Question

if the project schedule review shows that you are 20% behind schedule, the project manager should:...

if the project schedule review shows that you are 20% behind schedule, the project manager should: a. immediately notify the project sponsor b. add the event to the risk register c. report the variance as an issue d. perform additional cycles of risk identification because you obviously missed one of the risks

0 0
Add a comment Improve this question Transcribed image text
Answer #1

c. report the variance as an issue

Identifying the risk at this stage shall not actually help in curbing the lagging in schedule neither would adding the event to the risk register help. So alternatively, it is recommended to report the variance as an issue and check for possible solutions such as Crashing in the project wherein additional resources could be added in the critical path to cover the lag in the schedule to some extent.

Add a comment
Know the answer?
Add Answer to:
if the project schedule review shows that you are 20% behind schedule, the project manager should:...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Develop a Risk Log (aka Risk Register), identifying ten (10) risks for a project you are...

    Develop a Risk Log (aka Risk Register), identifying ten (10) risks for a project you are currently working on. Format the spreadsheet such that it is understandable to all project stakeholders regardless of their knowledge of Project and/or Risk Management, and easily viewable, for reporting purposes. The format should be valuable to both technical team members and your project sponsor. Rubric Points Identification of Risks 50 Required Fields 20 Grammar and Proper Citations 10 Clear Format and Easy to View/...

  • Use the following scenario. Review the scenario first and then continue on with your assignment. Consider...

    Use the following scenario. Review the scenario first and then continue on with your assignment. Consider saving the PDF or printing it out for your reference. You have been meeting with the CEO, the project sponsor, your manager, and the heads of all the other departments to discuss the project and their expectations. You are starting to be concerned about the level of risk of this project and whether or not the organization really understands it. As far as you...

  • Understanding project risk is vital to the successful completion of the project. Read the following passage...

    Understanding project risk is vital to the successful completion of the project. Read the following passage below and answer the following questions in approximately 150 words Communicate About Risks Failed projects show that project managers in such projects were frequently unaware of the big hammer that was about to hit them. The frightening finding was that frequently someone of the project organisation actually did see the hammer, but didn't inform the project manager of its existence. If you don't want...

  • You just completed developing the schedule for your project and got the approval from stakeholders and...

    You just completed developing the schedule for your project and got the approval from stakeholders and the sponsor. One of the team members assigned to work on a critical component informs you that she needs additional time to complete her activities as several relevant pieces were missed during planning. Her updated estimate would have no impact on the critical path; thus, the project duration would be the same. The best approach the project manager may take in this situation will...

  • NO EXPLANATION NEEDED, JUST ANSWER. A senior manager is in the process of selecting a project...

    NO EXPLANATION NEEDED, JUST ANSWER. A senior manager is in the process of selecting a project manager for a new initiative that is very important for the company’s future. What is the key factor in choosing a project manager? The project manager should be the most technically competent person on the team The PM works well with various levels of management The project manager should be the functional manager of the most people on the team The project manager must...

  • Woolong Company produces high-end vacuum cleaners and has hired you to oversee the development and release...

    Woolong Company produces high-end vacuum cleaners and has hired you to oversee the development and release of their latest product. A preliminary project initiation meeting will result in the identification of the project sponsor, selection of a project manager, and creation of the project charter. A manager in the production department who knows you are taking a college project management course asks you to prepare a report to help them prepare for the meeting by answering the following questions: Who...

  • 1 You are project manager in a global project with a team consisting of people from...

    1 You are project manager in a global project with a team consisting of people from various countries. What can you try to prevent misunderstandings due to cross-cultural differences? a Use all communication methods available that are suitable for the team and follow up in writing when communicating verbally. Remember that cultural and individual diversity may help project teams solving unforeseen problems during the course of the project. b When you are about to form a team for your project,...

  • Assignment Details Scenario You have been asked to be the project manager for the development of...

    Assignment Details Scenario You have been asked to be the project manager for the development of an information technology (IT) project. The system to be developed will allow a large company to coordinate and maintain records of the professional development of its employees. The company has over 30,000 employees who are located in four sites: Florida, Colorado, Illinois, and Texas. The system needs to allow employees to locate and schedule professional development activities that are relevant to their positions. Sophisticated...

  • Consider the proposal. Should SCF accept or reject ACL’s request? If you were the project manager,...

    Consider the proposal. Should SCF accept or reject ACL’s request? If you were the project manager, which option would you select? What risks are involved with your choice and with ACL’s request? Shell Case Fabricators BACKGROUND Shell Case Fabricators (SCF) designs and builds shell casings that enclose electronic products such as calculators, cell phones, modems. Typically the cases are plastic or plastic compounds. SCF has six different production lines that cover different types of product. For example, the largest high...

  • Qualitative risks are typically categorized by a group of experts to determine the probability and the...

    Qualitative risks are typically categorized by a group of experts to determine the probability and the impact to project objectives. In the example below, consider the next steps that should be taken as project manager to assemble a group of experts to participate. Who would you select and why? Project Management Body of Knowledge (PMBOK) defines risks as “an uncertain event or condition, that if it occurs, has a positive or negative effect on one or more project objectives” (ProjectRiskCoach,...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT