Given:
AC = $78,000, PV = $84,000, EV = $81,000, AT = 70 days
Cost variance = EV – AC = $81,000 - $78,000 = $3,000
Schedule variance: EV – PV = $81,000 - $84,000 = -$3000
CPI = EV/AC = 1.03
SPI = EV/PV = 0.96
Cost Schedule Index = EV^2/(AC)(PV) = ($81,000)^2/($78,000)($84,000)Cost Schedule Index = 6,561,000,000 / 6,552,000,000
Cost Schedule Index = 1.001
Time Variance = ST –AT = (AT)(CSI)–AT = (70)(1.001)–70
Time Variance = 0.07 days
3. A software development project at day 70 exhibits an actual cost of $78,000 and a...
For a project, in X day, planned value, earned value and actual cost of the tasks are given in dollar in the table below. Planned $1000 to complete project. Task Actual Cost Work Performed Budgeted Cost Work Scheduled 50 70 30 100 50 2 3 4 5 Budgeted Cost Work Performed 50 70 30 50 0 Total: 250 a. Find schedule and cost variance. Explain what it means? b. Find schedule and cost performance index. c. Find estimate to complete...
#1. A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000. For the work performed to date, the budgeted value is $272,000. What are the cost and schedule variances for the project? What are the SPI and CPI? What is your assessment of the project from a cost and schedule perspective? #2. A project has just completed the 87th item in its plan. It was scheduled to have spent $168,000 at...
2. Find the schedule and cost variances for a project that has as actual cost at month 16 of $540,000, a scheduled cost of $523,000, and an earned value of $535,000. What do the results tell you?
7. Given an activity in an advertising project whose planned cost was $12,000 but actual cost to date is $10,000 so far and the value completed is only 70 percent, calculate the cost and schedule variances. Will the client be pleased or angry?
Determine the schedule and cost variance for a project that has an actual cost at month 10 of $600,000, a scheduled cost of $600,000 and an earned value of $600,000.
5. A consulting project has an actual cost in month 10 of $23.000, a scheduled cost of $17,000, and a value com pleted of $20,000. Find the schedule and cost variances and the three indexes.
CodeHead Software Inc. does software development. One important activity in software development is writing software code. The manager of the WordPro Development Team determined that the average software programmer could write 25 lines of code in an hour. The plan for the first week in May called for 4,650 lines of code to be written on the WordPro product. The WordPro Team has five programmers. Each programmer is hired from an employment firm that requires temporary employees to be hired...
6. A project to develop technology training seminars is 5 days behind schedule at day 65. It had a planned cost of $735,000 for this point in time, but the actual cost is only $550,000. Estimate the schedule and cost variances. Re-estimate the variances if the actual cost had been $750,000
Your project to obtain charitable donations is now 43 days into a planned 53-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 37 days of the project and to bring in $25,900. Even though we are 43 days into the project, we still see that we have only 89% of this activity complete. The second activity relates to company donations and is scheduled to...
2. A sales project at month 5 had an actual cost of $34,000, a planned cost of $42,000, and a value completed of $39,000. Find the cost and schedule variances and the CPI and SPI