Question

Problem 17-7 Three recent college graduates have formed a partnership and have opened an advertising firm. Their first project consists of activities listed in the following table. Use Table B TIME IN DAYS Immediate Activity Predecessor Optimistic Most Likely Pessimistic 12 15 End E, G, I b.What is the probability that the project can be completed in 24 days or less? In 21 days or less? (Round your te and z values to 2 decimal places and Standard deviation to 3 decimal places. Round your final answers to 4 decimal places.) Probability Days 24 days or less 21 days or less 0.9686 c. Suppose it is now the end of the seventh day and that activities A and B have been completed while activity D is 50 percent completed. Time estimates for the completion of activity D are 5, 6, and 7. Activities C and H are ready to begin. Determine the probability of finishing the project by day 24 and the probability of finishing by day 21. (Round your intermediate calculations to 3 decimal places and final answers to 4 decimal places.) Probability Day 24 Day 21

0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

Book1 Microsoft Excel sert Page Layout Formulas Home Ins cut Copy E AutosSum Calibri ору- B I 표, , , ク,스, 谭- 幽Merge & Center.

Please note the to is optimistic time

tm is most likely time

tp is pessimistic time

te is expected time and is calculated by the formula = \frac{t_{o}+4*t_{m}+t_{p}}{6}

and the standard deviation is calculated by = \frac{t_{p}-t_{o}}{6}

Variance = standard deviation ^2

It is calculated for each activity

Then we draw the network diagram of the project and as from the diagram it is evident that there are three paths to complete the project

A-C-E

B-H-I

D-F-G

Calculate the expected time of each path by adding the expected time of each path activity and variance by adding the variance

(** we cant add standard deviation simply to get the resultant we need a variance to add and then take the square root to calculate resultant standard deviation)

A-C-E

te= 6+8.17+6.33=20.50

variance = 0.111+0.694+0.444=1.249

St dev= sqrt(1.249) = 1.117

Path B-H-I

te= 8.50+4.17+6.83 = 19.50

variance = 0.25+0.028+0.25=0.528

std dev=0.726

Path D-F-G

te = 12+6+3.5= 21.50

variance = 1+0.111+0.694=1.805

std dev= 1.343

now we have to calculate the z values for each path and from the normal table we can get the probability

z=\frac{x-\mu}{\sigma}
for 24 days x=24

path A-C-E = z=\frac{24-20.5}{1.117} = 3.13 probability = NORMSDIST(3.13,TRUE) = 1.00

path B-H-I = z=\frac{24-19.5}{0.726} = 6.19 probabilty = 1.00

path D-F-G = z=\frac{24-21.5}{1.343} =1.86 probability = 0.97

So probability of fininshing the oriject 24 days or less = 1.00*1.00*0.97 = 0.9686

similarly for 21 days

path -A-C-E = z=\frac{21-20.5}{1.117} = 0.446 = prbobability = 0.67

path B-H-I = z= 2.06 prob = 0.98

path D-F-G = z= -0.37 prob= 0.36

so probability of completion 21 days or less = 0.67*0.98*0.36= 0.2363

***************************************************************************************************

A and B is completed by 7 th day so there expected time is 7

C and H are having no changes only D is

pathA- C-E

expected time= 7+8.17+6.33 = 21.5

variance = 41/36 = 1.138

path D-F-G

only D is changed its expected time will be = (5+4*6+7)/6 = 6 and variance is 0.111

expeted time for this path = 15.50

total duration = 7+15.5 = 22.5

variance = 33/36 = 0.916

(33 comes from addition of (tp-to)^2)

similarly for path B-H-I

total time =7+11= 18

variance= 10/36 = 0.278

Probabilty calcualtion for 24 days

path-A-C-E = z=\frac{24-21.5}{1.067} =0.99

path D-F-G = 0.94

path B-H-I = 1.00

so total probability = 0.99*0.94*1.00 =0.9306

similarly for 21 days or less

path A-C-E = 0.3192

path-D-F-G = 0.0582

pathB-H-I = 1.00

so total probability = 0.3192*0.0582*1= 0.0186

Please comment if any doubt

Rate me

Thanks

Add a comment
Know the answer?
Add Answer to:
Problem 17-7 Three recent college graduates have formed a partnership and have opened an advertising firm....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Problem 17-7 Three recent college graduates have formed a partnership and have opened an advertising firm....

    Problem 17-7 Three recent college graduates have formed a partnership and have opened an advertising firm. Their first project consists of activities listed in the following table. Use Table B. TIME IN DAYS Immediate Activity Predecessor Optimistic Most Likely Pessimistic 15 12 7 End E,G,1 b.What is the probability that the project can be completed in 24 days or less? In 21 days or less? (Round your te and z values to 2 decimal places and "Standard deviation" to 3...

  • Three recent college graduates have formed a partnership and have opened an advertising firm. Their first...

    Three recent college graduates have formed a partnership and have opened an advertising firm. Their first project consists of activities listed in the following table. Use Table B. TIME IN DAYS Activity Immediate Predecessor Optimistic Most Likely Pessimistic A — 5 6 7 B — 8 8 11 C A 6 8 11 D — 9 12 15 E C 5 6 9 F D 5 6 7 G F 2 3 7 H B 4 4 5 I H...

  • Three recent college graduates have formed a partnership and have opened an advertising firm. Their first...

    Three recent college graduates have formed a partnership and have opened an advertising firm. Their first project consists of activities listed in the following table. Use Table B. TIME IN DAYS Activity Immediate Predecessor Optimistic Most Likely Pessimistic A — 5   6          7          B — 8   8          11          C A 6   8          11          D — 9   12          15          E C 5   6          9          F D 5   6          7         ...

  • You are responsible for managing a project with the following activities (all times are given in...

    You are responsible for managing a project with the following activities (all times are given in weeks): Optimistic Most Likely Pessimistic Immediate Time Predecessor(s) Time Activity Time 4 C, D D, E 12 4 8 6 4 What is the expected time of completion of the project? (weeks) (Include 1 decimal place, e.g.,3.1.) abs What is the probability that the project will be completed in 24 weeks or less? (Provide ab 2 decimal places, no 90 sign, e.g., 2.12 for...

  • Problem 9-17 The Porsche Shop, founded in 1985 by Dale Jensen, specializes in the restoration of...

    Problem 9-17 The Porsche Shop, founded in 1985 by Dale Jensen, specializes in the restoration of vintage Porsche automobiles. One of Jensen's regular customers asked him to prepare an estimate for the restoration of a 1964 model 356SC Porsche. To estimate the time and cost to perform such a restoration, Jensen broke the restoration process into four separate activities: disassembly and initial preparation work (A), body restoration (B), engine restoration (C), and final assembly (D). Once activity A has been...

  • H m Problem 21 Question Help Recently, you were assigned to manage a project for your...

    H m Problem 21 Question Help Recently, you were assigned to manage a project for your company. You have constructed a network diagram depicting the various activities in the project (shown below to the right). In addition, you have asked your team to estimate the amount of time that they would expect each of the activities to take. Their responses are shown in the following table: Time Estimates (days) Most Likely Activity Optimistic Pessimistic A 4 8 12 5 12...

  • Problem 9-09 (Algorithmic) At a local university, the Student Commission on Programming and Entertainment (SCOPE) is...

    Problem 9-09 (Algorithmic) At a local university, the Student Commission on Programming and Entertainment (SCOPE) is preparing to host its first rock concert of the school year. To successfully produce this rock concert, SCOPE has listed the requisite activities and related information in the following table (duration estimates measured in days). Immediate Most Activity Predecessor(s) Optimistic Probable Pessimistic A: Negotiate contract with - 9 10 11 selected musicians B: Reserve site - 7 9 11 C: Manage travel logistics A...

  • Coleman Rich Control Devices, Inc., produces custom-built relay devices for auto makers. The most recent project...

    Coleman Rich Control Devices, Inc., produces custom-built relay devices for auto makers. The most recent project undertaken by Rich requires 14 different activities. Rich's managers would like to determine the total project completion time (in days) and those activities that lie along the critical path. The appropriate data are shown in the following table: பா் Immediate Immediate Time (days) Time (days) Predecessor(s) Activity Predecessor(s) b b Activity a 6 E, F G, H A 4 5 8 3 3 B...

  • Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their...

    Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their immediate predecessors, and the optimistic, most likely, and pessimistic estimates of their times (in days) are provided below. Activity Description Immediate Predecessors Optimistic Time (days) Most Likely Time (days) Pessimistic Time (days) TE ES EF LF LS Slack Standard Dev Variance A Select manager -- 10 12 20 13 0 1.67 B Select site -- 8 15 22 15 0 2.33 C Hire workers...

  • Rich Cole Control Devices, Inc., produces custom-built relay devices for auto makers. The most recent project...

    Rich Cole Control Devices, Inc., produces custom-built relay devices for auto makers. The most recent project undertaken by Cole requires 14 different activities appropriate data are shown in the following table Time (days) Immediate bPredecessor(s)Activitya Time (days) Immediate Activity a bPredecessor(s) E, F G, H 10 17 B, C 5 6 10 6 L, M a) The expected completion time of the project days (round your response to two decimal places) The activities that represent the project's critical path are...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT