Question

Problem 9-17 The Porsche Shop, founded in 1985 by Dale Jensen, specializes in the restoration of...

Problem 9-17

The Porsche Shop, founded in 1985 by Dale Jensen, specializes in the restoration of vintage Porsche automobiles. One of Jensen's regular customers asked him to prepare an estimate for the restoration of a 1964 model 356SC Porsche. To estimate the time and cost to perform such a restoration, Jensen broke the restoration process into four separate activities: disassembly and initial preparation work (A), body restoration (B), engine restoration (C), and final assembly (D). Once activity A has been completed, activities B and C can be performed independently of each other; however, activity D can be started only if both activities B and C have been completed. Based on his inspection of the car, Jensen believes that the following time estimates (in days) are applicable:

Activity Optimistic Most Probable Pessimistic
A 3 4 8
B 5 8 11
C 2 4 6
D 4 5 12

Jensen estimates that the parts needed to restore the body will cost $3000 and that the parts needed to restore the engine will cost $5000. His current labor costs are $400 a day.

  1. (i) 62c19597-71b5-4b11-9638-8bb95fccb3a2.JPG
  2. What is the expected project completion time?

    Critical Path:  

    If required, round your answer to one decimal place.

    Expected time =  days
  3. Jensen's business philosophy is based on making decisions using a best- and worst-case scenario. Develop cost estimates for completing the restoration based on both a best- and worst-case analysis. Assume that the total restoration cost is the sum of the labor cost plus the material cost.

    If required, round non-monetary answers to the nearest whole number. If required, round monetary answers to the nearest dollar.

    Best Cost (Optimistic Times) = days

    Total Cost = $  

    Worst Cost (Pessimistic Times) =  days

    Total Cost = $  
  4. If Jensen obtains the job with a bid that is based on the costs associated with an expected completion time, what is the probability that he will lose money on the job?

    If required, round non-monetary answer to two decimal places. If required, round monetary answer to the nearest dollar.

    Bid Cost = $  

    probability time and cost will exceed the expected time and cost (If required, round your answer to two decimal places).
  5. If Jensen obtains the job based on a bid of $16,800, what is the probability that he will lose money on the job?

    Note: Use Appendix B to identify the areas for the standard normal distribution. If required, round your answer to four decimal places.

    The probability of a loss is
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Tural cost Will be in optimistic scenario - 3000 + 5ooo + 12 (400) = $ 12800 For pessimistic scenario - 03 Project CompletionD OSO The probablity of completion of work at Expected time will be always 10.50 in PERR Metwork So the probullity of not comCalealating Prabublou cef the proyect in 22 days completing Before that we need to calculate Oc6q էր | 0 0 0 | 1. 2- (1 ՐՐՐԸShort Summary of answers (Detailed explanation is in the images above):

Expected project completion time is 18.5 days with critical path A-B-D

In Optimistic scenario the project competion time will be 12 days and the cost $12,800

In Pessimistic scenario the project completion time will be 31 days and cost will be $20,400

The probability of loss at expected time will be 0.50 with bid of $15,400

If Jensen bid $16,800, the probability he will make loss is 0.0301  

Kindly give a upvote...

Add a comment
Know the answer?
Add Answer to:
Problem 9-17 The Porsche Shop, founded in 1985 by Dale Jensen, specializes in the restoration of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 17-7 Three recent college graduates have formed a partnership and have opened an advertising firm....

    Problem 17-7 Three recent college graduates have formed a partnership and have opened an advertising firm. Their first project consists of activities listed in the following table. Use Table B TIME IN DAYS Immediate Activity Predecessor Optimistic Most Likely Pessimistic 12 15 End E, G, I b.What is the probability that the project can be completed in 24 days or less? In 21 days or less? (Round your te and z values to 2 decimal places and "Standard deviation" to...

  • Problem 17-7 Three recent college graduates have formed a partnership and have opened an advertising firm....

    Problem 17-7 Three recent college graduates have formed a partnership and have opened an advertising firm. Their first project consists of activities listed in the following table. Use Table B. TIME IN DAYS Immediate Activity Predecessor Optimistic Most Likely Pessimistic 15 12 7 End E,G,1 b.What is the probability that the project can be completed in 24 days or less? In 21 days or less? (Round your te and z values to 2 decimal places and "Standard deviation" to 3...

  • H m Problem 21 Question Help Recently, you were assigned to manage a project for your...

    H m Problem 21 Question Help Recently, you were assigned to manage a project for your company. You have constructed a network diagram depicting the various activities in the project (shown below to the right). In addition, you have asked your team to estimate the amount of time that they would expect each of the activities to take. Their responses are shown in the following table: Time Estimates (days) Most Likely Activity Optimistic Pessimistic A 4 8 12 5 12...

  • Three recent college graduates have formed a partnership and have opened an advertising firm. Their first...

    Three recent college graduates have formed a partnership and have opened an advertising firm. Their first project consists of activities listed in the following table. Use Table B. TIME IN DAYS Activity Immediate Predecessor Optimistic Most Likely Pessimistic A — 5   6          7          B — 8   8          11          C A 6   8          11          D — 9   12          15          E C 5   6          9          F D 5   6          7         ...

  • Three recent college graduates have formed a partnership and have opened an advertising firm. Their first...

    Three recent college graduates have formed a partnership and have opened an advertising firm. Their first project consists of activities listed in the following table. Use Table B. TIME IN DAYS Activity Immediate Predecessor Optimistic Most Likely Pessimistic A — 5 6 7 B — 8 8 11 C A 6 8 11 D — 9 12 15 E C 5 6 9 F D 5 6 7 G F 2 3 7 H B 4 4 5 I H...

  • Problem 9-09 (Algorithmic) At a local university, the Student Commission on Programming and Entertainment (SCOPE) is...

    Problem 9-09 (Algorithmic) At a local university, the Student Commission on Programming and Entertainment (SCOPE) is preparing to host its first rock concert of the school year. To successfully produce this rock concert, SCOPE has listed the requisite activities and related information in the following table (duration estimates measured in days). Immediate Most Activity Predecessor(s) Optimistic Probable Pessimistic A: Negotiate contract with - 9 10 11 selected musicians B: Reserve site - 7 9 11 C: Manage travel logistics A...

  • Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their...

    Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their immediate predecessors, and the optimistic, most likely, and pessimistic estimates of their times (in days) are provided below. Activity Description Immediate Predecessors Optimistic Time (days) Most Likely Time (days) Pessimistic Time (days) TE ES EF LF LS Slack Standard Dev Variance A Select manager -- 10 12 20 13 0 1.67 B Select site -- 8 15 22 15 0 2.33 C Hire workers...

  • our categories of overhead. The expected overhead costs for each category for Maintenance Materials handing 26....

    our categories of overhead. The expected overhead costs for each category for Maintenance Materials handing 26. Stanford Corporation has f next year are as follows: $210,000 90,000 75,000 150,000 Setups Inspection The company has been asked to submit a bid for a proposed job. The plant manacer mbanufacturing this job would result in new business in future years. Bids are usually based upon full manufacturing cost plus 30 percent. Estimates for the proposed job are as follows: Direct materials Direct...

  • Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their...

    Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their immediate predecessors, and the optimistic, most likely, and pessimistic estimates of their times (in days) are provided below. Activity Description Immediate Predecessors Optimistic Time (days) Most Likely Time (days) Pessimistic Time (days) TE ES EF LF LS Slack Standard Dev Variance A Select manager -- 10 12 20 13 0 1.67 B Select site -- 8 15 22 15 0 2.33 C Hire workers...

  • #1 #2 #3 #4 Time Estimates (in weeks) for SOM's Bus Project is given in the...

    #1 #2 #3 #4 Time Estimates (in weeks) for SOM's Bus Project is given in the following table. Activity Optimistic time Most likely time Pessimistic time A 2 4 6 B 3 5 8 Ic с 4 6 8 D 3 5 10 Please help the project management team to find the standard deviation of Activity D. keep two decimals if not exact, either round up or down is ok. For example, for 0.1346, (0.13 or 13) and (0.14 or.14)...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT