe and explain how sound industry standards or best practices...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT