Question

Suppose that you have two possible projects. Project 1 gives a profit of 10 in period...

Suppose that you have two possible projects. Project 1 gives a profit of 10 in period 0 and 9 in period 1. Project 2 gives a profit of 12 in period 0 and 6.5 in period 1. Suppose that the interest rate r = 0.30. Which project is better? (Hint: no matter when you want to consume, higher PDV is always better.)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

R = 30%

Present worth of project 1 = 10 + 9/(1+30%)

Present worth of project 1 = 16.92

Present worth of project 2 = 12 + 6.5/(1+30%)

Present worth of project 2 = 17

Since project 2 has higher present worth than the project 1, so project 2 is better and project 2 should be selected.

Add a comment
Know the answer?
Add Answer to:
Suppose that you have two possible projects. Project 1 gives a profit of 10 in period...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Suppose that you have two possible projects. Project A gives a profit of 10 in period...

    Suppose that you have two possible projects. Project A gives a profit of 10 in period 0 and 9 in period 1. Project B gives a profit of 12 in period 0 and 6.5 in period 1. Suppose that the interest rate r = 0.05. Which project is better? (Hint: no matter when you want to consume, higher PDV is always better.)

  • You are considering the following two mutually exclusive projects. The required rate of return is 10.75...

    You are considering the following two mutually exclusive projects. The required rate of return is 10.75 percent for project A and 12 percent for project B. Which project should you accept and why? Project A -36,000 21,600 18,200 22,100 Project B -69,900 52,600 46,100 Year 1 2 3 0 Project B; because it has the largest total cash inflow Project A; because its NPV is about $796 more than the NPV of Project B Project B; because it returns all...

  • 1) You are considering two possible projects (Project A and Project B) that would start at...

    1) You are considering two possible projects (Project A and Project B) that would start at the beginning of 2020.  Your boss has indicated that she only wants to select one of these projects given resource constraints and uncertainties about the economy.  She has asked you to evaluate each project and recommend which project you think the company should select.    You have made the following forecasts for each project.  Project A would require an initial investment of $6.4M (USD) on January 1, 2020...

  • 1) You are considering two possible projects (Project A and Project B) that would start at...

    1) You are considering two possible projects (Project A and Project B) that would start at the beginning of 2020.  Your boss has indicated that she only wants to select one of these projects given resource constraints and uncertainties about the economy.  She has asked you to evaluate each project and recommend which project you think the company should select.    You have made the following forecasts for each project.  Project A would require an initial investment of $6.4M (USD) on January 1, 2020...

  • You are trying to determine which of two none mutually exclusive projects to undertake. Project A...

    You are trying to determine which of two none mutually exclusive projects to undertake. Project Adam has an initial outlay of $10,000, an NPV of $4,392.15, an IRR of 1 1.33%, and an EAA of $1,158.64. Project Eve has an initial outlay of $15,000, an NPV of $5,833.73, an IRR of 9.88%, and an EAA of $1 0 3.50 The cost of capital for both projects is 9%, and the prolects have different lives. If the projects are not repeatable,...

  • 1 2. Assume you are trying to compare Project Alpha to Project Beta. Both projects have...

    1 2. Assume you are trying to compare Project Alpha to Project Beta. Both projects have the same appropriate discount rate. Project Alpha generates infinite after tax cash flows which do not grow; the first cash flow is $80M one year from now (T=1) and will cost $600M today (T=0). Project Beta generates infinite after tax cash flows which do not grow; the first cash flow is $40M one year from now (T1) and will cost $300M today (T 0)....

  • #1 Questions a) to e) refer to two projects with the following cash flows: Year Project...

    #1 Questions a) to e) refer to two projects with the following cash flows: Year Project B Project A -$200 -$200 80 100 100 100 a) If the opportunity cost of capital is 10%, which of these projects is worth pursuing? Explain. b) Suppose that you can choose only one of these projects. Which would you choose? The discount rate is still 10%. Justify your reasoning. c) Which project would you choose if the opportunity cost of capital were 16%?...

  • 12. Assume you are trying to compare Project Alpha to Project Beta. Both projects have the...

    12. Assume you are trying to compare Project Alpha to Project Beta. Both projects have the same appropriate discount rate. Project Alpha generates infinite after tax cash flows which do not grow; the first cash flow is $80M one year from now (T=1) and will cost $600M today (T=0). Project Beta generates infinite after tax cash flows which do not grow; the first cash flow is $40M one year from now (T=1) and will cost $300M today (T=0). Which statement...

  • QUESTION TWO XYZ Ltd is considering three possible capital projects for next year. Each project has...

    QUESTION TWO XYZ Ltd is considering three possible capital projects for next year. Each project has a 1- year life, and project returns depend on next year's state of the economy. The estimated return are shown in the table: State of the Probability Rate of Return economy of occurrence A B с Recession Average Boom 0.25 0.50 0.25 10% 14 16 9% 13 18 14% 12 10 Required: i. ii. iii. iv. Compute each projects expected rate of return Compute...

  • 1. You must analyze the cash flows of two projects, S and L. Project S: CF0...

    1. You must analyze the cash flows of two projects, S and L. Project S: CF0 = -1500; CF1 = 800; CF2 = 700; CF3 = 100; CF4 = 600 Project L: CF0 = -1500; CF1 = 200; CF2 = 600; CF3 = 900; CF4 = 700 Given a required rate of return of 10%, what is the IRR of the better project? (Note: the better project may not be the one with the higher IRR)

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT