Hello,
Can you please help me with this problem and give an explanation for each required tab (1-3)? Thank you.
Statement showing computation of Gross Profit recognizze over time assuming percebtage of completion method | |||||
Percentages of completion | |||||
Choose numerator | ÷ | Choose denominator | = | % complete to date | |
Actual costs to date | Estimated total costs | ||||
2021 | $90 | ÷ | $250 | = | 36.00% |
(90+160) | |||||
2022 | $160 | ÷ | $200 | = | 80.00% |
(90+70) | (160+40) | ||||
2023 | 100.00% | ||||
2021 | |||||
To date (A) | Recognized in prior years (B) | Recognized in 2018 (A-B) | |||
Construction revenue | $119 | $0 | $119 | ||
(330X36%) | |||||
Less: Construction expense | $90 | $0 | $90 | ||
Gross profit (loss) | $29 | $0 | $29 | ||
2022 | |||||
To date (A) | Recognized in prior years (B) | Recognized in 2019 (A-B) | |||
Construction revenue | $264 | $119 | $145 | ||
(330X80%) | Prevoius Year | ||||
Less: Construction expense | $160 | $90 | $70 | ||
(90+70) | Prevoius Year | ||||
Gross profit (loss) | $104 | $29 | $75 | ||
2023 | |||||
To date (A) | Recognized in prior years (B) | Recognized in 2020 (A-B) | |||
Construction revenue | $330 | $264 | $66 | ||
Contract Value | |||||
Less: Construction expense | $205 | $160 | $45 | ||
(90+70+45) | Prevoius Year) | ||||
Gross profit (loss) | $125 | $104 | $21 |
2. Statement showing revenue and gross profit assuming this project does not qualify for revenue recognition over time. ( $ in Million) | ||||
Year | Revenue recognized | Gross Profit (Loss) recognized | ||
2021 | $0 | $0 | ||
2022 | $0 | $0 | ||
2023 | $330 | $125 | ||
(330-205) |
Part-3 : Computation of Revenue and gross profit or loss to be recognized in 2022 (using the percentage of completion ) | |||||
Percentages of completion | |||||
Choose numerator | ÷ | Choose denominator | = | % complete to date | |
Actual costs to date | Estimated total costs | ||||
2022 | $160 | ÷ | $320 | = | 50.00% |
(90+70) | (90+70+160) | ||||
2022 | |||||
To date | Recognized in prior years | Recognized in 2019 | |||
Construction revenue | $165 | $119 | $46 | ||
(330*50%) | |||||
Less:Construction expense | $160 | $90 | $70 | ||
(90+70) | |||||
Gross profit (loss) | $5 | $29 | ($24) |
Hello, Can you please help me with this problem and give an explanation for each required...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $310 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows $ in millions): 2021 $ 70 2022 $60 30 2023 $30 Costs incurred during the year Estimated costs to complete as of December...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $400 million. The expected completion date is April 1, 2023. just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 2021 2022 2023 $ 60 $130 $55...
Exercise 6-20 (Algo) Long-term contract; revenue recognition over time vs. upon project completion [LO6-9] On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $390 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $220 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 2021 2022 2023 $ 40 $80 $50...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $370 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 70 $ 110 $ 80 Estimated costs to complete as of...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $310 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 $ 70 130 Costs incurred during the year Estimated costs to complete as of December 31 2022 $60 30...
Hello, Can you please help me with this problem and give an explanation for the required tabs (1,2 and 3)? Thank you Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $5,140,000. Curtiss concludes that the contract does not...
On June 15, 2021. Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington D.C. for $350 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows (5 in millions): 2021 $ 3e 170 Costs incurred during the year Estimated costs to complete as of December 31 2022 $142 0...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $320 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 80 $ 40 $ 90 Estimated costs to complete as of...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $320 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 80 $ 40 $ 90 Estimated costs to complete as of...