In the given case,
Contract for building a factory = $15 million
The contractor incurred a cost of $1 million on the construction up to December 31, 2008.
Estimated cost of completion of contract = $15 million
Particulars | Amount ($) |
Cost of construction of factory incurred 31.12.2008 | 1 million |
Add :- estimated future cost | 15 million |
Total estimated cost of construction | 16 millions |
Contract price | 15 millions |
Stage of completion
Percentage of completion till date to total estimated cost of construction = (1÷16)×100 = 6.25%
Revenue and profit to be recognised for the year 31st December 2008 = $15 millions × 6.25% = $937500
Loss for the year 31.12.2008 = $1milliion - $937500 = $62500.
From the given contract,
We can recognise the revenue of $937500 and a loss of $62500.
These are all information required to solve the above given question.
I hope, all the above mentioned information and calculations are useful and helpful to you.
If there is any clarifications required regarding there were provided answer, please mention them in comment box.
Thank you.
Questions Bigtime Builders Limited undertook a contract for building a factory for $ 15 million. The...
1.Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp. at a fixed contract price of $27.5 million on 6/15/2016. Construction of the building is completed on 12/15/2018. Hometown Construction expects the building to be completed in two and a half years and uses the Percentage of Completion Method (cost to cost approach) to account for the contract. Cost information related to the contract are as follows: 2016 2017 2018 Actual Construction costs incurred...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging from 10−20 homes and are typically sold during construction or soon after. To secure the home upon completion, buyers must pay a deposit of 10% of the price of the home with the remaining balance due upon completion of the house and transfer of title. Failure to pay the full amount results in forfeiture...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging from 10–20 homes and are typically sold during construction or soon after. To secure the home upon completion, buyers must pay a deposit of 10% of the price of the home with the remaining balance due upon completion of the house and transfer of title. Failure to pay the full amount results in forfeiture...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging from 10−20 homes and are typically sold during construction or soon after. To secure the home upon completion, buyers must pay a deposit of 10% of the price of the home with the remaining balance due upon completion of the house and transfer of title. Failure to pay the full amount results in forfeiture...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging from 10−20 homes and are typically sold during construction or soon after. To secure the home upon completion, buyers must pay a deposit of 10% of the price of the home with the remaining balance due upon completion of the house and transfer of title. Failure to pay the full amount results in forfeiture...
Citation Builders, In., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging from 10-20 homes and are typically sold during construction or soon after. To secure the home upon completion, buyers must pay a deposit of 10% of the price of the home with the remaining balance due upon completion of the house and transfer of title. Failure to pay the full amount results in forfeiture...
Sunland Construction is constructing an office building under contract for Cannon Company and uses the percentage-of-completion method. The contract calls for progress billings and payments of $1250000 each quarter. The total contract price is $18546000 and Sunland estimates total costs of $17900000. Sunland estimates that the building will take 3 years to complete, and commences construction on January 2, 2018 At December 31, 2019, Sunland Construction estimates that it is 80% complete with the building: however, the estimate of total...
Hubbard Building Company signed a contract with a customer on November 1, 2016. The contract called for construction of a building to begin by December 31, 2016, and to be completed by December 31, 2017. The contract price was $8.0 million. Hubbard estimated that the building would cost $5 million. On November 15, 2016, the customer was required to make an advance payment of $1,000,000. No work was done on the project until January 2017. How much income from the...
1.2 Dundee limited undertook a contract for N$500 000 on 1st January 2018. On 31 December 2018 when the accounts were closed, the following details about the contract were gathered Particulars Materials purchased Wages paid General expenses Plant Purchased Materials on hand 31-12-2018 Wages accrued 31-12-2018 Work certified Cash received De Work uncertified 100,000 45,000 10,000 50,000 25,000 5,000 200,000 50,000 5,000 15,000 ation of Plant The above contract contained an escalator clauses which read as follows: In the event...
On March 1, 2017, Bonita Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,450,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $2,824,800 $2,086,300 $2,418,900 Estimated costs to complete the contract at 12/31 3,595,200 2,418,900 –0– Billings...