Perform a PERT analysis. For all high-level activities in this project, calculate the following:
1. Optimistic time
2. Most likely time
3. Pessimistic time
4. Expected activity time
5. Standard deviation
6. Variance
7. For one date ahead of most likely completion date, calculate Z and hence the probability of completion by that date.
8. For one date behind the most likely completion date, calculate Z and hence the probability of completion by that date.
The data
Project Mile Stone
Start - 08:00 8/8/2019 & Finish 12 pm 6/4/2020
Mobilization
Start - 08:00 4/9/2019 & Finish 2 pm 25/9/2019
Procurement & construction
Start - 08:00 8/8/2019 & Finish 3 pm 31/3/2020
Demobilization
Start - 07:00 2/4/2020 & Finish 12 pm 6/4/2020
Crushing line
Start - 08:00 8/8/2019 & Finish 3 pm 31/3/2020
Conveyor
Start - 15:00 14/10/2019 & Finish 1 pm 14/1/2020
Infrastructure
Start - 13:00 28/11/2019 & Finish 3 pm 31/3/2020
Civils
Start - 14:00 14/10/2019 & Finish 5 pm 8/11/2019
Structural & Mechanical
Start - 14:00 11/11/2019 & Finish 5 pm 1/1/2020
Electrical
Start - 00:00 13/11/2019 & Finish 1 pm 14/1/2020
SL.NO | NAME | TIME | |||||
1 | projProject Mile Stone | 239 4H | |||||
2 | Procurement & construction | 233 7H | |||||
3 | Crushing line | 233 7H | |||||
4 | Mobilization | 21 6H | |||||
5 | Conveyor | 91 22H | |||||
6 | Civils | 27 3H | |||||
7 | Structural & Mechanical | 51 3H | |||||
8 | Electrical | 31 13H |
Perform a PERT analysis. For all high-level activities in this project, calculate the following: ...
PERT Analysis: The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 3 8 14 B - 8 8 8 C A 6 9 18 D B 6 11 17 According to the data in the above Table: What is the critical path? What is the minimum expected completion time for the project? According to the above Table, there are four activities in the project....
The table below shows the output from a system that uses PERT for project scheduling. The project involves 12 interdependent activities and all times are reported in weeks. Based on the information provided, answer the following questions: IMMEDIATE EXPECTED ACTIVITY PREDECESSORS TIME EARLIEST EARLIEST LATEST LATEST START FINISH START FINISH 16 BNS lolos 12 4 31 28 43 32 10 6 38 D, J, K (a) What is the minimum expected time required to complete the project? (b) How is...
Consider the following project activities: Calculate the expected time (te) for each activity. Draw an Activity on Node (AON) diagram to reflect the flow of these activities. Calculate the Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF) for each activity. Calculate the slack for each activity. Identify all activities on the Critical Path. Use the data to calculate the probability the project will finish in 20 weeks (Hint: z-score). Activity A 8 с D E...
1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...
Question 13 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) A 2 B 3 с 2 D A,B 5 E CD F D 4 G E 2 1 Determine the duration of the project. a. 13 weeks b. 12 weeks OC. 11 weeks d. 10 weeks e. 9 weeks Question 14 Assume that activity F has the following times: Early start time (ES) =...
Pert project method Activity Predecessors A group 5 optimistic Most likely Pessimistic Expected Variance a m b Time (t) o 2 3 2 1 B с D NWN mlm A 1 A,B 2 4 1 6 7 9 F 1 с с DE F,G 4 2 5 3 G 4 12 H 2 4 From the table above find the flowing answers. 1. Construct the project Network 2. Find the expected duration and Variance of each activity 3. Find the...
HOMEWORK ASSIGNMENT FOR PROJECT MANAGEMENT 13. An automation project has the following activities and related data Time (weeks)Crash Immed. Maximum Activity Prede- Opti- Most Cost/week Crashable Mean Varice cessors mistic (a) Likely (m) mistic (c (S1000) Weeks E(t) V(t) C A 5 D A 4 E B1 F B1 G C,D,E 2 6 6 HF2 12 15 3 13a. (5 points) Compute the mean and variance of each activity and record them on the table above. 13b. (5 points) Develop...
NETWORK: PERT 4 - Consider the following table: ACTIVITY PREC. ACT. TIME ESTIMATES tml - 2 (days) tp c D, E 1) Construct a PERT network. [NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.) 2) By using ES, EF, LF, LS, find the slack of each activity and the critical path. 3) Find the completion time (x) and the standard deviation (6) for the project-...
You are responsible for managing a project with the following activities (all times are given in weeks): Optimistic Most Likely Pessimistic Immediate Time Predecessor(s) Time Activity Time 4 C, D D, E 12 4 8 6 4 What is the expected time of completion of the project? (weeks) (Include 1 decimal place, e.g.,3.1.) abs What is the probability that the project will be completed in 24 weeks or less? (Provide ab 2 decimal places, no 90 sign, e.g., 2.12 for...
Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the amount of time it took to complete several recent jobs. Some of his workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are given in the following table: Activity: a,b.c.d.e.f.g.h.i.j,k Time.(Days ) A, M, B, predecessors A= 2, 5, 9, zero B=...