Question

Assembly Line Balancing

Stanford Rosenberg Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predeces- sors for the tasks are as follows:

Screen Shot 2021-07-28 at 19.30.49.png

Rosenberg’s goal is to produce 200 PDAs per hour.

  1. a)  What is the cycle time?

  2. b)  What is the theoretical minimum for the number of work-

    stations that Rosenberg can achieve in this assembly line?

  3. c. Draw a diagram of the production process.

  4. d. With the diagram that you have described above, can the production process run properly according to the plan? Explain the process of each workstation that you have created!.


0 0
Add a comment Improve this question Transcribed image text
Request Professional Answer

Request Answer!

We need at least 8 more requests to produce the answer.

2 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the answer will be notified once they are available.
Know the answer?
Add Answer to:
Assembly Line Balancing
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Stanford Rosenberg Computing wants to establish an assembly line for producing a new product, the Personal...

    Stanford Rosenberg Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows: Task Immediate Predecessor A B с D E Time (sec) 12 14 8 5 18 A A B,C D Rosenberg's goal is to produce 180 PDAs per hour. a) The cycle time for the production of a PDA = 20.57 seconds (round your response to two decimal places)....

  • a) The cycle time for the production of a PDA = ____ seconds. b) The theoretical...

    a) The cycle time for the production of a PDA = ____ seconds. b) The theoretical minimum number of workstations that Rosenburg can achieve in this assembly line = ____. c) For one to assign the tasks to the actual workstations and be able to use the "theoretical minimum" number, the activity assignment should be: ??? d) Were you able to assign all the tasks to the theoretical minimum number of workstations? Yes or No. Stanford Rosenberg Computing wants to...

  • em 9.14 Question Help 3 per Sue Hains Appliances wants to establish an assembly line to...

    em 9.14 Question Help 3 per Sue Hains Appliances wants to establish an assembly line to manufacture its new product, the Micro Popcom Popper. The goal is to produce five poppers per hour The tasks, task times, and immediate predecessors for producing one Micro Popcorn Popper are as follows: estions: 3 Task tion 1 (0/1) А Performance Time Task Must Follow (mins Task Usted Below 10 12 А B 11 B,C 7 С 5 DE B D E F a)...

  • Question 1- Assembly Line Balancing A ball-bearing assembly firm wants to set up an assembly line...

    Question 1- Assembly Line Balancing A ball-bearing assembly firm wants to set up an assembly line that must have an output of 60 units per hour. The work elements, task times and their precedence relationships are shown in Table 1: Table 1 Work Element Time (sec.) Immediate Predecessor(s) A 40 NONE B 30 A C 50 A D 40 B E 6 B F 25 C G 15 C H 20 D, E I 18 F, G J 30 H,...

  • The operations manager of an instruments company is balancing an assembly line. The company needs to...

    The operations manager of an instruments company is balancing an assembly line. The company needs to build 96 instruments per 24-hour day. The assembly line activities are: a. Draw the precedence diagram. b. If the daily (24-hour) production rate is 96 units, what is the greatest possible cycle time? c. If the cycle time after allowances is given as 10 minutes, what is the daily (24-hour) production rate? d. With a 10-minute cycle time, what is the theoretical minimum number...

  • The desired daily output for an assembly line is 540 units. This assembly line will operate...

    The desired daily output for an assembly line is 540 units. This assembly line will operate 729 minutes per day. The following table contains information on this product's task times and precedence relationships: TASK TASK TIME (SECONDS) IMMEDIATE PREDECESSOR A 30 — B 28 A C 18 B D 69 B E 34 A F 36 E G 42 C, D H 24 F, G b. What is the workstation cycle time? Cycle time seconds c. Balance this line using...

  • EXAMPLE 8.2: Assembly-Line Balancing The Model J Wagon is to be assembled on a conveyor belt....

    EXAMPLE 8.2: Assembly-Line Balancing The Model J Wagon is to be assembled on a conveyor belt. Five hundred wagons are required per day. Production time per day is 420 minutes, and the assembly steps and times for the wagon are given in Exhibit 8.9A. Assignment: Find the balance that minimizes the number of workstations, subject to cycle time and precedence constraints SOLUTION I. Draw a precedence diagram. Exhibit 8.9B illustrates the sequential relationships identi- fied in Exhibit 8.9A. (The length...

  • Agent Smith, operations manager at the Matrix franchise, faces assembly line balancing problems. He has been...

    Agent Smith, operations manager at the Matrix franchise, faces assembly line balancing problems. He has been told that the firm needs to assemble 1400 agents per day. There are 420 minutes of productive time in each working day. The assembly line activities are given below: Task Time (seconds) Predecessor A 13 - B 4 A C 10 B D 10 - E 6 D F 12 E G 5 E H 6 F, G I 7 H J 5 H...

  • Francis Johnson's plant needs to design an efficient assembly line to make a new product. The...

    Francis Johnson's plant needs to design an efficient assembly line to make a new product. The assembly line needs to produce 12 units per hour, and there is room for only five workstations. The tasks and the order in which they must be performed are shown in the following table. Tasks cannot be split, and it would be too expensive to duplicate any task. TASK TIME IMMEDIATE TASK (MINUTES) PREDECESSOR 2.5 2.0 2.0 3.0 3.0 3.0 3.0 A,B, C b....

  • This problem is similar to Alt-Cat 8.2 and 8.3. An assembly line is to be designed...

    This problem is similar to Alt-Cat 8.2 and 8.3. An assembly line is to be designed to operate 9.5 hours per day and supply a steady demand of 450 units per day. Here are the tasks and their performance times: PERFORMANCE PRECEDING TASK PERFORMANCE TIME (SECONDS) 25 30 15 10 40 20 PRECEDING TASK TASKS TIME (SECONDS) TASK 56 40 38 15 39 20 h,i j, k b. What is the workstation cycle time? Hint: draw the diagram first. tion...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT