Fix gross profit (loss) in requirement 5 only
DONT USE THIS WAY
Gross profit recognized = revenue -actual cost
2018 3,000,000-2,400,000 = 600,000
2019 3,019,400-3,800,000 = -780,600
2020 -100,000 actual loss - profit recognized in 2018 - loss recognized in 2019
= -100,000 - 600,000 - (-780,600)
=80600
2020 gross profit = 80600
I POSTED THIS QUESTION TWICE BEFORE AND THEY USED THIS METHOD AND IT IS NOT CORRECT
IT IS WRONG I DONT WANT TO SEE IT AGAIN
I DONT WANT TO SEE -300,000 ON 2019
I DONT WANT TO SEE -100,000 ON 2020
ALL WRONG AS SHOWN
In 2018, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2020. Information related to
the contract is as follows:
FIX
2018 | 2019 | 2020 | |||||||
Cost incurred during the year | $ | 2,400,000 | $ | 3,600,000 | $ | 2,200,000 | |||
Estimated costs to complete as of year-end | 5,600,000 | 2,000,000 | 0 | ||||||
Billings during the year | 2,000,000 | 4,000,000 | 4,000,000 | ||||||
Cash collections during the year | 1,800,000 | 3,600,000 | 4,600,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
Required:
1. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years.
2-a. In the journal below, complete the necessary
journal entries for the year 2018 (credit "Various accounts" for
construction costs incurred).
2-b. In the journal below, complete the necessary
journal entries for the year 2019 (credit "Various accounts" for
construction costs incurred).
2-c. In the journal below, complete the necessary
journal entries for the year 2020 (credit "Various accounts" for
construction costs incurred).
3. Complete the information required below to
prepare a partial balance sheet for 2018 and 2019 showing any items
related to the contract.
4. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years assuming
the following costs incurred and costs to complete information.
2018 | 2019 | 2020 | |||||||
Cost incurred during the year | $ | 2,400,000 | $ | 3,800,000 | $ | 3,200,000 | |||
Estimated costs to complete as of year-end | 5,600,000 | 3,100,000 | 0 | ||||||
5. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years assuming
the following costs incurred and costs to complete information.
2018 | 2019 | 2020 | |||||||
Cost incurred during the year | $ | 2,400,000 | $ | 3,800,000 | $ | 3,900,000 | |||
Estimated costs to complete as of year-end | 5,600,000 | 4,100,000 | 0 | ||||||
5)
2018 | 2019 | 2020 | |
estimated cost to complete [A] | 5600000 | 4100000 | 0 |
cost incurred till date[B] | 2400000 | 2400000+3800000= 6200000 | 6200000+3900000=10100000 |
Total cost to complete [A+B] | 8000000 | 10300000 | 10100000 |
**Cost incurred till date = Cost incurred till last period+ cost incurred during the current year
2018 | 2019 | 2020 | |
% of completion [cost incurred till date /total cost to complete] | 2400000/8000000 | 6200000/10300000 | 10100000/10100000 |
30% | 60.19417% | 100% |
2018 | 2019 | 2020 | |
Revenue to recognized {(Contract price *%of completion)-revenue recognized till date} | {(10,000,000*30%)-0}=3000000 |
{(10000000*60.19417%)-3000000} {6019400-3000000) 3019400 |
{(10,000,000*100%)-6019400} {10,000,000-6019400} 3980600 |
Gross profit (Revenue recognized -cost incurred during the year) | 3000000-2400000= 600000 | -900000 | 200000 |
***since in 2019 ,the total cost to complete exceeds contract price ,any loss on contract should be immediately recognized as per accounting principle .
Loss on contract = 10000000-10300000= -300000
Gross profit /(loss) to recognize in year 2019 = profit/(loss) on contract - any profit recognized in earlier years
= -300000- 600000
= -900000
2020;
Profit/(loss) on contract = 10000000-10100000= -100000
Gross profit /(loss) to recognized in 2020 = -100000-(-300000)
= -100000 +300000
= 200000
Fix gross profit (loss) in requirement 5 only DONT USE THIS WAY Gross profit recognized = revenue -actual cost 2018 3,00...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,200,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,400,000 5,600,000 2,000,000 1,800,000 2022 $3,600,000 2,000,000 4,000,000 3,600,000 4,000,000 4,600,000 Assume that Westgate Construction's contract with Santa Clara County does not...
Fix Problem 5-12 Long-term contract; revenue recognized over time; loss projected on entire project [LO5-9] Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,000,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The...
Required information The following information applies to the questions displayed below.) In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $2,200,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,400,000 5,600,000 2,000,000 1,800,000 2019 $3,600,000 2,000,000 4,000,000 3,600,000 4,000,000 4,600,000...
Required information (The following information applies to the questions displayed below.) In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $1,940,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,604,000 5,796,000 2,040,000 1,820,000 2019 $4,032,000 1,764,000 4,596,000 4,000,000 3,364,000 4,180,000...
it says it's incomplete, please help On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,600,000. During 2018, costs of $2,200,000 were incurred with estimated costs of $4,200,000 yet to be incurred. Billings of $2,700,000 were sent, and cash collected was $2,450,000. In 2019, costs incurred were $2,700,000 with remaining costs estimated to be $3,900,000. 2019 billings were $2,950,000 and $2,675,000 cash was collected. The project was completed...
Problem 6-11 (Algo) Long-term contract; revenue recognition upon completion (LO6-9) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $1,797,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $3,096,000 5,504,000 2,600,000 2,400,000 2022 $3,870,000 1,634,000 4,366,000 4,200,000 3,034,000 3,400,000 Assume...
omework Saved Help Save & Exit Submit Check my work Exercise 5-19 Long-term contract; revenue recognition over time; loss projected on entire project [LO5-9] On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,180,000. During 2018, costs of $2,060,000 were incurred with estimated costs of $4,060,000 yet to be incurred. Billings of $2,560,000 were sent, and cash collected was $2,310,000. In 2019, costs incurred were $2,560,000 with remaining...
Required information The following information applies to the questions displayed below) In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $2,200,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,400,000 5,600,000 2,000,000 1,800,000 2019 $3,600,000 2.000.000 4,000,000 3,600,000 4.000.000 4.600.000...
3. On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2018, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2019, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2019 billings were $2,850,000 and $2,575,000 cash was collected. The project was completed in 2020 after additional costs...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,125,000. During 2018, costs of $2,050,000 were incurred, with estimated costs of $4,050,000 yet to be incurred. Billings of $2,560,000 were sent, and cash collected was $2,300,000. In 2019, costs incurred were $2,560,000 with remaining costs estimated to be $3,675,000. 2019 billings were $2,810,000, and $2,525,000 cash was collected. The project was completed in 2020 after additional costs of...