Schedule of Cost | |||||||
Job 101 | Job 102 | Job 103 | Job 104 | Total | |||
Direct material | 2200 | 5700 | 7100 | 1700 | 16700 | ||
Direct Labour | 2700 | 6800 | 9200 | 2100 | 20800 | ||
Manufacturing Overheads | 1200 | 2000 | 3800 | 1000 | 8000 | ||
Total | 6100 | 14500 | 20100 | 4800 | 45500 | ||
Journal entries: | |||||||
S.no. | Accounts title and explanations | Debit $ | Credit $ | ||||
a. | Raw material Inventory | 37000 | |||||
Accounts payable | 37000 | ||||||
b. | Work in process inventory | 16700 | |||||
Manufacturing Overheads | 1350 | ||||||
Raw material inventory | 18050 | ||||||
c & d. | Work in process inventory | 20800 | |||||
Manufacturing Overheads | 2250 | ||||||
Wages payable | 23050 | ||||||
e. | Manufacturing Overheads | 2400 | |||||
Accounts payable | 2400 | ||||||
Job Order Cost; Journal Entries; Ending Work in Process; Inventory Analysis Sultan, Inc. manufactures goods to...
Sultan, Inc. manufactures goods to special order and uses a job order cost system. During its first month of operations, the following selected transactions took place REQUIRED: 1) Prepare journal entries to record the transactions. 2) Compute the ending balance in Work in Process. 3) Compute the ending balance in Finished Goods. a. $37,000 b. $ 2,200 5,700 7,100 1,700 1,350 C. Materials purchased on account. Materials issued to the factory: Job 101 ....... Job 102 Job 103. Job 104...
P1-9 Data analysis; manufacturing statement Glasson Manufacturing Co. produces only one product. You have obtained the following information from the corporation's books and records for the current year ended December 31, 2016: a. Total manufacturing cost during the year was $1,000,000, including direct materials, direct labor, and factory overhead. b. Cost of goods manufactured during the year was $970,000. c. Factory Overhead charged to Work in Process was 75% of direct labor cost and 27% of the total manufacturing cost....
Chapter 2 Job Order Cost Problem Hi Gloss Printing Company uses a job order cost system. The following data summarize the operations related to production for June, the first month of operations: a. (Pts. 4) Materials purchased on account, $43,500. b. (Pts. 18) Materials requisitioned and factory labor used, use one entry for materials and a separate entry for factory labor Materials Factory Labor Job 101 $9.000 $5,700 2,890 Job 103 3,100 Job 104 2,240 Job 105 8,500 4,060 Job...
Entries and Schedules for Unfinished Jobs and Completed Jobs Hildreth Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations: Materials purchased on account, $2,110. Materials requisitioned and factory labor used: Job No. Materials Factory Labor 101 $2,440 $2,460 102 2,980 3,320 103 1,980 1,620 104 6,690 6,100 105 4,250 4,650 106 3,100 2,950 For general factory use 830 3,640 Factory overhead costs incurred on account, $4,660....
Entries and Schedules for Unfinished Jobs and Completed Jobs Hildreth Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations: Materials purchased on account, $3,350. Materials requisitioned and factory labor used: Job No. Materials Factory Labor 101 $2,610 $2,330 102 3,180 3,150 103 2,110 1,540 104 7,150 5,780 105 4,540 4,400 106 3,310 2,800 For general factory use 890 3,450 Factory overhead costs incurred on account, $4,990....
Entries and Schedules for Unfinished Jobs and Completed Jobs Hildreth Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations: Materials purchased on account, $2,820. Materials requisitioned and factory labor used: Job No. Materials Factory Labor 101 $2,600 $2,090 102 3,170 2,820 103 2,110 1,380 104 7,120 5,180 105 4,520 3,950 106 3,300 2,510 For general factory use 880 3,090 Factory overhead costs incurred on account, $4,970....
Entries and Schedules for Unfinished Jobs and Completed Jobs Hildreth Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations: Materials purchased on account, $2,820. Materials requisitioned and factory labor used: Job No. Materials Factory Labor 101 $2,600 $2,090 102 3,170 2,820 103 2,110 1,380 104 7,120 5,180 105 4,520 3,950 106 3,300 2,510 For general factory use 880 3,090 Factory overhead costs incurred on account, $4,970....
Entries and Schedules for Unfinished Jobs and Completed Jobs Hildreth Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations: Materials purchased on account, $2,690. Materials requisitioned and factory labor used: Job No. Materials Factory Labor 101 $1,840 $2,910 102 2,240 3,930 103 1,490 1,920 104 5,040 7,220 105 3,200 5,500 106 2,340 3,490 For general factory use 630 4,310 Factory overhead costs incurred on account, $3,510....
Entries and Schedules for Unfinished Jobs and Completed Jobs Hildreth Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations: Materials purchased on account, $3,320. Materials requisitioned and factory labor used: Job No. Materials Factory Labor 101 $2,300 $3,280 102 2,810 4,430 103 1,860 2,160 104 6,300 8,130 105 4,000 6,200 106 2,920 3,940 For general factory use 780 4,850 Factory overhead costs incurred on account, $4,390....
Entries and Schedules for Unfinished Jobs and Completed Jobs Hildreth Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations: Materials purchased on account, $3,280. Materials requisitioned and factory labor used: Job No. Materials Factory Labor 101 $2,220 $1,890 102 2,710 2,550 103 1,800 1,250 104 6,080 4,690 105 3,860 3,570 106 2,820 2,270 For general factory use 750 2,800 Factory overhead costs incurred on account, $4,240....