Answer 1 | |||
Year | 2021 | 2022 | 2023 |
Cost incurred during the year | $ 2,523,000 | $ 3,177,000 | $ 1,980,000 |
Cumulative cost incurred at end of year | $ 2,523,000 | $ 5,700,000 | $ 7,680,000 |
Cumulative cost incurred at end of year | $ 2,523,000 | $ 5,700,000 | $ 7,680,000 |
Add: Estimated costs to complete as of year-end | $ 6,177,000 | $ 1,800,000 | $ 0 |
Total estimated cost | $ 8,700,000 | $ 7,500,000 | $ 7,680,000 |
Percentage of completion (cumulative cost incurred at end of year / Total estimated cost) | 29.00% | 76.00% | 100.00% |
Revenue recognized till the date (10000000 * percentage of completion) | $ 2,900,000 | $ 7,600,000 | $ 10,000,000 |
Less: Revenue recognized up to earlier year | $ 0 | $ 2,900,000 | $ 7,600,000 |
Revenue recognized in current year | $ 2,900,000 | $ 4,700,000 | $ 2,400,000 |
Revenue recognized in current year | $ 2,900,000 | $ 4,700,000 | $ 2,400,000 |
Less: cost incurred during the year | $ 2,523,000 | $ 3,177,000 | $ 1,980,000 |
Gross Profit (Loss) | $ 377,000 | $ 1,523,000 | $ 420,000 |
Date | General Journal | Debit | Credit |
2021 | Construction in progress | 2,523,000 | |
Various Accounts | 2,523,000 | ||
(To record cost incurred in Progress.) | |||
2021 | Accounts receivable | 2,070,000 | |
Billings on construction contract | 2,070,000 | ||
(To record Billings to Customer.) | |||
2021 | Cash | 1,835,000 | |
Accounts receivable | 1,835,000 | ||
(To record cash collected from customer.) | |||
2021 | Construction in progress | 377,000 | |
Cost of construction | 2,523,000 | ||
Construction Revenue | 2,900,000 | ||
(To record recognize Revenue.) | |||
2022 | Construction in progress | 3,177,000 | |
Various Accounts | 3,177,000 | ||
(To record cost incurred in Progress.) | |||
2022 | Accounts receivable | 3,630,000 | |
Billings on construction contract | 3,630,000 | ||
(To record Billings to Customer.) | |||
2022 | Cash | 3,400,000 | |
Accounts receivable | 3,400,000 | ||
(To record cash collected from customer.) | |||
2022 | Construction in progress | 1,523,000 | |
Cost of construction | 3,177,000 | ||
Construction Revenue | 4,700,000 | ||
(To record recognize Revenue.) | |||
2023 | Construction in progress | 1,980,000 | |
Various Accounts | 1,980,000 | ||
(To record cost incurred in Progress.) | |||
2023 | Accounts receivable | 4,300,000 | |
Billings on construction contract | 4,300,000 | ||
(To record Billings to Customer.) | |||
2023 | Cash | 4,765,000 | |
Accounts receivable | 4,765,000 | ||
(To record cash collected from customer.) | |||
2023 | Construction in progress | 420,000 | |
Cost of construction | 1,980,000 | ||
Construction Revenue | 2,400,000 | ||
(To record recognize Revenue.) | |||
2023 | Billings on construction contract | 10,000,000 | |
Construction in progress | 10,000,000 | ||
(To record completion of contract.) |
Calculation | 2021 | 2022 |
Beginning Accounts receivable | 235,000 | |
Billings | 2,070,000 | 3,630,000 |
Less: Collections | 1,835,000 | 3,400,000 |
Accounts receivable | 235,000 | 465,000 |
Partial Balance sheet | 2021 | 2022 | ||
Current assets | ||||
Accounts receivable | 235,000 | 465,000 | ||
Construction in progress | $ 2,900,000 | $ 7,600,000 | ||
Less: Billings (for 2022 = 2070000 + 3630000) | 2,070,000 | 5,700,000 | ||
Cost and profit in Excess of Billings | 830,000 | 1,900,000 |
Required information IThe following information apples to the questions displayed below. In 2021, the Westgate Cons...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs to complete as of year-end 5,184,000 2,376,000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs to complete as of year-end 5,184,000 2,376,000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,016,000 $ 2,808,000 $ 2,613,600 Estimated costs to complete as of year-end 5,184,000 2,376,000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the...
! Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2022 $3, 984, 000 1, 826, 000 4, 444, 000 3, 900, 000 2021 $2, 490, 000 2023 $2, 008, 600 Cost incurred during the year Estimated costs to complete as of year-end Billings during...
Required information (The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,259,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,291,000 5,609,000 2,110,000 1,855,000 2022 $3,555,000 2,054,000 3,736,000 3,500,000 4,154,000 4,645,000...
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,230, 800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,610,000 6,390,000 2,100,000 1,850,000 2022 $3,162,000 2,028,000 3,672,000 3,000,000 4,228,000...
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,016,000 5,184,000 2,180,000 1,890,000 2022 $2,808,000 2,376,000 2,644,000 2,500,000 2023 $2,613,600 0 5,176,000...
The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000...
Required information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,424, 400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,204,000 5,396,000 2,140,000 1,870,000 2022 $3,192,000 2,204,000 3,256,000 3,200,000 4,604,000...