5) Coolant circulation pump X for continuous operation in a nuclear power station has M yrs. and MTTR 10 hrs. A standby older pump Y with the same capacity is also used with MTBF -22 mo. and MTTR...
5) Coolant circulation pump X for continuous operation in a nuclear power station has MTBF = 2 yrs. and MTTR = 10 hrs. A standby older pump Y with the same capacity is also used with MTBF = 22 mo. and MTTR = 15 hrs. Perfect switching between pumps A and B of the plant is assumed. (i) Draw the detailed Markov process graph of the cooling pump system and determine the limiting (steady-state) probability of all states that it...
5) Coolant circulation pump X for continuous operation in a nuclear power station has MTBF = 2 yrs. and MTTR = 10 hrs. A standby older pump Y with the same capacity is also used with MTBF = 22 mo. and MTTR = 15 hrs. Perfect switching between pumps A and B of the plant is assumed. (i) Draw the detailed Markov process graph of the cooling pump system and determine the limiting (steady-state) probability of all states that it...