Question

Problem 17-7 Three recent college graduates have formed a partnership and have opened an advertising firm. Their first projecc. Suppose it is now the end of the seventh day and that activities A and B have been completed while activity D is 50 percen

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Activity a m b te = (a +4m +b) / 6 SD = (b - a) / 6 Var = SD2
A 5 6 7 6.00 0.333 0.111
B 8 8 11 8.50 0.500 0.250
C 6 8 11 8.17 0.833 0.694
D 9 12 15 12.00 1.000 1.000
E 5 6 9 6.33 0.667 0.444
F 5 6 7 6.00 0.333 0.111
G 2 3 7 3.50 0.833 0.694
H 4 4 5 4.17 0.167 0.028
I 5 7 8 6.83 0.500 0.250

(b)

There are three different independent paths: A-C-E, B-H-I, and D-F-G

Find the path-wise te and variances as shown below

Activity te Var
A 6.00 0.111
C 8.17 0.694
E 6.33 0.444
Total 20.50 1.25
SD 1.118
Activity te Var
B 8.50 0.25
H 4.17 0.03
I 6.83 0.25
Total 19.50 0.53
SD 0.726
Activity te Var
D 12.00 1.00
F 6.00 0.11
G 3.50 0.69
Total 21.50 1.81
SD 1.344

For completion within 24 days

  • Path A-C-E: z = (24 - 20.50) / 1.118 = 3.13, So, Prob (Completion) = 0.9991
  • Path B-H-I: z = (24 - 19.50) / 0.726 = 6.20, So, Prob (Completion) = 1
  • Path D-F-G: z = (24 - 21.50) / 1.344 = 1.86, So, Prob (Completion) = 0.9686

So, Prob(Completion within 24 days) = 0.9991 * 1 * 0.9686 = 0.9677

For completion within 21 days

  • Path A-C-E: z = (21 - 20.50) / 1.118 = 0.45, So, Prob (Completion) = 0.6736
  • Path B-H-I: z = (21 - 19.50) / 0.726 = 2.07, So, Prob (Completion) = 0.9808
  • Path D-F-G: z = (21 - 21.50) / 1.344 = -0.37, So, Prob (Completion) = 0.3557

So, Prob(Completion within 24 days) = 0.6736 * 0.9808 * 0.3557 = 0.2350

(c)

Activity a m b te = (a +4m +b) / 6 SD = (b - a) / 6
D 5 6 7 6 0.333333333
Activity te Var
A 0.00 0.000
C 8.17 0.694
E 6.33 0.444
Total 14.50 1.14
SD 1.067
Activity te Var
B 0.00 0.00
H 4.17 0.03
I 6.83 0.25
Total 11.00 0.28
SD 0.527
Activity te Var
D 6.00 0.333
F 6.00 0.11
G 3.50 0.69
Total 15.50 1.14
SD 1.067

For completion within 24 days (i.e. in another 17 days)

  • Path A-C-E: z = (17 - 14.50) / 1.067 = 2.34, So, Prob (Completion) = 0.9904
  • Path B-H-I: z = (17 - 11.00) / 0.527 = 11.39, So, Prob (Completion) = 1
  • Path D-F-G: z = (17 - 15.50) / 1.067 = 1.41, So, Prob (Completion) = 0.9207

So, Prob(Completion within 24 days) = 0.9904 * 1 * 0.9207 = 0.9119

For completion within 21 days (i.e. in another 14 days)

  • Path A-C-E: z = (14 - 14.50) / 1.067 = -0.47, So, Prob (Completion) = 0.3192
  • Path B-H-I: z = (14 - 11.00) / 0.527 = 5.69, So, Prob (Completion) = 1
  • Path D-F-G: z = (14 - 15.50) / 1.067 = -1.41, So, Prob (Completion) = 0.0793

So, Prob(Completion within 24 days) = 0.3192 * 1 * 0.0793 = 0.0253

Add a comment
Know the answer?
Add Answer to:
Problem 17-7 Three recent college graduates have formed a partnership and have opened an advertising firm....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 17-7 Three recent college graduates have formed a partnership and have opened an advertising firm....

    Problem 17-7 Three recent college graduates have formed a partnership and have opened an advertising firm. Their first project consists of activities listed in the following table. Use Table B TIME IN DAYS Immediate Activity Predecessor Optimistic Most Likely Pessimistic 12 15 End E, G, I b.What is the probability that the project can be completed in 24 days or less? In 21 days or less? (Round your te and z values to 2 decimal places and "Standard deviation" to...

  • Three recent college graduates have formed a partnership and have opened an advertising firm. Their first...

    Three recent college graduates have formed a partnership and have opened an advertising firm. Their first project consists of activities listed in the following table. Use Table B. TIME IN DAYS Activity Immediate Predecessor Optimistic Most Likely Pessimistic A — 5 6 7 B — 8 8 11 C A 6 8 11 D — 9 12 15 E C 5 6 9 F D 5 6 7 G F 2 3 7 H B 4 4 5 I H...

  • Three recent college graduates have formed a partnership and have opened an advertising firm. Their first...

    Three recent college graduates have formed a partnership and have opened an advertising firm. Their first project consists of activities listed in the following table. Use Table B. TIME IN DAYS Activity Immediate Predecessor Optimistic Most Likely Pessimistic A — 5   6          7          B — 8   8          11          C A 6   8          11          D — 9   12          15          E C 5   6          9          F D 5   6          7         ...

  • You are responsible for managing a project with the following activities (all times are given in...

    You are responsible for managing a project with the following activities (all times are given in weeks): Optimistic Most Likely Pessimistic Immediate Time Predecessor(s) Time Activity Time 4 C, D D, E 12 4 8 6 4 What is the expected time of completion of the project? (weeks) (Include 1 decimal place, e.g.,3.1.) abs What is the probability that the project will be completed in 24 weeks or less? (Provide ab 2 decimal places, no 90 sign, e.g., 2.12 for...

  • H m Problem 21 Question Help Recently, you were assigned to manage a project for your...

    H m Problem 21 Question Help Recently, you were assigned to manage a project for your company. You have constructed a network diagram depicting the various activities in the project (shown below to the right). In addition, you have asked your team to estimate the amount of time that they would expect each of the activities to take. Their responses are shown in the following table: Time Estimates (days) Most Likely Activity Optimistic Pessimistic A 4 8 12 5 12...

  • Problem 9-17 The Porsche Shop, founded in 1985 by Dale Jensen, specializes in the restoration of...

    Problem 9-17 The Porsche Shop, founded in 1985 by Dale Jensen, specializes in the restoration of vintage Porsche automobiles. One of Jensen's regular customers asked him to prepare an estimate for the restoration of a 1964 model 356SC Porsche. To estimate the time and cost to perform such a restoration, Jensen broke the restoration process into four separate activities: disassembly and initial preparation work (A), body restoration (B), engine restoration (C), and final assembly (D). Once activity A has been...

  • Problem 9-09 (Algorithmic) At a local university, the Student Commission on Programming and Entertainment (SCOPE) is...

    Problem 9-09 (Algorithmic) At a local university, the Student Commission on Programming and Entertainment (SCOPE) is preparing to host its first rock concert of the school year. To successfully produce this rock concert, SCOPE has listed the requisite activities and related information in the following table (duration estimates measured in days). Immediate Most Activity Predecessor(s) Optimistic Probable Pessimistic A: Negotiate contract with - 9 10 11 selected musicians B: Reserve site - 7 9 11 C: Manage travel logistics A...

  • Coleman Rich Control Devices, Inc., produces custom-built relay devices for auto makers. The most recent project...

    Coleman Rich Control Devices, Inc., produces custom-built relay devices for auto makers. The most recent project undertaken by Rich requires 14 different activities. Rich's managers would like to determine the total project completion time (in days) and those activities that lie along the critical path. The appropriate data are shown in the following table: பா் Immediate Immediate Time (days) Time (days) Predecessor(s) Activity Predecessor(s) b b Activity a 6 E, F G, H A 4 5 8 3 3 B...

  • A small software development project has eight major activities. The times are estimated and prov...

    A small software development project has eight major activities. The times are estimated and provided in the table below: Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessor(s) A 3 4 5 -- B 5 7 9 -- C 2 3 10 A D 2 5 8 B E 1 7 7 B F 3 5 7 C, D G 7 8 9 D, E H 2 6 10 F Answer the following questions based on above table 1-2...

  • Recently, you were assigned to manage a project for your company. You have constructed a network...

    Recently, you were assigned to manage a project for your company. You have constructed a network diagram depicting the various activities in the project (shown below to the right). In addition, you have asked your team to estimate the amount of time that they would expect each of the activities to take. Their responses are shown in the following table: ơ Time Estimates (days) Optimistic Most Likely Pessimistic Activity ơ ال 7 کره ) | Start Finish 6 ای یا...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT