In an assembly line, the uniform time that each piece of work spends at a workstation...
The desired daily output for an assembly line is 540 units. This assembly line will operate 729 minutes per day. The following table contains information on this product's task times and precedence relationships: TASK TASK TIME (SECONDS) IMMEDIATE PREDECESSOR A 30 — B 28 A C 18 B D 69 B E 34 A F 36 E G 42 C, D H 24 F, G b. What is the workstation cycle time? Cycle time seconds c. Balance this line using...
9. A new product is to be assembled on a 100% manual assembly line. The line is designed to produce 120,000 units/yr. Work content time for the product is 39.5 min. The assembly line will operate 50 wklyr, 5 shifts/wk, 8 hr/shift. Expected line efficiency is 96%. There will be one worker per station. Determine (a) average hourly production rate, (b) cycle time, and (c) ideal minimum number of workstations.(6 pts)
9. A new product is to be assembled on...
An assembly line is to operate eight hours per day with a desired output of 160 units per day. The following table contains information on this product's task times and precedence relationships: IMMEDIATE PREDECESSOR TASK TIME (SECONDS) 100 TASK A 70 D 50 40 C C. D 70 140 G H b. What is the required workstation cycle time meet the desired output rate? (Round your answer to the nearest whole number.) Workstation cycle time seconds per unit c. Balance...
Stanford Rosenberg Computing wants to establish an
assembly line for producing a new product, the Personal Digital
Assistant (PDA). The tasks, task times, and immediate predeces-
sors for the tasks are as follows:
Rosenberg’s goal is to produce 200 PDAs per hour.
a) What is the cycle time?
b) What is the theoretical minimum for the number of work-
stations that Rosenberg can achieve in this assembly line?
c. Draw a diagram of the production process.d. With the diagram that...
Stanford Rosenberg Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows: Task Immediate Predecessor A B с D E Time (sec) 12 14 8 5 18 A A B,C D Rosenberg's goal is to produce 180 PDAs per hour. a) The cycle time for the production of a PDA = 20.57 seconds (round your response to two decimal places)....
The operations manager of an instruments company is balancing an
assembly line. The company needs to build 96 instruments per
24-hour day. The assembly line activities are:
a. Draw the precedence diagram.
b. If the daily (24-hour) production rate is 96 units, what is
the greatest possible cycle time?
c. If the cycle time after allowances is given as 10 minutes,
what is the daily (24-hour) production rate?
d. With a 10-minute cycle time, what is the theoretical minimum
number...
Problem 2: Workstation Assignment (8 points) A product has a takt time of 70 seconds and the following precedence diagram. Task A 20 sec Task B 40 sec Task E 60 sec Task G 50 sec Task C 40 sec Task D 10 sec Task F 20 sec a) Assign tasks to workstations using the most following tasks" heuristic rule to break any ties. Show which tasks are assigned to each workstation (4 points) b) Assign tasks to workstations using...
Problem 2: Workstation Assignment (8 points) A product has a takt time of 70 seconds and the following precedence diagram. Task A 20 sec Task B 40 sec Task E 60 sec Task G 50 sec Task C 40 sec Task D 10 sec Task F 20 sec a) Assign tasks to workstations using the "most following tasks" heuristic rule to break any ties. Show which tasks are assigned to each workstation (4 points). b) Assign tasks to workstations using...
1. Balance delay" is another name for the percentage of idle time in a product layout. True False 2. The percentage of idle time in an assembly line is called cycle time. True False 3. For a production line, daily capacity can be determined by dividing the daily operating time by the line's cycle time. True False 4. Heuristic approaches (e.g. LOT, RPW) to line balancing are the only approach that will guarantee an optimal solution. True False 5. Cycle...
Francis Johnson's plant needs to design an efficient assembly line to make a new product. The assembly line needs to produce 12 units per hour, and there is room for only five workstations. The tasks and the order in which they must be performed are shown in the following table. Tasks cannot be split, and it would be too expensive to duplicate any task. TASK TIME IMMEDIATE TASK (MINUTES) PREDECESSOR 2.5 2.0 2.0 3.0 3.0 3.0 3.0 A,B, C b....