Question

x-barstd de We are going to combine a couple of activities that we performed on the HW. The hypothetical15.1977 1.16544 is asValues you are permitted to type in 0, 1, 5, 10, 14, 15, 16, 17, 20, 25 → Answer each of the below questions as instructed; m6. Using your answer to #3, what is the expected cost ($k) for completing too soon? Report to one decimal place. Answer 7, us

x-barstd de We are going to combine a couple of activities that we performed on the HW. The hypothetical15.1977 1.16544 is as follows: Do not touch these cell values. An international company, InterCo, has contracted with a housing construction company that has been selected to construct a new tract of 193 upscale homes for several families that are being relocated to start a new InterCo facility. Families will be phased in at this new tract, so having a reasonable degree of confidence about when each house will be completed is very important. To this end, the construction company will pay penalties if the houses are either completed too early or too late. But select them for your calculations at the right - Data (in units of calendar weeks) from 213 previous similar construction jobs (houses) are found below this text box. Interco would like to have each house be completed in 15 1 weeks (i.e., 14-16 weeks). You are permitted to freeze cells along Row 3 If the company completes too soon ( -175.4% 2. What is the probability that a house will be completed more than 17 weeks from start? Answer -193.9% 3. What is the probability that a house will be completed in less than 14 weeks from start? Answer -15,2% 4. What is the probability that a house will be completed within the specified time frame of 14-16 weeks? Answer-> 309.196 5. Using your answer to #4, how many of the 193 houses are expected to be completed on time? Report to one decimal place. Answer houses
6. Using your answer to #3, what is the expected cost ($k) for completing too soon? Report to one decimal place. Answer 7, using your answers to #1 & #2, what is the expected cost ($k) for completing in 16-17 weeks? Report to one decimal place. Answer 8. Using your answer to #2, what is the expected cost ($k) for completing in more than 17 weeks? Report to one decimal place. Answer 9. Using the SUM macro and your answers for #6-8, what is the total penalty the construction company is expected to pay? Answer 10. What is the probability that a house will be completed in exactly 15 weeks? Answer
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1.

P(X > 16) =P(Z > (16 - 15.1977)/1.16544) =P(Z > 0.6884) =0.246 =24.6%

2.

P(X > 17) =P(Z > (17 - 15.1977)/1.16544) =P(Z > 1.5465) =0.061 =6.1%

3.

P(X < 14) =P(Z < (14 - 15.1977)/1.16544) =P(Z < -1.0277) =0.152 =15.2%

4.

P(14 \leq X \leq 16) =P(-1.0277 \leq Z \leq 0.6884) =1 - 0.152 - 0.246 =0.602 =60.2%

5.

193*60.2% =116.2 houses are expected to be completed on time.

6.

The expected cost for completing too soon =10k*15.2% =1.5k

7.

P(16 < X \leq 17) =P(X > 16) - P(X > 17) =0.246 - 0.061 =0.185 =18.5%.

So, the expected cost for completing in 16 - 17 weeks =15k*18.5% =2.8k

8.

The expected cost for completing in more than 17 weeks =20k*6.1% =1.2k

9.

The total penalty the construction company is expected to pay =1.5k + 2.8k + 1.2k =5.5k

10.

Since normal distribution is a continuous probability distribution, the probability that the normal random variable, X equals any exact value is always 0.

So, P(X =15) =0

Add a comment
Know the answer?
Add Answer to:
X-barstd de We are going to combine a couple of activities that we performed on the HW. The hypot...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • (All answers were generated using 1,000 trials and native Excel functionality.) A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for th...

    (All answers were generated using 1,000 trials and native Excel functionality.) A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows: Activity Activity Time (weeks) Probability A 5 0.25 6 0.35 7 0.25 8 0.15 B 3 0.20 5 0.55 7 0.25 C 10 0.10 12 0.25 14 0.40 16 0.20 18 0.05 D 8 0.60 10 0.40 (a)...

  • 1. The activities needed for a new project your company is undertaking are listed in the...

    1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...

  • Sox Engineering designs and constructs air conditioning and heating​ (HVAC) systems for hospitals and clinics. Currently...

    Sox Engineering designs and constructs air conditioning and heating​ (HVAC) systems for hospitals and clinics. Currently the​ company's staff is overloaded with design work. There is a major design project due in 99 weeks. The penalty for completing the design late is ​$14 comma 00014,000 per​ week, since any delay will cause the facility to open later than​ anticipated, and cost the client significant revenue. If the company uses its inside engineers to complete the​ design, it will have to...

  • Orleans Construction Company Case (adapted from Meredith and Mantel) The Orleans Construction Company, a small construction...

    Orleans Construction Company Case (adapted from Meredith and Mantel) The Orleans Construction Company, a small construction company in North Carolina, has been awarded a contract for the construction of a new 25,000 soccer stadium at Greensboro. The City is hoping to use this facility to attract a new soccer franchise. The construction cannot start earlier than March 2, 2020 (because of the availability of bond funds) and must be completed within 1 year (52 weeks). A penalty clause of $13,000...

  • EX16 XL _CH01_GRADER ML2 HW - Real Estate Sales Report 1.3 Project Description: You own a...

    EX16 XL _CH01_GRADER ML2 HW - Real Estate Sales Report 1.3 Project Description: You own a small real estate company in Indianapolis. You track the real estate properties you list for dlients. You want to analyze sales for selected properties. Yesterday, you prepared a workbook with a worksheet for recent sales data and another worksheet listing several properties you listed. You want to calculate the number of days that the houses were on the market and their sales percentage of...

  • Question 1 10 points Save Answer A project consists of three activities: A, B, and C....

    Question 1 10 points Save Answer A project consists of three activities: A, B, and C. Activities A and B can begin at time 0 (start of the project), but activity C can only start after B is completed. The project ends when all activities are completed. The durations of the activities were simulated 10 times and the following values were obtained: Run 1 A Duration B Duration C Duration 51 48 17 60 48 19 2 3 30 39...

  • Check my work mode: This shows what is correct or incorrect for the work you have...

    Check my work mode: This shows what is correct or incorrect for the work you have completed so far. It does not indicate Is it reasonable to assume that Treasury bonds will provide higher returns in recessions than in booms? Yes No b. Calculate the expected rate of return and standard deviation for each investment. (Do not round intermediate calculation your answers as a percent rounded to 1 decimal place.) Answer is complete but not entirely correct. Expected Rate of...

  • Problem 9-17 The Porsche Shop, founded in 1985 by Dale Jensen, specializes in the restoration of...

    Problem 9-17 The Porsche Shop, founded in 1985 by Dale Jensen, specializes in the restoration of vintage Porsche automobiles. One of Jensen's regular customers asked him to prepare an estimate for the restoration of a 1964 model 356SC Porsche. To estimate the time and cost to perform such a restoration, Jensen broke the restoration process into four separate activities: disassembly and initial preparation work (A), body restoration (B), engine restoration (C), and final assembly (D). Once activity A has been...

  • Choose an event or significant task and prepare an activities list following a format similar to...

    Choose an event or significant task and prepare an activities list following a format similar to that used in the text, Table 9.3, Chapter 9, page 391. Be sure to include the immediate predecessors. Then, create a project network similar to that shown in Figure 9.7, Chapter 9, page 392. Do NOT include times for the activities and do NOT attempt to determine the critical path. Examples of events you might consider (there are many others): formal dinner for 5...

  • Using the model, predict sales for the fourth quarter of year 2015 You are projecting future...

    Using the model, predict sales for the fourth quarter of year 2015 You are projecting future sales and have constructed a linear model using historical sales data for each of the four quarters between years 2011 and 2014. Answer questions 24-28 using the information below Regression Statistics Obs Quarter Year Sales Sales 1 2011 71 Multiple R 0.995 7 2011 49 R Square 0.990 90 58 3 2011 Adjusted R Square 0.986 80 4 2011 78 Standard Error 1.561 70...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT