Question

Hello, Assume that a company produce 100 units of laptops in assembly line process, using the...

Hello,

Assume that a company produce 100 units of laptops in assembly line process, using the bellow information, calculate the throughput ratio to measure the process efficiency:

Process time = 11 hours    ,    Waiting time = 2 hours

Could you please answer with an explaination ? As I know here we are supposed to use the throughput ratio expressed as a percentage.

Thanks in advance :)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Throughput ratio can be defined as the return per factory hour divided by the cost per factory hour.

which is 11/11+2 = 11/13 = 0.8461

which is equal to the process efficiency = 84.61%

The ratio means that company is paying its resources for 13 hours ( 11 productive and 2 non productive hours), but it is getting a work worth 11 hours only. Hence the efficiency of 84.61%.

Add a comment
Know the answer?
Add Answer to:
Hello, Assume that a company produce 100 units of laptops in assembly line process, using the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 9. A new product is to be assembled on a 100% manual assembly line. The line is designed to produce 120,000 units/yr. Work content time for the product is 39.5 min. The assembly line will operate...

    9. A new product is to be assembled on a 100% manual assembly line. The line is designed to produce 120,000 units/yr. Work content time for the product is 39.5 min. The assembly line will operate 50 wklyr, 5 shifts/wk, 8 hr/shift. Expected line efficiency is 96%. There will be one worker per station. Determine (a) average hourly production rate, (b) cycle time, and (c) ideal minimum number of workstations.(6 pts) 9. A new product is to be assembled on...

  • A pipe bending machine used to produce ship system components was operated as follows: The perio...

    A pipe bending machine used to produce ship system components was operated as follows: The period of operation was 25 days @ 10 hrs per day. It produced 800 total pipe details, of which 40 were rejected by quality inspectors. The total setup time for the machine during the 25 days was 22 hours. The machine had 3 unplanned breakdown events 1.5 hours for a power failure 0.5 hours for computer network failure 2.2 hours for lubricant pump failure The...

  • Hello, I created this question myself and was able to use the excel OM software for...

    Hello, I created this question myself and was able to use the excel OM software for the answer. I was wondering if you could help me translate the information. what does this all mean? The question is in the upper right hand corner. Thanks in advance. AutoSave Group Project7.9.20 Kimberly Smith KE ER de Home Insert Page Layout Formulas Data Review Help Comments casti General 28 O 09- Α' Α' Wrap Test A-EE. Merge Center - BTW BE- Weas Sort...

  • Summary: A car part manufacturing company currently produce a suspension assembly for Toyota Motor Corporation. Figure...

    Summary: A car part manufacturing company currently produce a suspension assembly for Toyota Motor Corporation. Figure 1 shows the breakdown structure of the suspension assembly and Figure 2 shows the final assembly and how to fit into a car. Table 1 shows the name of components, part numbers and number of components in each suspension assembly. Figure 1. Breakdown structure of Suspension Assembly Figure 2. Suspension Assembly Number in Figure 1 Part number Part name Amount per assembly 1 PA-T15-001...

  • 9. An analysis of company performance using DuPont analysis Aa Aa Walking down the hall of...

    9. An analysis of company performance using DuPont analysis Aa Aa Walking down the hall of your office building with a sheaf of papers in his hand, your friend and colleague, Jason, stepped into your office and asked the following Jason Do you have 10 or 15 minutes that you can spare? You Sure, I've got a meeting in an hour, but I don't want to start something new and then be interrupted by the meeting, so how can I...

  • 9. An analysis of company performance using DuPont analysis A sheaf of papers in her hand,...

    9. An analysis of company performance using DuPont analysis A sheaf of papers in her hand, your friend and colleague, Chloe, steps into your office and asked the following. CHLOE: Do you have 10 or 15 minutes that you can spare? YOU: Sure, I've got a meeting in an hour, but I don't want to start something new and then be interrupted by the meeting, so how can I help? CHLOE: I've been reviewing the company's financial statements and looking...

  • 9. An analysis of company performance using DuPont analysis Walking down the hall of your office...

    9. An analysis of company performance using DuPont analysis Walking down the hall of your office building with a sheaf of papers in her hand, your friend and colleague, Chloe, stepped into your office and asked the following. CHLOE: Do you have 10 or 15 minutes that you can spare? YOU: Sure, I've got a meeting in an hour, but I don't want to start something new and then be interrupted by the meeting, so how can I help? CHLOE:...

  • Book Example P7-38 (similar to) Katharine Austen is the owner of Quality Bikes, a company that...

    Book Example P7-38 (similar to) Katharine Austen is the owner of Quality Bikes, a company that produces high quality cross-country bicycles. Quality years Quality Bikes has purchased titanium from suppliers in the supply chain. Quality Bikes uses titanium for the bio year, Quality Bikes hired Michael Berkner, a recent graduate from State University, as purchasing manager. Michael (Click the icon to view the standard and actual information.) Read the requirements. Requirement 1. Compute the direct materials price and efficiency variances....

  • Hello, If anyone can help me I will grestly appreciate it! I will also give a...

    Hello, If anyone can help me I will grestly appreciate it! I will also give a thumbs up! Autotech Manufacturing is engaged in the production of replacement parts for automobiles. One plant specializes in the production of two parts: Part 127 and Part 234. Part 127 produces the highest volume of activity, and for many years it was the only part produced by the plant. Five years ago, Part 234 was added. Part 234 was more difficult to manufacture and...

  • Sample of CSV file tweet tweet_id airline_sentiment airline 567591480085463000 negative United 567588278875213000 neutral Delta 567590027375702000 negative...

    Sample of CSV file tweet tweet_id airline_sentiment airline 567591480085463000 negative United 567588278875213000 neutral Delta 567590027375702000 negative Delta 5 567592368451248000 negative United 6 567594449874587000 negative Southwest United United United @united yes. We waited in line for almost an hour to do so. Some passengers just left not wanting to wait past 1am. @JetBlue's new CEO seeks the right balance to please passengers and Wall ... - Greenfield Daily Reporter http://t.co/LM3opxkxch @JetBlue is REALLY getting on my nerves !! YOY#nothappy @united the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT