Question

A warehouse has to meet the demand for a product shown below. Each unit of stock remaining at the end of a month has a notional holding cost of 20. If there are shortages, 20 % of orders are lost with a cost of 200 a unit, and the rest are met by late deliveries with a cost of 50 a unit. A production department sends the product to the warehouse. Designed capacity of this department is 400 units a month, but utilization seldom exceeds 80 %. Every time the production rate is changed it costs 15 000.

How would you set about designing an aggregate plan for the product?

Month Aggregate demand 310 280 260 300 360 250 160 100

In preparing your answers you can use a spreadsheet software.

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Maximum Production 400*80% 320 units

Shortage Cost (In case of even One Unit Shortage)

1 2 3 4 5 6 7 8
24800 22400 20800 24000 28800 20000 12800 8000

Month 1 Shortage cost : 310*20%*200# + 310*80%*50# = 24800

#Provided in question

In the First Month the Shortage Cost Comes around Rs. 24,800/- So definitely we cannot afford have a shortage. The Max. Production in QTY is 320 Units. For 310 units demand in the first month if we produce 320 units it will increase our holding cost. so in month 1 we produce 310 Units.

Production Plan for 8 months

Month 1 2 3 4 5 6 7 8
Production 310 310 310 310 310 310 80 80
excess units 0 30 80 90 40 100 20 0

Month 2 Holding cost : 30*20# = 600

#Provided in question

Holding cost for Above

1 2 3 4 5 6 7 8
0 600 1600 1800 800 2000 400 0

cost on Change in production rate

1 2 3 4 5 6 7 8
0 0 0 0 0 0 15000 0

Total Cost = 22,200

upto month 6 the same production pattern of 310 units can be maintained and if we change the production rate in between it will cost us Rs.15000/- . So out of 8 months, production rate has been changed for only one month to minimize the cost and to equalize demand and supply. Production rate is changed on month 7 because changing it in earlier months and producing remaining demand equally over the remaining months gives rise to shortage cost and if we plan to reduce shortage cost by changing the production rate again it will cost another 15,000/-. Therefore production rate is changed on month 7 and remaining demand has been produced equally over remaining months.

Result:

Production pattern

Month 1 2 3 4 5 6 7 8
Production 310 310 310 310 310 310 80 80

Total Cost 22,200/-

  

Add a comment
Know the answer?
Add Answer to:
A warehouse has to meet the demand for a product shown below. Each unit of stock...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 13-4 The current aggregate demand requirements for a firm are shown below for the next...

    Problem 13-4 The current aggregate demand requirements for a firm are shown below for the next six months MonthMay June July Aug Sept Oct Demand 260 240 240 240 270 290 The firm always plans to meet all demand. The firm currently has 260 workers capable of producing 260 units in a month (1 unit/worker). The workforce can be increased (at a cost of $650 (at a cost of $1,300 per worker). Inventory holding cost is $150 per unit per...

  • The current aggregate demand requirements for a firm are shown below for the next six months:...

    The current aggregate demand requirements for a firm are shown below for the next six months: Month May June July Aug Sept Oct Demand 270 250 250 250 280 300 The firm always plans to meet all demand. The firm currently has 270 workers capable of producing 270 units in a month (1 unit/worker). The workforce can be increased (at a cost of $700 per worker) or decreased (at a cost of $1,400 per worker). Inventory holding cost is $175...

  • Check The current aggregate demand requirements for a firm are shown below for the next six...

    Check The current aggregate demand requirements for a firm are shown below for the next six months: Month May June July Aug Sept Oct 230 Demand 210 210 210 240 260 Click here for the Excel Data File The firm always plans to meet all demand. The firm currently has 230 workers capable of producing 230 units in a month (1 unit/worker). The workforce can be increased (at a cost of $500 per worker) or decreased (at a cost of...

  • A firm must plan production for the next six months. Each unit costs $370 to produce...

    A firm must plan production for the next six months. Each unit costs $370 to produce and it has an inventory holding cost of $23 per unit per month based on ending inventory levels. The cost to hire a worker is $220, and the cost to fire a worker is $440 per worker. Each worker produces 10 units per month There are 20 persons on the payroll at the beginning of the first month. The company currently has 150 units...

  • The current aggregate demand requirements for a firm are shown below for the next six months:...

    The current aggregate demand requirements for a firm are shown below for the next six months: Month May June July Aug Sept Oct Demand 230 210 210 210 240 260 PpictureClick here for the Excel Data File ped The firm always plans to meet all demand. The firm currently has 230 workers capable of producing 230 units in a month (1 unit/worker). The workforce can be increased (at a cost of $500 per worker) or decreased (at a cost of...

  • The demand for a product is 12,500 units for a three month period. Each unit of...

    The demand for a product is 12,500 units for a three month period. Each unit of product has a purchase price of $15 and ordering costs are $20 per order placed. The annual holding cost of one unit of product is 10% of its purchase price. What is the Economic Order Quantity (to the nearest unit)?

  • A product has a demand of 436 units per month. Ordering cost is $20, and holding...

    A product has a demand of 436 units per month. Ordering cost is $20, and holding cost is $4 per unit per year. The EOQ model is appropriate. The total management cost (holding and setup costs only) for this product will be per year. demand 436 per month order cost $20 per order holding cost $4 per unit per year Excel Access QUESTION 29 A drone company builds its own motors, which are then put into each drone. While the...

  • Makes skis, unow boar and high end sledding equsipment As shown below,t Slopes & S the demand for...

    makes skis, unow boar and high end sledding equsipment As shown below,t Slopes & S the demand for its peoducts is highly seasonal. The company empleys 10 workers who can each produce 200 units of various eqipmest per s limaited to regla production each period Subcontracting is unlimined Haring and fxing costs are $500 per workn laventory holding coss are $2 per unit per month Grven the estimates of demand below, a. the current workforce level (uapplemented with overtime and...

  • A firm must plan production for the next six months. Each unit costs $430 to produce...

    A firm must plan production for the next six months. Each unit costs $430 to produce and it has an inventory holding cost of $15 per unit per month based on ending inventory levels. The cost to hire a worker is $280, and the cost to fire a worker is $560 per worker. Each worker produces 10 units per month. There are 20 persons on the payroll at the beginning of the first month. The company currently has 150 units...

  • 1) All 20 consumers are alike and each has a demand curve for a monopolist's product...

    1) All 20 consumers are alike and each has a demand curve for a monopolist's product of p=12-2q. The cost of production C(Q)=Q. Let the monopolist charge a price of $r per unit purchased and a subscription fee of $F that must be paid by each producer. Find the r and F that maximize profits. a) What is r? b) What is F? c) What is the maximum profit the monopolist can earn in this market? (pi) 2)All 200 consumers...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT