Question

A general contractor has a contract to construct the water line for a new subdivision. The...

A general contractor has a contract to construct the water line for a new subdivision. The original estimate for the water line was $189,000 and no changes have been made to the budget. The water line has been installed by the general contractor itself and the costs to date for the water line are $119,000 and it is estimated that it will take another $22,000 to complete the water line.

What is the total committed cost of the water line for the general contractor? (Answer with a number only)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

the committed cost is any cost that a business entity has already made and connot recover by any means as well as the obligations that a business has already made and can not get out of.

hence, the committed cost here is what the contractor has already made and have to be made i.e. 119000+22000 = $ 141000 .

Add a comment
Know the answer?
Add Answer to:
A general contractor has a contract to construct the water line for a new subdivision. The...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • engineering economics A contractor has been awarded the contract to construct a 6-mile-long tunnel in the...

    engineering economics A contractor has been awarded the contract to construct a 6-mile-long tunnel in the mountains. During the 5-year construction period, the contractor will need water from nearby stream. She will construct a pipeline to carry the water to the main construction yard, an analysis of costs for various pipe sizes is as follows 3. Pipe Sizes (in) 24,000 28,000 30,000 Installed cost of pipeline and pump 20,000 Cost per hour for 1.5 0.75 0.55 0.35 Salvage value of...

  • Assume the following: You are a contractor and have just been awarded a Greenfield Project. A...

    Assume the following: You are a contractor and have just been awarded a Greenfield Project. A budget has been established to install 20,000ft of pipe at an estimated 15,000 man hours and an estimated billable cost of $700,000. The original schedule planned for 4,000ft of pipe to be installed per day by a 300-man crew working a 10-hour shift (anticipated). The job was scheduled to start in Monday and finish on Friday. On Monday 2,000 ft of pipe was installed....

  • Assume the following: You are a contractor and have just been awarded a Greenfield Project. A...

    Assume the following: You are a contractor and have just been awarded a Greenfield Project. A budget has been established to install 20,000ft of pipe at an estimated 15,000 man hours and an estimated billable cost of $700,000. The original schedule planned for 4,000ft of pipe to be installed per day by a 300-man crew working a 10-hour shift (anticipated). The job was scheduled to start in Monday and finish on Friday. On Monday 2,000ft of pipe was installed. On...

  • Construction Engineering Financial No need to use all rows. Just use what you need and have....

    Construction Engineering Financial No need to use all rows. Just use what you need and have. Assignment Description: A contractor has signed a contract to pour the footing, foundation, and slab floor for a building. The contractor uses the costs codes and descriptions from RS Means (see below). The original estimate for the labor to complete the footing and foundation was $8,400 and the contractor has subcontractor the work out for $8,560. The subcontractor has billed the contractor for $2,700...

  • 9. The government agency for which a con- tractor has been working has notified the contractor...

    9. The government agency for which a con- tractor has been working has notified the contractor of a desire to extend the origi- al contract to include three additional units. The initial contract called for four units to be built and delivered. The con- tractor must now estimate the total time required to complete the next three units. Upon reviewing records for the original contract, it was discovered that data for the second unit are inaccurate and cannot be used....

  • Hector is a building contractor and entered into a contract on February 1, 2018 to build...

    Hector is a building contractor and entered into a contract on February 1, 2018 to build a house for Lois for $350,000 with a completion date of July 1, 2018. Payments are to be made to Hector by Lois of $50,000 on the signing of the contract, $150,000 on April 1, provided the house is partially completed as defined in the contract, and $150,000 on July 1, 2018, when the house is fully completed. Lois is very clear that the...

  • 1) Construct a network diagram for the activities 2) Determine the critical path for the network using the ES/EF/LS/LF algorithm. Are there several critical paths? What is the length of the “project”...

    1) Construct a network diagram for the activities 2) Determine the critical path for the network using the ES/EF/LS/LF algorithm. Are there several critical paths? What is the length of the “project”? ії A family has decided to remodel their kitchen. They will be doing so without the help of an interior designer, though they will be having contractors do all the work. The project will involve replacing the cabinets, the floors, and the countertop, as well as painting the...

  • Bramble Construction Company has entered into a contract beginning January 1, 2020, to build a parking...

    Bramble Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $902,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $272,700 $466,620 $618,000 Estimated costs to complete 333,300 139,380 –0– Progress billings to date 273,000 546,000 902,000 Cash collected to date...

  • Cheyenne Construction Company has entered into a contract beginning January 1, 2017, to build a parking...

    Cheyenne Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $596,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $895,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $268,200 $482,760 $605,000 Estimated costs to complete 327,800 113,240 –0– Progress billings to date 267,000 552,000 895,000 Cash collected to date...

  • Pronghorn Construction Company has entered into a contract beginning January 1, 2020, to build a parking...

    Pronghorn Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $596,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $894,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $274,160 $417,200 $607,000 Estimated costs to complete 321,840 178,800 –0– Progress billings to date 272,000 550,000 894,000 Cash collected to date...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT