In all of the exercises involving variances, use “F” and “U” to designate favorable and unfavorable variances, respectively.
(Appendix) Calculating factory overhead: four variances
Gonzo Gasket Co. budgets 8,000 direct labor hours for the year. The total overhead budget is expected to amount to $20,000. The standard cost for a unit of the company’s product estimates the variable overhead as follows:
Variable factory overhead (3 hours @ $2 per direct labor hour) . . . . $6 per unit
The actual data for the period follow:
Actual completed units. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2,500
Actual direct labor hours. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7,640
Actual variable overhead. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $16,100
Actual fixed overhead . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3,920
Using the four-variance method, calculate the overhead variances.
(Hint: First compute the budgeted fixed overhead rate.)