B-E-G is the critical path
And the project duration is 21 as per the given information
QUESTION 20 The critical path of the project outlined below has been determined of B-F-H. What is the slack time for activity F? Time Immediate Activity (wks) Predecessor(s) A 7 B B с 2 А D 2 А E 3 B F 5 G 9 CE H 8 DF B
What is the critical path? Start-A-D-G-End O Start-A-D-F-End Start-A-E-G-End O Start-B-E-G-End What is the EF (earliest finish) of activity E? o o ООООО < N N What is the LS (latest start) of activity E? ООООО The list of activities, their times (in weeks), and precedence relationships for a new project are given below. Activity Immediate Predecessor Activity Time A L - L 4 B - 1 2 C - A, B F DL 4 G C, D, E What...
QUESTION 17 The critical path of the projected below as been determine what they Activity Time Immediate Predecessor A 7 8 C 2 A D A E F 5 G CE 8 D. QUESTION 17 A B The critical path of the project outlined below has been mined of B-F-H. What is the slack time for activity F? Time Immediate Activity (wks) Predecessor(s) 7 8 с 2 А A E B F G 9 CE H 8 DF D 2...
For the network shown D(4) B(12) E(6) G(4) C(6) F(5) a-1. Determine the critical path A-C-E-G A-C-F-G A-B-D-G A-B-E-G a-2. Determine the early completion time in weeks for the project. Early completion time For the data shown, reduce the project completion time by three weeks. Assume a linear cost per week shortened weeks NORMAL NORMAL CRASH CRASH ACTIVITY TIME COST TIME COST $ 7,300 2$13,400 18,200 6,550 6,800 5,400 9,000 8,400 7 12 6 12,400 10 5,400 4,500 3,200 6,700...
Let U ={a, b, c, d, e, f, g, h, i, j, k}. Let A={d, f, g, h, i, k}. Let B={a, d, f, g, h}. Let C={a, c, f. i, k} Determine (AUC) U ( AB). Choose the correct answer below and, if necessary, fill in the answer box in your choice. OA. (AUC) U(ANB)= } (Use a comma to separate answers as needed.) OB. (A'UC) U (ANB) is the empty set. LE This Question: 1 pt Let U={x|XEN...
You perform interrupted conjugation using an a+b+c+d+e+f+g+h+ Hfr strain and an F– strain that is a–b–c–d–e–f–g–h–. You observe the following genes transferred together in order from last to first: h+b+g+d+ e+f+d+g+ f+e+a+c+ What is the map order of the genes?
D Question 6 5 pts Project B: What is/are the critical path(s) for this project? Activity Immediate Predecessor Activity Duration 6 A,B D,E G,F BDFH BEGH and CGH BEFH BEGH
Question i: Calculate the dates PI and PT for each activity.
Identify the Project Critical Path. Is it posible to finish the
Project in 42 weeks? [Explain your answer in slide 3]
Question ii: Imagine that Activity A actually ends in 3 weeks, the
B in 12 weeks and the C in 13 weeks. Recalcula la fecha de
terminación del proyecto. In what activities would you focus on to
readjust the Project so that it is completed in less than...
Given a chromosome with the gene order, A B C D ∙ E F G H, and an inverted chromosome with this gene order, A F E ∙ D C B G H, which of the following recombinant chromosomes would result from a crossover between C and D? A) A B C C B G H and H G F E ∙ D C B G H B) A B C D ∙ E F A and H ∙ G...
Consider the following project network and activity times (in weeks): Start Finish Activity | A B C D E F G H Time 5 37 6 7 310 8 a. Identify the critical path. b. How much time will be needed to complete this project? c. Can activity D be delayed without delaying the entire project? If so, by how many weeks? d. Can activity C be delayed without delaying the entire project? If so, by how many weeks? What...