Solution:
Budgeted indirect cost rate: [Budgeted indirect costs (assembly support) / Budgeted direct labor hours] = [5,100,000 / 150,000 hours] = $34 per direct labor hour
Actual indirect cost rate: [Actual indirect costs (assembly support) / Actual direct labor hours] = [5,355,000 / 153,000 hours] = $35 per direct labor hour
Normal costing |
Steel Wheels |
Magic Wheels |
Direct costs |
||
Direct materials |
78,290 |
94,650 |
Direct labor |
25,445 |
32,752 |
103,735 |
127,402 |
|
Indirect costs |
||
Manufacturing support ($34*840; $34*960) |
28,560 |
32,640 |
Total costs |
132,295 |
160,242 |
Actual costing |
Steel Wheels |
Magic Wheels |
Direct costs |
||
Direct materials |
78,290 |
94,650 |
Direct labor |
25,445 |
32,752 |
103,735 |
127,402 |
|
Indirect costs |
||
Manufacturing support ($35*840; $35*960) |
29,400 |
33,600 |
Total costs |
133,135 |
161,002 |
As per policy we have to answer first question
fun toys use a job-costing system II. Calculation and Analysis (42 points in total) 41. Fun...
The Lowell Company uses a normal job-costing system at its Minneapolis plant. The plant has a machining department and an assembly department. Its job-costing system has two direct-cost categories (direct materials and direct manufacturing labor) and two manufacturing overhead cost pools (the machining department overhead, allocated to jobs based on actual machine-hours, and the assembly department overhead, allocated to jobs based on actual direct manufacturing labor costs). The 2017 budget for the plant is as follows: E (Click the icon...
Question 2(lob casting accounting for Marks) anufacturing overhead) 125 The Matthew Company uses a normal job-costing system at its Minneapolis plant. The plant has a machining department and an assembly department. Its job- costing system has two direct-cost categories (direct materials and direct manufacturing labor) and two manufacturing overhead cost pools (the machining department overhead, allocated to jobs based on actual machine hours, and the assembly department overhead, allocated to jobs based on actual direct manufacturing labor costs). The 2017...
Andrews Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Andrews budgets 2017 assembly-support costs to be $ 8,000,000 and 2017 direct labor-hours to be 160,000 . At the end of 2017 , Andrews is comparing the costs of several jobs that were started and completed in 2017 .Direct materials and direct...
Job costing, normal and actual costing. Atkinson Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Atkinson budgets 2017 assembly-support costs to be $ 8,800,000 and 2017 direct labor-hours to be 220,000.At the end of 2017, Atkinson is comparing the costs of several jobs that were started and completed in 2017 .Laguna...
Question 2 (Job costing, accounting for manufacturing overhead rates) 25 Marks) The Matthew Company uses a normal job-costing system at its Minneapolis plant. The plant has a machining department and an assembly department. Its job- costing system has two direct-cost categories (direct materials and direct manufacturing labor) and two manufacturing overhead cost pools (the machining department overhead, allocated to jobs based on actual machine-hours, and the assembly department overhead, allocated to jobs based on actual direct manufacturing labor costs). The...
The Lowell Company uses a normal job-costing system at its Minneapolis plant. The plant has a machining department and an assembly department. Its job-costing system has two direct-cost categories (direct materials and direct manufacturing labor, and two manufacturing overhead cost pools (the machining department overhead allocated to jobs based on actual machine-hours, and the assembly department overhead, allocated to jobs based on actual direct manufacturing labor costs). The 2017 budget for the plant is as follows: (Click the icon to...
E4-23 (similar to) Question Help Attleboro Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Attleboro budgets 2017 assembly-support costs to be $8,600,000 and 2017 direct labor-hours to be 215,000. At the end of 2017, Attleboro is comparing the costs of several jobs that were started and completed in 2017. (Click the...
4-25 Job cesting, accounting for manufacturing overhead, budgeted rates. The Matthew Company uses a normal job-costing system at its Minneapolis plant. The plant has a machining department and an assem- bly department. Its job-costing system has two direct-cost categories (direct materials and direct manufac- turing labor) and two manufacturing overhead cost pools (the machining department overhead, allocated to jobs based on actual machine-hours, and the assembly department overhead, allocated to jobs based on actual direct manufacturing labor costs). The 2017...
In a job-order costing system that is based on machine-hours, which of the following formulas is correct? A) Predetermined overhead rate = Actual manufacturing overhead ÷ Actual machine-hours B) Predetermined overhead rate = Actual manufacturing overhead ÷ Estimated machine-hours C) Predetermined overhead rate = Estimated manufacturing overhead ÷ Estimated machine-hours D) Predetermined overhead rate = Estimated manufacturing overhead ÷ Actual machine-hours 41. Which of the following statements about using a plantwide overhead rate based on direct labor is correct? A)...
need help with requirements 4-9 Southwick Company uses normal costing in its job-costing system. Partially completed T-accounts and additional information for Southwick for 2017 are as follow (Click the icon to view the T-accounts ) (Click the icon to view the additional information) Read the requirements Requirement 1. What was the amount of direct materials issued to production during 2017? Direct materials issued to production during 2017 was $ 237,000 Requirement 2. What was the amount of manufacturing overhead allocated...