Question

QUESTION 2 – SENSITIVITY ANALYSIS (25 POINTS) Consider a project to supply Detroit with 40,000 tons...

QUESTION 2

SENSITIVITY ANALYSIS

(25 POINTS)

Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. You will need an initial $5,600,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $600,000 and that variable costs should be $250 per ton. Further, the accounting department will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life and estimate a salvage value of $450,000 after dismantling costs. The marketing department estimates that the automakers will let the contract at a selling price of $340 per ton. The engineering department estimates you will need an initial net working capital investment of $560,000. You require a return of 13 percent and face a marginal tax rate of 24 percent on this project.

Suppose you’re confident about your own projections, but you’re a little unsure about Detroit’s actual machine screw requirements.

a. What is the sensitivity of the project OCF to changes in the quantity

supplied?

b. What about the sensitivity of NPV to changes in quantity supplied?

c. Given the sensitivity number you calculated, is there some minimum level

of output below which you wouldn't want to operate?

0 0
Add a comment Improve this question Transcribed image text
Answer #1
40000 tons NPV calculations
Year 0 1 2 3 4 5 6
1.Initial Investment -5600000
2.Initial NWC -560000 560000
3.After tax Salvage(450000*(1-24%)) 342000
Operating Cash flows:
4.Sales revenue at 340/ton 13600000 13600000 13600000 13600000 13600000 13600000
5. Variable costs at 250/ton -10000000 -10000000 -10000000 -10000000 -10000000 -10000000
6.Fixed costs -600000 -600000 -600000 -600000 -600000 -600000
7.EBT(4+5+6) 3000000 3000000 3000000 3000000 3000000 3000000
8. Tax at 24% -720000 -720000 -720000 -720000 -720000 -720000
9.EAT(7+8) 2280000 2280000 2280000 2280000 2280000 2280000
10.Depn.tax shield(5600000-450000)/6*24% 206000 206000 206000 206000 206000 206000
11.OCF 2486000 2486000 2486000 2486000 2486000 2486000
12. Total annual C/fs(1+2+3+11) -6160000 2486000 2486000 2486000 2486000 2486000 3388000
13.PV F at 13%(1/1.13^Yr.n) 1 0.88496 0.78315 0.69305 0.61332 0.54276 0.48032
14.PV at 13%(12*13) -6160000 2200000 1946903 1722923 1524710 1349301 1627319
15. NPV(Sum of Row 14) 4211156
a.. OCF at 40000 tons
((40000*(340-250))-600000)*(1-24%)+206000=
2486000
OCF at 45000 tons
((45000*(340-250))-600000)*(1-24%)+206000=
2828000
Change in OCF for 5000 tons
2828000-2486000=
342000
So, sensitivity of OCF per ton=
342000/5000=
68.4
(for b.) NPV at
45000 tons
Year 0 1 2 3 4 5 6
1.Initial Investment -5600000
2.Initial NWC -560000 560000
3.After tax Salvage(450000*(1-24%)) 342000
Operating Cash flows:
4.Sales revenue at 340/ton 15300000 15300000 15300000 15300000 15300000 15300000
5.Variable costs at 250/ton -11250000 -11250000 -11250000 -11250000 -11250000 -11250000
6.Fixed costs -600000 -600000 -600000 -600000 -600000 -600000
7.EBT(4+5+6) 3450000 3450000 3450000 3450000 3450000 3450000
8. Tax at 24% -828000 -828000 -828000 -828000 -828000 -828000
9.EAT(7+8) 2622000 2622000 2622000 2622000 2622000 2622000
10. Depn.tax shield(5600000-450000)/6*24% 206000 206000 206000 206000 206000 206000
11.OCF 2828000 2828000 2828000 2828000 2828000 2828000
12. Total annual C/fs(1+2+3+11) -6160000 2828000 2828000 2828000 2828000 2828000 3730000
13.PV F at 13%(1/1.13^Yr.n) 1 0.88496 0.78315 0.69305 0.61332 0.54276 0.48032
14.PV at 13%(12*13) -6160000 2502654.9 2214739 1959946 1734465 1534925 1791588
15. NPV(Sum of Row 14) 5578318
b.Sensitivity analysis of NPV:
NPV at 40000 tons 4211156
NPV at 45000 tons 5578318
Change in NPV for 5000 tons 1367162
So, sensitivity of NPV per ton=
1367162/5000= 273.43
per ton
c.. YES.
c.Minimum level of output below which he will not operate will be at which output level,the NPV becomes 0
That can be found by using "Goal seek" function Excel,
Setting the cell containing the NPV value to 0
by changing the quantity (in tons) value
& the value got is
24598.91 tons
ie. 24599 tons
below which the NPV will be NEGATIVE.
Add a comment
Know the answer?
Add Answer to:
QUESTION 2 – SENSITIVITY ANALYSIS (25 POINTS) Consider a project to supply Detroit with 40,000 tons...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Consider a project to supply Tacoma with 40,000 tons of machine screws annually for automobile production....

    Consider a project to supply Tacoma with 40,000 tons of machine screws annually for automobile production. You will need an initial $5,600,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $600,000 and that variable costs should be $250 per ton. Further, the accounting department will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life and estimate a...

  • Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. - Initial investment of $5,600,000 in threading equipment - the project will last for 6 years. -The accounting department estimates that annual fixed costs will be $600,000 -variable costs should be $250 per ton. - depreciate initial investment straight-line to 0 over 6 years with salvage value of $450,000 -contract at selling price of $340 per ton - the engineering department estimates you will...

  • Consider a project to supply Detroit with 28,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 28,000 tons of machine screws annually for automobile production. You will need an initial $5,200,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,250,000 and that variable costs should be $235 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production. You will need an initial $4,500,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,075,000 and that variable costs should be $200 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $4,600,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,100,000 and that variable costs should be $205 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $4,600,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,100,000 and that variable costs should be $205 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $6,000,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,450,000 and that variable costs should be $275 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production with other de...

    Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production with other details as follows: - Initial investment of $5,600,000 in threading equipment - the project will last for 6 years. -The accounting department estimates that annual fixed costs will be $600,000 -variable costs should be $250 per ton. - depreciate initial investment straight-line to 0 over 6 years with salvage value of $450,000 -contract at selling price of $340 per ton - the...

  • Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. - Initial investment of $5,600,000 in threading equipment - the project will last for 6 years. -The accounting department estimates that annual fixed costs will be $600,000 -variable costs should be $250 per ton. - depreciate initial investment straight-line to 0 over 6 years with salvage value of $450,000 -contract at selling price of $340 per ton - the engineering department estimates you will...

  • Consider a project to supply Detroit with 20,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 20,000 tons of machine screws annually for automobile production. You will need an initial $3,600,000 Investment in threading equipment to get the project started, the project will last for 4 years. The accounting department estimates that annual fixed costs will be $850,000 and that variable costs should be $240 per ton; accounting will depreciate the initial fixed asset Investment straight-line to zero over the 4-year project life. It also estimates a salvage value...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT