E9-2 Computing profit or loss on a bid Sebastian and Whitley, plumbers, successfully bid $30,000 for the plumbing work on a n
0 Balanced Scorecard, and Quality Costs profit or loss on the job in (a) dollars and (b) as a 515 Compute the profit or loss
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1.

Total direct costs = $2,500

Direct labor cost = $9,500

Overhead = 150$ of direct labor cost

= 9,500 x 150%

= $14,250

Total cost = Other direct costs + Direct labor cost + Overhead

= 2,500+9,500+14,250

= $26,250

(a)

Profit = Bid price - Total costs

= 30,000-26,250

= $3,750

(b)

Profit percentage = Profit/Bid price

= 3,750/30,000

= 12.5%

2.

Direct labor cost + overheads

= 9,500+14,250

= $23,750

Direct labor cost plus overhead as a percentage of total cost = 23,750/26,250

= 90.4%

Kindly comment if you need further assistance.

Thanks‼!

Add a comment
Know the answer?
Add Answer to:
E9-2 Computing profit or loss on a bid Sebastian and Whitley, plumbers, successfully bid $30,000 for...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Blast said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers...

    Blast said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $2,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and operates a job order costing system. Manufacturing overhead cost is applied to jobs on the basis of direct labor cost. The following estimates were made at the beginning of the...

  • Markup on Cost, Cost-Based Pricing Arthur Quillen Construction Company is a general contractor that specializes in...

    Markup on Cost, Cost-Based Pricing Arthur Quillen Construction Company is a general contractor that specializes in custom residential housing. Each job requires a bid that includes Quillen’s direct costs and subcontractor costs as well as an amount referred to as “overhead and profit.” Quillen’s bidding policy is to estimate the costs of direct materials, direct labor, and subcontractors’ costs. These are totaled, and a markup is applied to cover overhead and profit. In the coming year, the company believes it...

  • Question: Exercise 2-5 Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Overhead Rates...

    Question: Exercise 2-5 Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Overhead Rates [LO2-4] Exercise 2-5 Computing Total Job Costs and Unit Product Costs Using Multiple Predetermined Overhead Rates (LO2-4] Braverman Company has two manufacturing departments-Finishing and Fabrication. The predetermined overhead rates in Finishing and Fabrication are $13.00 per direct labor-hour and 120% of direct materials cost, respectively. The company's direct labor wage rate is $20.00 per hour. The following information pertains to Job 700: Direct materials...

  • Hello, what is the answer to the question? EXERCISE 2–3 Computing Total Job Costs and Unit...

    Hello, what is the answer to the question? EXERCISE 2–3 Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate LO2-3 @ Mickley Company's plantwide predetermined overhead rate is $14.00 per direct labor-hour and its direct labor wage rate is $17.00 per hour. The following information pertains to Job A-500: Direct materials $231 Direct labor $153 Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 40 units,...

  • Homework - Chapter 2 Saved 3 Exercise 2-3 Computing Total Job Costs and Unit Product Costs...

    Homework - Chapter 2 Saved 3 Exercise 2-3 Computing Total Job Costs and Unit Product Costs Using a Plantwide Predeterminecd Overhead Rate [LO2-3] 14.28 points Mickley Company's plantwide predetermined overhead rate is $22.00 per direct labor-hour and its direct labor wage rate is $15.00 per hour. The following information pertains to Job A-500: Direct materials Direct labor $ 210 $ 150 eBook Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of...

  • 2 Exercise 2-3 (Algo) Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined...

    2 Exercise 2-3 (Algo) Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate (LO2-3) 7.22 points Mickley Company's plantwide predetermined overhead rate is $24.00 per direct labor-hour and its direct labor wage rate is $15.00 per hour. The following information pertains to Job A-500: eBook Hint Direct materials Direct labor $ 240 $ 225 Print References Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 60...

  • Exercise 2-3 Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate...

    Exercise 2-3 Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate [LO2-3] Mickley Company's plantwide predetermined overhead rate is $22.00 per direct labor-hour and its direct labor wage rate is $15.00 per hour. The following information pertains to Job A-500: Direct materials Direct labor $ 210 $ 300 Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 30 units, what is the unit product cost for...

  • Exercise 2-3 Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate...

    Exercise 2-3 Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate [LO2-3) Mickley Company's plantwide predetermined overhead rate is $21.00 per direct labor-hour and its direct labor wage rate is $11.00 per hour. The following information pertains to Job A-500: Direct materials Direct labor Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 60 units, what is the unit product cost for this job? (Round your...

  • Exercise 2-3 Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate...

    Exercise 2-3 Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate (LO2-3] Mickley Company's plantwide predetermined overhead rate is $19.00 per direct labor-hour and its direct labor wage rate is $10.00 per hour. The following information pertains to Job A-500: Direct materials Direct labor $ 260 $ 100 Required: 1. What is the total manufacturing cost assigned to Job A-500? 2. If Job A-500 consists of 70 units, what is the unit product cost for...

  • Exercise 2-3 Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate...

    Exercise 2-3 Computing Total Job Costs and Unit Product Costs Using a Plantwide Predetermined Overhead Rate [LO2-3] Mickley Company's plantwide predetermined overhead rate is $19.00 per direct labor-hour and its direct labor wage rate is $14.00 per hour. The following information pertains to Job A-500: $ 240 $140 Direct materials Direct labor Required: 1. What is the total manufacturing cost assigned 2. If Job A-500 consists of 60 units, what is the unit product cost for this job? (Round your...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT