Question

50 70 24 Question 3 (a) Explain the term limiting factor in a production strategy and give four (4) examples (b) Xexe Ltd p

c. assuming labor hours is a limiting factor in the period, advise management on the most appropriate mix if labor hours is limited to 45,000hrs

d. assuming, material is a limiting factor in the period, advise management on the most appropriate mix if materials is limited to 55,000kgs in the period

e. which product should the company office concentrate more of its materials and labour and why?

0 0
Add a comment Improve this question Transcribed image text
Answer #1
a & b Product A Product B Product C Product D Total
Sales per unit 50 70 80 100
Variable cost per unit(Material + Labour) 18 40 34 34
Contribution margin per unit 32 30 46 66
Fixed allocated on the basis of Maximum demand 2500 2500 2500 2500
Break even point(Fixed cost allocated/CM per unit) 78 83 54 38
c Maximum demand 3000 3000 3000 3000
Contribution margin per unit 32 30 46 66
No. of hours per unit 3 2 7 5
Contribution margin per hours 10.67 15.00 6.57 13.20
Ranking based on CM per hour III I IV II
Maximum hours required 9000 6000 21000 15000 51000
Allocation of 45,000 labour hours based on ranking 9000 6000 15000 15000 45000
d Maximum demand 3000 3000 3000 3000
Contribution margin per unit 32 30 46 66
Materials per unit 3 9 5 6
Contribution margin per material 10.67 3.33 9.20 11.00
Ranking based on CM per material II IV III I
Maximum materials 9000 27000 15000 18000 69000
Allocation of 45,000 labour hours based on ranking 9000 3000 15000 18000 45000
e The company concentrate on Product D as it has the highest contribution margin per unit
Add a comment
Know the answer?
Add Answer to:
c. assuming labor hours is a limiting factor in the period, advise management on the most appropriate mix if labor h...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • a)calculate the breakeven point of units for each product b)assuming, materials is a limiting factor in...

    a)calculate the breakeven point of units for each product b)assuming, materials is a limiting factor in the period, advise management on the most appropriate mix c)assuming labour is a limiting factor in the period, advise management on the most appropriate mix d)which product should the company office concentrate more of its materials and labour on and why? e)compute the total contribution the company would earn from the production mix determined in (b) above UUU Question 1 cts (giving a Explain...

  • A. Assuming use of direct-labor hours to apply overhead to production, compute the unit manufacturing costs...

    A. Assuming use of direct-labor hours to apply overhead to production, compute the unit manufacturing costs of the Standard and Enhanced products if the expected manufacturing volume is attained. Manufacturing cost per unit: Standard $ ? and Enhanced $ ? B. Assuming use of activity-based costing, compute the unit manufacturing costs of the Standard and Enhanced products if the expected manufacturing volume is attained. Manufacturing cost per unit: Standard $ ? and Enhanced $ ? C. By using direct-labor hours...

  • Variances questions, Introduction To Management Accounting 2 help me in all of them please if possible....

    Variances questions, Introduction To Management Accounting 2 help me in all of them please if possible. thank you. QUESTION -VARIANCES 2 The standard cost card for product Z shows the following details: Standard costs per unit of Z produced: 4 kgs of material A €3.10 per kg 3 litres of material B @ €1.70 per litre 2.5 hours of direct labour €12 per hour Variable production overhead @ €10 per direct labour hour Standard factory cost per unit 12.40 5.10...

  • QUESTION 2 2 points Save Afirm with a standard costing system budgets 5,000 direct labor hours at $20 per hours t...

    QUESTION 2 2 points Save Afirm with a standard costing system budgets 5,000 direct labor hours at $20 per hours to make 2,000 units. The firm actually produced 2,000 units using 6,000 direct labor hours at $22 per hour. When labor occurred during the period, what was the total dollar value of the credit to wages payable? QUESTION 3 2 points Tolton, Inc. is just shy of hitting its operating income target. The manager. KT. Tolton, decides to purchase inferior...

  • The Engineering Manager in A Company Ltd. is responsible for maximising the profit from four product...

    The Engineering Manager in A Company Ltd. is responsible for maximising the profit from four product lines A, B, C and D. They have been provided with the following information Direct materials (kgs) 80 90 95 70 Direct labour (hrs) Welding Assembly Finishing 4.5 3.5 9.5 4 Selling price per unit (E) 1500 2500 3000 1000 Max.sales for the period in units) 400 300 280 450 250 250 250 250 Budgeted production (in units) Additional information is also provided i....

  • Q.2 As Engineering Manager in Your Company Ltd. you are responsible for maximising the profit from...

    Q.2 As Engineering Manager in Your Company Ltd. you are responsible for maximising the profit from four product lines W, X, Y and Z. You have been provided with the following information Direct materials (kg) 75 90 85 70 Direct labour (h) 3.5 Fabrication Assembly Packaging 4.5 8 3.5 4.5 9.5 4 Selling price per unit (£) 1400 2350 3000 1200 300 450 Max. sales for the period (in units) 400 280 280 Budgeted production (in units) 300 270 270...

  • please answer these questions. 6. In producing 12,400 units of product last period, Fern LTD. used...

    please answer these questions. 6. In producing 12,400 units of product last period, Fern LTD. used S53,940 pounds of Material B, costing $210,366. The company has established the standard of using 4.3 pounds of Material B per unit of product, at a price of $4.00 per pound Calculate the price, quantity, and total materials variances and indicate if they are favorable or unfavorable. Variance amount F or U Price variance aubisteluale Quantity variance Total materials variance hubniasxa baol toubong isdrio...

  • Q.3 Answer all parts Total 20 marks] The Engineering Manager in A Company Ltd. is responsible...

    Q.3 Answer all parts Total 20 marks] The Engineering Manager in A Company Ltd. is responsible for maximising the profit from four product lines A, B, C and D. They have been provided with the following information; Direct materials (kgs) 80 90 95 70 Direct labour (hrs) Welding Assembly Finishing 4.5 9.5 4 3.5 4 8 4 4.5 4 Selling price per unit (E) 1500 2500 3000 1000 300 450 Max.sales for the period (in units) 400 280 250 Budgeted...

  • Q.3 Answer all parts Total 20 marks] The Engineering Manager in A Company Ltd. is responsible...

    Q.3 Answer all parts Total 20 marks] The Engineering Manager in A Company Ltd. is responsible for maximising the profit from four product lines A, B, C and D. They have been provided with the following information; Direct materials (kgs) 80 95 70 Direct labour (hrs) Welding Assembly Finishing 4.5 9 4 4.5 9.5 4 3.5 4 8 4 Selling price per unit (E) 1500 2500 3000 1000 280 Max.sales for the period in units) 400 300 450 250 250...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT