Question

Determine the schedule and cost variance for a project that has an actual cost at month...

Determine the schedule and cost variance for a project that has an actual cost at month 10 of $600,000, a scheduled cost of $600,000 and an earned value of $600,000.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

BCWP = budgeted cost of work performed = (Earned Value)

ACWP = actual cost of work performed

BCWS =budgeted cost of work scheduled

BCWP = $600,000.

ACWP = $600,000.

BCWS = $600,000.

Schedule variance = SV = BCWP - BCWS = $600,000. - $600,000 = $ 0

Cost variance = CV = BCWP - ACWP = $600,000 - $600,000 = $ 0

Add a comment
Know the answer?
Add Answer to:
Determine the schedule and cost variance for a project that has an actual cost at month...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT