Question

Consider a project to supply Tacoma with 40,000 tons of machine screws annually for automobile production....

Consider a project to supply Tacoma with 40,000 tons of machine screws annually for automobile production. You will need an initial $5,600,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $600,000 and that variable costs should be $250 per ton. Further, the accounting department will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life and estimate a salvage value of $450,000 after dismantling costs. The marketing department estimates that the automakers will let the contract at a selling price of $340 per ton. The engineering department estimates you will need an initial net working capital investment of $560,000. You require a return of 13 percent and face a marginal tax rate of 24 percent on this project.

Suppose you’re confident about your own projections, but you’re a little unsure about Tacoma’s actual machine screw requirements.

a. What is the sensitivity of the project OCF to changes in the quantity supplied?

b. What about the sensitivity of NPV to changes in quantity supplied?

c. Given the sensitivity number you calculated, is there some minimum level of output below which you wouldn’t want to operate?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

CF0=-Cost of equipment-working capital
CF1, CF2, CF3, CF4, CF5=((number of cartons*(price per carton-variable cost per carton)-fixed costs per year-depreciation)*(1-tax rate)+depreciation)
Additional cash flow in year 6=Salvage value*(1-tax rate)+working capital
Depreciation=Initial cost of equipment/5
NPV=CF0+CF1/(1+r)+CF2/(1+r)^2+CF3/(1+r)^3+CF4/(1+r)^4+CF5/(1+r)^5+CF6/(1+r)^6+Additional cash flow in year 6/(1+r)^6

a. What is the sensitivity of the project OCF to changes in the quantity supplied?
=(340-250)*(1-24%)
=68.4

b. What about the sensitivity of NPV to changes in quantity supplied?
=(340-250)*(1-24%)/13%*(1-1/1.13^6)
=273.4324056

c. Given the sensitivity number you calculated, is there some minimum level of output below which you wouldn’t want to operate?
-5600000-560000+560000/1.13^6+450000*(1-24%)/1.13^6+((Q*(340-250)-600000-5600000/6)*(1-24%)+5600000/6)/13%*(1-1/1.13^6)>=0
=>Q>=24335.755762

Add a comment
Know the answer?
Add Answer to:
Consider a project to supply Tacoma with 40,000 tons of machine screws annually for automobile production....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. - Initial investment of $5,600,000 in threading equipment - the project will last for 6 years. -The accounting department estimates that annual fixed costs will be $600,000 -variable costs should be $250 per ton. - depreciate initial investment straight-line to 0 over 6 years with salvage value of $450,000 -contract at selling price of $340 per ton - the engineering department estimates you will...

  • Consider a project to supply Detroit with 28,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 28,000 tons of machine screws annually for automobile production. You will need an initial $5,200,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,250,000 and that variable costs should be $235 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production. You will need an initial $4,500,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,075,000 and that variable costs should be $200 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $4,600,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,100,000 and that variable costs should be $205 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $4,600,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,100,000 and that variable costs should be $205 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $6,000,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,450,000 and that variable costs should be $275 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. - Initial investment of $5,600,000 in threading equipment - the project will last for 6 years. -The accounting department estimates that annual fixed costs will be $600,000 -variable costs should be $250 per ton. - depreciate initial investment straight-line to 0 over 6 years with salvage value of $450,000 -contract at selling price of $340 per ton - the engineering department estimates you will...

  • Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production with other de...

    Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production with other details as follows: - Initial investment of $5,600,000 in threading equipment - the project will last for 6 years. -The accounting department estimates that annual fixed costs will be $600,000 -variable costs should be $250 per ton. - depreciate initial investment straight-line to 0 over 6 years with salvage value of $450,000 -contract at selling price of $340 per ton - the...

  • QUESTION 2 – SENSITIVITY ANALYSIS (25 POINTS) Consider a project to supply Detroit with 40,000 tons...

    QUESTION 2 – SENSITIVITY ANALYSIS (25 POINTS) Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. You will need an initial $5,600,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $600,000 and that variable costs should be $250 per ton. Further, the accounting department will depreciate the initial fixed asset investment straight-line to zero over...

  • Consider a project to supply Detroit with 20,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 20,000 tons of machine screws annually for automobile production. You will need an initial $3,600,000 Investment in threading equipment to get the project started, the project will last for 4 years. The accounting department estimates that annual fixed costs will be $850,000 and that variable costs should be $240 per ton; accounting will depreciate the initial fixed asset Investment straight-line to zero over the 4-year project life. It also estimates a salvage value...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT