Question

a) The Walter Group provides the following data for June 2019 when 15,000 units were manufactured. Standard Material cos...

a) The Walter Group provides the following data for June 2019 when 15,000 units were manufactured.

Standard Material cost (per Unit) 8.50kg @ $7.50 per Kg.

Actual Material cost (Per Unit) 6.75Kg @ $13.5 per Kg.

Standard Labour cost (Per Unit) 5.5hrs @ $15 per hour

Actual Labour cost (Per Unit) 6.5hrs @ $12.2 per hour

Calculate the following:

1. Direct Material Variance

2. Direct Material Quantity/Usage Variance

3. Total Material Cost Variance

4. Direct Labour rate Variance

5. Direct Labour efficiency Variance

6. Total Labour Cost Variance

b) Calculate variable overhead spending variance if actual labour hours used are 260, standard variable overhead rate is $10.40 per direct labour hour and actual variable overhead rate is $9.30 per direct labor hour. Also specify whether the variance is favorable or unfavorable.

c) Define the term Variance Analysis and highlight its Advantages and Disadvantages

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Data for material variances:

Standard quantity of direct material for 15,000 units = 15,000 units * 8.50 Kg per unit = 127,500 Kgs

Standard rate per Kg of direct material = $7.50 per Kg

Standard cost of direct material = 127,500 Kgs * $7.50 per Kg = $956,250

Actual quantity of direct material for 15,000 units = 15,000 units * 6.75 Kg per unit = 101,250 Kgs

Actual rate per Kg of direct material = $13.50 per Kg

Actual cost of direct material = 101,250 Kgs * $13.50 per Kg = $13,66,875

1. Direct material price variance = (Standard rate per unit - Actual rate per unit) * Actual quantity of direct material

= ($7.50 - $13.50) * 101,250 Kg = $607,500 (U) Unfavorable Variance

2. Direct material usage variance = (Standard quantity of direct material - Actual quantity of direct material) * Standard rate

= (127,500 Kg - 101,250 Kg) * $7.50 = $196,875 (F) Favorable Variance

3. Total Material Cost Variance = Standard cost of direct material - Actual cost of direct material

= $956,250 - $ 13,66,875 = $410,625 (U) Unfavorable Variance

Data for labor variances:

Standard hours of direct labor for 15,000 units = 15,000 units * 5.50 hours per unit = 82,500 hours

Standard rate per hour of direct labor = $15 per hour

Standard cost of direct labor = 82,500 hours * $15 per hour = $12,37,500

Actual hours of direct labor for 15,000 units = 15,000 units * 6.50 hour per unit = 97,500 hours

Actual rate per hour of direct labor = $12.20 per hour

Actual cost of direct labor = 97,500 hours * $12.20 per hour = $11,89,500

4. Direct labor rate variance = (Standard rate per hour - Actual rate per hour) * Actual direct labor hours

= ($15 - $12.20) * 97,500 hours = $273,000 (F)   Favorable Variance

5. Direct labor efficiency variance = (Standard hours - Actual hours) * Standard rate per direct labor hour

= (82,500 hours - 97,500 hours) * $15  = $225,000 (U) Unfavorable Variance

6. Total Labor Cost Variance = Standard cost of direct labor - Actual cost of direct labor

= $12,37,500 - $ 11,89,500 = $48000 (F) Favorable Variance

7. Data for variable overhead spending variance

Actual direct labor hours used (Given) = 260 direct labor hours

Standard variable overhead rate (Given) = $10.40 per labor hour

Actual variable overhead rate (Given) = $9.30 per labor hour

Variable overhead spending variance = (Standard variable overhead rate - Actual variable overhead rate) * Actual direct labor hours

= ($10.40 - $9.30) * 260 direct labor hours

= $286 (F)   Favorable Variance

Add a comment
Know the answer?
Add Answer to:
a) The Walter Group provides the following data for June 2019 when 15,000 units were manufactured. Standard Material cos...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A.(i) Moment Inc. provides the following data for June 2016 when 15,000 Units are manufactured: S...

    A.(i) Moment Inc. provides the following data for June 2016 when 15,000 Units are manufactured: Standard Material Cost (Per Unit) 8.50 kg @ $ 7.50/kg Actual Material Cost (Per Unit) 6.75 kg @ $ 13.5/kg Standard Labor cost (Per Unit) 5.5 hrs @ $ 15/hr Actual Labor cost (Per Unit) 6.5 hrs @ $ 12.2/hr Calculate: Direct Material Price Variance Direct Material Quantity/Usage Variance Total Material Cost Variance Direct Labor Rate Variance Direct Labor Efficiency Variance Total Labor Cost Variance...

  • Black and Decker Corporation has the following information is for their standard and actual costs: Standard...

    Black and Decker Corporation has the following information is for their standard and actual costs: Standard Costs: Budgeted units of production - 9,000 (100% of capacity) Standard material per unit - 12 lbs. Standard material cost - $14.00 per pound Standard labor hours per unit - 12 Standard labor rate - $29.00 per hour Standard variable overhead rate - $7.50 per labor hour Budgeted fixed overhead - $729,000 Fixed overhead rate is based on budgeted labor hours at 100% capacity...

  • Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...

    Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 6 kg at $9.00 per kg Direct labour: 3 hours at $15 per hour Variable overhead: 3 hours at $5 per hour $ 54.00 45.00 15.00 Total standard cost per unit $ 114.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...

  • Question 27 At the end of June, the manager of the B.C. manufacturing plant was provided...

    Question 27 At the end of June, the manager of the B.C. manufacturing plant was provided with the following variance analysis report. Favourable (F)/ Unfavourable (U) Budget 310,000 Actual 323,000 Variance 13,000 п Production in units Production costs: Direct material Direct labour Variable overhead costs Fixed overhead costs Total production costs $742,109 1,395,000 131,750 147,250 $2,416,109 $749,581 1,420,440 135,821 139,870 $2,445,712 $(7,472) (25,440) (4,071) 7,380 $(29,603) псс с The manager immediately called the production supervisor, demanding an explanation for the...

  • The monthly budget of Steelworks, manufacturers of specialist cabinets, was prepared on the following specification:

    The monthly budget of Steelworks, manufacturers of specialist cabinets, was prepared on the following specification:Production and sales30 000 unitsSelling priceR80 per unitDirect materials input5 kg per unit at a cost of R1,20 per kgDirect labour input2 hours per unit at a rate of R4 per hourVariable overheadR2 per direct labour hourFixed overheadR110 000 per monthThe following actual results were recorded for the month of August:Stock of finished goods at start of month8 000 unitsSales40 000 unitsProduction42 800 unitsStock of finished...

  • Question: Waterways Continuing Problem 12 At the end of June the manager of the B.C. manufacturing...

    Question: Waterways Continuing Problem 12 At the end of June the manager of the B.C. manufacturing plant was provided with the following variance analysis report: Favourable (F)/ Unfavourable (U) Budget Actual Variance Production in units 310,000 323,000 13,000 Production costs: Direct material $(11,781) (25,440) (4,538) $737,800 $749,581 U Direct labour Variable overhead costs Fixed overhead costs 1,395,000 131,750 147,250 1,420,440 U 136,288 U 139,870 7,380 F Total production costs $(34,379) $2,411,800 $2,446,179 U The manager immediately called the production supervisor,...

  • A company produces a product which has a standard variable production cost of $8 per unit made up as follows:          ...

    A company produces a product which has a standard variable production cost of $8 per unit made up as follows:                                                                $ Per Unit Direct material                                 $4.60 (2kg X $2.30 per kg) Direct labour                                     $2.10 (0.7 hours x $3.00 per hour) Variable overhead                          $1.3 Fixed manufacturing costs are treated as period costs. The following information is available for the period just ended, Variable manufacturing cost of sales (at standard cost)                                  $263,520 Opening stock of finished goods (at standard cost)                                         $120,800 Closing...

  • tic microcomputer cases at a selling price of $10.00 machine hours. The standard variable costs per...

    tic microcomputer cases at a selling price of $10.00 machine hours. The standard variable costs per Containers, Inc. produced 62,500 and sold 59,000 plastic micr each. Manufacturing overhead is allocated on the basis of machine hours. computer case were: Quantity Rate Direct Materials 1.5 kg $ 1.20 per kg Direct Labour 0.50 labour hours $ 15.00 per hour Variable Overhead 0.20 machine hours $6.00 per hour Total $1.80 7.50 1.20 Information regarding fixed overhead includes the following: Budgeted Fixed Overhead:...

  • answere 7 to 11 7) During June, Bradley Company produced 4,000 units of product. The standard...

    answere 7 to 11 7) During June, Bradley Company produced 4,000 units of product. The standard cost card indicates the following labour standards per unit of output: 3.5 hours @ $6 per hour $21. During the month, the company worked 15.000 hours. The standard hours allowed for the month were a) 14,000 hours. b) 15,000 hours. c) 24,000 hours. d) 18,000 hours. 8) Refer to the data in question 17) above. What is the labour efficiency variance for June? a)...

  • Waterways Continuing Problem 12 At the end of June the manager of the B.C. manufacturing plant...

    Waterways Continuing Problem 12 At the end of June the manager of the B.C. manufacturing plant was provided with the following variance analysis report: Budget Actual Variance Favourable (F)/ Unfavourable (U) Production in units 332,000 347,000 15,000 F Production costs:    Direct material $996,000 $1,017,940 $(21,940) U    Direct labour 1,411,000 1,442,700 (31,700) U    Variable overhead costs 166,000 172,957 (6,957) U    Fixed overhead costs 174,300 168,620 5,680 F Total production costs $2,747,300 $2,802,217 $(54,917) U The manager immediately called the production supervisor,...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT