A project requires 17,000 allowed hours. Location of the work is above the arctic circle, and the efficiency is estimated as 45%. Is the gross hourly cost is $50, then what is the estimated cost? If the work is in Texas, hourly cost is $30, and an efficiency of 85% is assumed, then what is the cost of direct labor?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Hours required = 17,000

Arctic Circle:-

Efficiency = 45%

Total working hours required= 17,000/0.45= 37,770

Grossly hour rate = $50

Total cost of direct labour = 37,770*50=$188,500

Texas

Hourly cost = $30

Efficiency= 85%

Total working hours required= 17,000/0.85= 20,000

Direct labour cost= 20,000*30=$60,0000

Add a comment
Know the answer?
Add Answer to:
Construction Cost Analysis and Estimating: A project requires 17,000 allowed hours. Location of the work is...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Direct Labor Variances Bellingham Company produces a product that requires 3 standard direct labor hours per...

    Direct Labor Variances Bellingham Company produces a product that requires 3 standard direct labor hours per unit at a standard hourly rate of $8.00 per hour. If 6,300 units used 19,500 hours at an hourly rate of $7.60 per hour, what is the direct labor (a) rate variance, (b) time variance, and (c) cost variance7 Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. a. Direct labor rate variance...

  • Question 18 1 pts Acme Construction specializes in concrete work. Each job is a project and...

    Question 18 1 pts Acme Construction specializes in concrete work. Each job is a project and they rely heavily on part-time workers since project demand varies based on season, weather, and the number of projects to bid on. Based on supply and demand for laborer, the actual hourly pay varies throughout the year. Based on the previous years averages, the accounting department is using a standard value of $18 per hour for direct labor. On this project the number of...

  • 978-1-62131-102-7 High-Low Cost Estimation and Simple Regression Analysis Assume we have the following observations relating to...

    978-1-62131-102-7 High-Low Cost Estimation and Simple Regression Analysis Assume we have the following observations relating to overhead costs and direct labor hours for Department A of the ABC Company 3-27 Direct Labor Hours 15 20 14 13 18 15 12 16 18 19 Overhead Costs 40 50 35 30 36 31 41 42 45 TING FOR MANAGERIAL PLANNING, DECISION MAKING, AND CON KING, AND CONTROL Required there (1) Determine the budgeted overhead costs for Department A in a month when...

  • Matthews & Bros. is a local landscape construction company. In analyzing financial performance, the cost accountant...

    Matthews & Bros. is a local landscape construction company. In analyzing financial performance, the cost accountant compares actual results with a flexible budget. The standard direct labor rates used in the flexible budget are established each year at the time the annual plan is formulated and held constant for the entire year. The standard direct labor rates in effect for the current fiscal year and the standard hours allowed for the actual output of work for July are shown in...

  • The following question comes from the end of Chapter 8 on Cost-Benefit Analysis regarding the "Big...

    The following question comes from the end of Chapter 8 on Cost-Benefit Analysis regarding the "Big Dig" highway and bridge construction project. Assume that it is planned to take7 years to complete (from t-0 to t-6). . The project will require: $45 million in construction materials per year S20 million in labor costs per year Construction will disrupt transportation within the city for 7 years, which means longer commutes for 100,000 workers by 30 hours a year. These 100,000 workers...

  • Problem 09.020 Benefit/Cost Analysis of a Single Project A consultant, after 3 months of work, reported...

    Problem 09.020 Benefit/Cost Analysis of a Single Project A consultant, after 3 months of work, reported that the modified B/C ratio for a city owned hospital heliport project is 1.3. If the initial cost is $1.3 million and the annual benefits are $150,000, what is the amount of the annual M&O costs used in the calculation? The report stated that a discount rate of 11% per year and an estimated life of 45 years were used. The M&O cost is...

  • Problem 6 (12 points) Beck Construction Company began work on a new building project on January 1, 2016. The proje...

    Problem 6 (12 points) Beck Construction Company began work on a new building project on January 1, 2016. The project is to be completed by December 31, 2021, for a fixed price of $105 million. The following are the actual costs incurred and estimates of remaining costs to complete the project that were made by Beck's accounting staff: Year Actual Cost Incurred each year Estimated to complete 2019 $ 20 million $ 80 million 2020 $ 45 million $ 25...

  • Sheldon Company manufactures only one product and uses a standard cost system. During the past month,...

    Sheldon Company manufactures only one product and uses a standard cost system. During the past month, manufacturing operations for the company had the following variances: direct labor rate variance = $30,000 favorable; direct labor efficiency variance = $50,000 unfavorable. Sheldon allows 5 standard direct labor hours per unit produced, and its standard direct labor hourly pay rate is $50. During the month, the company used 25% more direct labor hours than the standard allowed for the output achieved. What was...

  • Extended Learning Exercise. You have been asked to prepare a quick estimate of the construction cost...

    Extended Learning Exercise. You have been asked to prepare a quick estimate of the construction cost for a coal-fired electricity generating plant and facilities. A work breakdown structure (levels one through three) is shown in the table below EE! Click the icon to view the work breakdown structure Click the icon to view the available information What is your estimated 2019 cost for building the coal-fired generating facility? Summarize your calculations in a cost estimating worksheet, and state the assumptions...

  • Please show all work to get to answer. Determining Unit Costs, Variance Analysis, and Interpretation Big Dog Company, a...

    Please show all work to get to answer. Determining Unit Costs, Variance Analysis, and Interpretation Big Dog Company, a manufacturer of dog food, produces its product in 1,000-bag batches. The standard cost of each batch consists of 6,000 pounds of direct materials at $0.30 per pound, 48 direct labor hours at $8.50 per hour, and variable overhead cost (based on machine hours) at the rate of $10 per hour with 18 machine hours per batch. The following variable costs were...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT