Question

Considering the following data for a project begun in 2018 by Timber Construction, with a contract price of $3,000,000....

Considering the following data for a project begun in 2018 by Timber Construction, with a contract price of $3,000,000. Dominion’s customer controls the building during the period of construction.

2018

2019

Current period costs

$360,000

$440,000

Estimated additional costs to complete

1,440,000

800,000

Progress billings

350,000

300,000

Collection on billings-current year

200,000

200,000

Using the table below, calculate the revenue to be recognized by Timber Construction during 2018 and 2019. Assume that percentage of completion is measured by the ratio of costs incurred to date divided by total estimated construction costs. .

Be sure to include ALL of your calculations in the table including the gross profit earned by Timber Construction in each year. Express gross profit margin in dollars and in percentage terms for each year.

Round all your percentage calculations to the nearest whole percent.

Using the information in your table, prepare all of the required journal entries for 2018 only.

Year(s)

2018

2019

General Journal

Date

Account Titles and Explanation

Debit

Credit

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Hey Dear,

Hope you are also doing well.

I have tried to give best possible answer. If you have any doubts, please mention in comment.

%E1 48 2000hz $ : (onu x 90 % - Lyold ssaulo (x ; $09) (? - 111) tifold rould ( 00000h $ noooh 8$ $600000 (w) Revenue to be rJournal Entry Zate ACLOUGH Title Emplanation Де» Credit 2018 Construction in progress (CIP) $360000 Accounts payable $3600002019 Construction in progress $ 400000 Expenses $ 440000 Revenue $840000

Thanks Dear, Have a Wonderful Day.

Add a comment
Know the answer?
Add Answer to:
Considering the following data for a project begun in 2018 by Timber Construction, with a contract price of $3,000,000....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 3. On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2018, costs of $2,100,000 were incurred...

    3. On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2018, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2019, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2019 billings were $2,850,000 and $2,575,000 cash was collected. The project was completed in 2020 after additional costs...

  • Bob Ltd signs a contract on 1 April 2018 to build an office building. The construction...

    Bob Ltd signs a contract on 1 April 2018 to build an office building. The construction is scheduled to commence 1 July 2018 and the estimated date of completion is 30 June 2021. The cost of the building is estimated to be $155m and the total contract price is fixed at $180m. The following data relates to the construction period: For the year ended 30 June 2019 2020 2021 $’000 $’000 $’000 Costs to date 46,500 108,500 155,000 Estimated Costs...

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,060,000. During 2018, costs of $2,020,000 were incurred with estimated costs of $4,020,000 yet to be incurred. Billings of $2,520,000 were sent, and cash collected was $2,270,000. In 2019, costs incurred were $2,520,000 with remaining costs estimated to be $3,630,000. 2019 billings were $2,770,000 and $2,495,000 cash was collected. The project was completed in 2020 after additional costs of...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,490,000 5,810,000 2,030,000 1,815,000 2019 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion. 3....

  • During 2017, Pearl Company started a construction job with a contract price of $1,610,000. The job...

    During 2017, Pearl Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 –0– Billings to date 301,000 897,000 1,610,000 Collections to date 271,000 817,000 1,428,000 A) Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ 258,000 Gross...

  • During 2017, Nilsen Company started a construction job with a contract price of $1,600,000. The job...

    During 2017, Nilsen Company started a construction job with a contract price of $1,600,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $400,000 $825,000 $1,070,000 Estimated costs to complete 600,000 275,000 –0– Billings to date 300,000 900,000 1,600,000 Collections to date 270,000 810,000 1,425,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2017 $ Gross profit recognized...

  • McCombs Contractors received a contract to construct a mental health facility for $2,500. Construction was begun...

    McCombs Contractors received a contract to construct a mental health facility for $2,500. Construction was begun in 2023 and completed in 2024. Cost and other data are presented below: 2024 $1,300 Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year 2023 $1,500 1,200 1,200 1,000 1,300 1,500 1. Compute the amount of revenue and gross profit recognized during 2023 and 2024. 2. Assume that McCombs recognizes revenue on this contract over...

  • During 2017, Cullumber Company started a construction job with a contract price of $1,610,000. The job...

    During 2017, Cullumber Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 -0- 1,610,000 Billings to date 301.000 897,000 271,000 1428,000 Collections to date 817,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used $ Gross profit recognized in 2017 $ Gross profit...

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,125,000. During 2018, costs of $2,050,000 were incurred, with estimated costs of $4,050,000 yet to be incurred. Billings of $2,560,000 were sent, and cash collected was $2,300,000. In 2019, costs incurred were $2,560,000 with remaining costs estimated to be $3,675,000. 2019 billings were $2,810,000, and $2,525,000 cash was collected. The project was completed in 2020 after additional costs of...

  • On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $360 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year Estimated costs to complete as of December 31 S 30 140 $40...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT