2) The following tasks been assigned for a project following the steps needed to develop a project network. Show al necessary steps and graphical representations. Find: 1 Critical Path for this project 2) Total free slack times for each activity 3) Total completion Time 4) The latest time that the activity D must be started to complete the project by...
In the following table the activities with their precedence sequence and expected time (days) are listed for a project: Activity Immediate Predecessor(s) Time (days) S A Figure 1 C A 4 5 5 F 5 F G E, F D GH 2 3 H The correct AOA precedence diagram is shown in a Figure 2 Q Figure 3
tual code de a Activity Predecessor Normal time A 2 B 3 C B A С 5 G. F H 15 HH 2 D И N M, J 1 - Calculate early start (ES), early finish (EF), late start (LS) and late finish (LF) for each activity - Draw Activity on Arrow network (AOA) - Draw Activity on Node network...
1) Construct an activity on arrow (AOA) network based on the activity description below. Activity Predecessors A - B A C A D A E B, C F E G F H G
Case-2 Consider that you have an interview in a construction firm and they asked you to develop an (AOA) network for a construction project has the following activities along with their relationships. Draw your suggested network. (15 Marks) (The project was started in activity A and it is the precedence of activities B,C,D &E, the activity B is followed by...
Given the following table, construct the network diagram, either AOA or AON. Times are in days a. Determine the expected duration of the project. b.Compute the probability that the project will take at least 18 days. Path Activity Time Estimates 4-5-6 7-8-10 3-6-9 7-8-10 2-3-4 1-4-6 Top Bottom E Path Activity Time Estimates 4-5-6 7-8-10 3-6-9 7-8-10 2-3-4 1-4-6 Top...
Please solve the following problems related to Chapter 17: Project Management: 1. Based on the following AOA diagram, please answer the following question: (1) Determine the critical path and the expected project duration (2) Determine the following quantities for each activity: the earliest start time, the latest start time, the earliest finish time and the latest finish time and the...
c. (5 points) If time is measured in days, what is the minimum number of days the project can be completed? 5. For the tolowing project petwork the tmes for each actvity are listed m tbe tatla below. Thare should be circles and arrows cornecting some of the circles, in the diagram below. If these are not visible or did...
For the following project with times to complete activities in weeks: ActivityDepend on a m b 1 3 6 2 3 6 3 79 2 23 34 5 B,C (a) Calculate the expected time and variance for each activity. Draw the project network (AOA). Determine the critical path, expected completion time and variance. (b) Determine the probability of finishing the...
Basic Project Management Lesson 6. Exercises 1. The AOA diagram of a project is shown below. The duration of each activity in days is shown by its side. a. Calculate the earliest and latest schedules of each event. b. Show the critical path by thickening the critical arrows. c. Fill in the Slack Table. -- a 15 Start Finish 11...