The following information is available for Baxter Manufacturing for April:
Actual machine hours | 860 | ||
Standard machine hours allowed | 940 | ||
Denominator activity (machine hours) | 1,015 | ||
Actual fixed overhead costs | $ | 4,200 | |
Budgeted fixed overhead costs | $ | 5,075 | |
Predetermined overhead rate ($1 variable + $5 fixed) | $ | 6 | |
What is the production volume variance for April?
Multiple Choice
$215.
$375.
$400.
$480.
Production Volume variance =
(budgeted hours - Actual hours worked) * budgeted overhead rate per hour
= (940 hours - 860 hours) * $6 per unit
= $480
Option 'D' is correct
The following information is available for Baxter Manufacturing for April: Actual machine hours 860 Standard machine...
The following information is available for Baxter Manufacturing for April: Actual machine hours Standard machine hours allowed Denominator activity (machine hours) Actual fixed overhead costs 1,030 1,090 1,850 $7,600 $7, 400 %24 Budgeted fixed overhead costs Predetermined overhead rate ($1 variable + $4 fixed) Is the fixed overhead price (spending) variance for April favorable or unfavorable? Multiple Choice Unfavorable Favorable < Prev 23 of 34 Next >
The following information is available for Baxter Manufacturing for April: Actual machine hours 850 Standard machine hours allowed 920 Denominator activity (machine hours) 1,060 Actual fixed overhead costs $ 4,000 Budgeted fixed overhead costs $ 4,240 Predetermined overhead rate ($1 variable + $4 fixed) $ 5 What is the fixed overhead price (spending) variance for April? Multiple Choice $350 $280 $560 $240
Actual machine hours Standard machine hours allowed Denominator activity (machine hours) Actual foxed overhead costs Budgeted foed overhead costs Predetermined overhead rate ($i variable - $5 fixed 1075 4.800 What is the fixed overhead spending (budget, variance? $575 $575 $420 O $350
Actual machine hours Standard machine hours allowed Denominator activity (machine hours) Actual foxed overhead costs Budgeted foed overhead costs Predetermined overhead rate ($i variable - $5 fixed 1075 4.800 What is the fixed overhead spending (budget, variance? $575 $575 $420 O $350
1,020 Actual machine hours Standard machine hours allowed Denominator activity machine hours) Actual fixed overhead costs Budgeted faxed overhead costs Predetermined overhead rate ($2 variable 3.000 4080 $4 foed What is the production volume variance? $180 $440 $390 5260
Actual machine hours 1,160 Standard machine hours allowed 1,310 Denominator activity (machine hours) 1,450 Actual fixed overhead costs $ 16,560 Budgeted fixed overhead costs $ 17,400 Predetermined overhead rate ($2 variable + $12 fixed) $ 14 What is the fixed overhead spending (price) variance? A. $840 favorable. B. $580 favorable. C. $280 favorable. D. $300 favorable.
tual mochine hours Standard mochine hours allowed Denominator activity (machine hours) Actual fixed overhead costs Budgeted fixed overhend costs Predetermined overhead rate ($2 variable $8 fixed 50 8,750 10 What is the fixed overhead production volume variance? $450 favorable $1.840 unfavorable O $220 favorable O $450 unfavorable O $880 favorable $1,840 favorable. some other amount favorable some other amount unfavorable O $220 unfavorable O $880 unfavorable
The following information is available for the Danske Company: Denominator hours for May 21,500 Actual hours worked during May 19,200 Standard hours allowed for May 14,600 Flexible budget fixed overhead cost $ 64,500 Actual fixed overhead costs for May $ 68,800 Danske Company had total underapplied overhead of $21,500. Additional information is as follows: Variable Overhead: Applied based on standard direct labor hours allowed $ 55,000 Budgeted based on standard direct labor hours 44,500 Fixed Overhead: Applied based on standard...
Asper Corporation has provided the following data for February. Denominator level of activity 9,300 machine-hours Budgeted fixed manufacturing overhead costs $ 284,020 Fixed component of the predetermined overhead rate $ 36.20 per machine-hour Actual level of activity 9,500 machine-hours Standard machine-hours allowed for the actual output 9,800 machine-hours Actual fixed manufacturing overhead costs $ 275,960 The budget variance for February is:
Asper Corporation has provided the following data for February. Denominator level of activity 9,700 machine-hours Budgeted fixed manufacturing overhead costs $ 288,420 Fixed component of the predetermined overhead rate $ 36.60 per machine-hour Actual level of activity 9,900 machine-hours Standard machine-hours allowed for the actual output 10,200 machine-hours Actual fixed manufacturing overhead costs $ 279,960 The budget variance for February is: